1.
The best point to do focus group testing is with the
a)
concept
b)
prototype
c)
beta
d)
gold master
2.
The total of estimated hours for each task times your hourly billing rate is presented in
a)
budget
b)
milestones
c)
proposal
d)
grant chart
3.
___________ depict all the tasks along a timeline
a)
Gantt charts
b)
Milestones
c)
Proposal
d)
Budget
4.
A program that has not yet been introduced to the public but is being released to a select few to test is happened in
a)
alpha testing
b)
beta testing
c)
gold master
d)
release
5.
A little extra padding to cover the inevitable unexpected costs, usually around 10- 15% is a
a)
contingencies budget
b)
extra budget
c)
GST
d)
emergency budge
6.
Detailed documents from large corporations that are "outsourcing" their multimedia development work is listed in
a)
request for proposal
b)
proposal
c)
planning file
d)
budget
7.
The building blocks of project management are
a)
budgets
b)
tasks
c)
proposals
d)
milestones
8.
The end of each phase of the development of a multimedia project is a natural place to set __________.
a)
prerequisites
b)
scopes
c)
contingencies
d)
milestones
9.
According to the planning and costing stages, three elements can vary in project estimates. What are they?
a)
Computers, climate,
and pressure
b)
Time, money, and
people
c)
Permissions,
workflow, and data
d)
Age, class, and
domain
10.
The general rule of thumb when working with computers and new technology under a deadline is that everything will:
a)
require resources
that exceed the budget
b)
go according to plan
c)
take longer to do
than you think it will
d)
be manageable by the
production team
11.
If the client changes his or her mind later in the process, any revisions of the previously approved materials would require a __________, meaning that the client agrees to pay the additional costs for making edits.
a)
CMP
b)
RFP
c)
sign-off
d)
change order
12.
What is the typical amount you should add to the total cost of your project to cover inevitable unexpected costs?
a)
There should be no
unexpected costs.
b)
Five to ten percent
c)
Ten to fifteen percent
d)
Twenty to twenty-five
percent
13.
The purpose of any __________ is to test the initial implementation of your idea and improve upon it based on test results.
a)
executive summary
b)
proposal
c)
prototype
d)
creative strategy
14.
The proper time to develop a revised and detailed project plan for the client and finalize your budget and payment schedule for the continuation of the project is:
a)
at the end of the
pilot phase
b)
at the end of beta development
c)
before developing the
prototype
d)
during pretesting
15.
A series of graphics that outline the visual details of a multimedia project is called:
a)
a storyboard
b)
a pictogram
c)
an icon
d)
a composite
16.
Which of the four navigational structures allows users to freely navigate through the content of the project, unbound by predetermined routes?
a)
Hierarchical
b)
Linear
c)
Nonlinear
d)
Composite
17.
According to the text, which of the following statements describes a successful graphic approach?
a)
Using simple screens with lots of white space
b)
Creating background images with lots of color
c)
Applying a variety of decorative pattern borders
d)
Employing at least five different fonts
18.
When using sound elements in your multimedia project, which of the following statements is not true?
a)
Always provide a toggle switch to disable the sound.
b)
Choose music that fits the atmosphere you wish to create.
c)
Use as many special effects as you can.
d)
Always test a project with potential users.
19.
Before you begin developing any multimedia project, you should not:
a)
Develop
a system for communication between you, the client, and the team.
b)
Organize a method for tracking the receipt of
the material.
c)
Establish a management structure with
milestones.
d)
Accept unlimited feedback and modifications.
20.
____ are often the first working drafts of your project, typically for internal circulation only, and can have problems or be incomplete.
a)
ASCII text files
b)
Alpha releases
c)
Stampers
d)
Beta releases
21.
When testing your product, you should:
a)
Concentrate on software configuration
b)
Focus on making the product work perfectly on one system
c)
Spend time configuring and testing various platforms
d)
Examine the bytes of data in the sector