180501 SRO Static #2

Total questions: 15

Worksheet time: 1hrs 9mins

Name
Class
Date
1.
Which safety system is not meeting its safety function? 
a)
LPSI
b)
EFW
c)
HPSI
d)
EDGs
2.
What action should have been taken in SPTA that was not performed?
a)
Align for emergency boration
b)
Manually trip the turbine
c)
Start the AACG
d)
Lockout an EDG
3.
What tripped the reactor? 
a)
RPS Manual
b)
RPS Auto due to high RCS pressure
c)
DSS Auto due to high RCS pressure
d)
DSS Manual
4.
Why was the plant tripped?
a)
SGTR >44 gpm
b)
2 stuck CEA’s
c)
LOCA >44 gpm
d)
Turbine vibes high
5.
What is the highest safety function that is not currently being met? 
a)
Reactivity
b)
MVAC
c)
Inventory Control
d)
Pressure Control
6.
What action should be taken to restore the highest safety function not met? 
a)
 Lockout 2K4B
b)
Verify PZR level 10-80%
c)
Align emergency boration
d)
Trip one RCP in each loop
7.
What procedure should the CRS diagnose following SPTA? 
a)
 SGTR
b)
Functional Recovery
c)
ESD
d)
LOCA
8.
What Safety Functions will not be satisfied when SPTAs are complete? 
a)
  Reactivity, Inventory control, and RCS heat removal temperature
b)
Inventory control, core heat removal, and RCS heat removal
c)
Reactivity, inventory control, and pressure control
d)
Inventory control, pressure control, and RCS heat removal
9.
What COPD-032 action should be performed for a safety component that has failed? 
a)
 Have the NLO’s check pump and breaker, then update and start 2P7B 
b)
Update and start 2P7B
c)
Have the NLO’s check pump and breaker, then update and start 2P89A
d)
Update and start 2P89A
10.
What system is currently inoperable for tech specs? 
a)
U1 CREACS only
b)
U2 CREACS only
c)
U1 and U2 CREACS
d)
CREACS is Operable for U1 and U2
11.
What is the next EOP major recovery strategy that should be implemented? 
a)
Lower RCS pressure to <1600#
b)
Commence RCS cooldown
c)
Isolate ‘A’ SG using Att. 10
d)
Maintain post-blowdown temperature and pressure
12.
What action should be taken regarding RCPs? 
a)
 Secure A and C RCPs
b)
Secure B and D RCPs
c)

Secure all RCPs

d)

Leave all RCPs running

13.
How will post-cooldown control be performed? 
a)
 Throttle 2CV-1001 upstream ADV
b)
Throttle 2CV-1002 upstream MOV
c)
Throttle 2CV-1051 upstream ADV
d)
Throttle 2CV-1052 upstream MOV
14.
Assuming no operator action, what system currently has U2 in TS 3.0.3 (SRO only)? 
a)
3.1.1.1, Shutdown Margin
b)
3.3.1.1, RPS
c)
3.5.3, HPSI
d)
3.7.1.2, EFW
15.
What EAL should be declared (SRO only)? 
a)
 NUE due to FU1
b)
NUE due to SU7
c)
Alert due to FA1
d)
SAE due to FS1