PMP - Time

Total questions: 10

Worksheet time: 9mins

Name
Class
Date
1.
You are managing a construction project for a new city water system. The contract requires you to use special titanium piping equipment that is guaranteed not to corrode. The titanium pipe must be resting in the ground a total of 10 days before connectors can be installed. In this example, the 10-day period is defined as—
a)
Lag 
b)
Lead 
c)
Float 
d)
Slack
2.
Of the following tools and techniques, which one is NOT used for schedule control? 
a)
Fast tracking 
b)
What-if scenario analysis 
c)
Three-point estimates 
d)
Adjusting leads and lags
3.
If, when developing your project schedule, you want to define a distribution of probable results for each  schedule activity and use that distribution to calculate another distribution of probable results for the total project, the most common technique to use is—
a)
PERT
b)
Monte Carlo Analysis
c)
Linear programming
d)
Concurrent engineering
4.
Your lead engineer estimates that a work package will most likely require 50 weeks to complete. It could be completed in 40 weeks if all goes well, but it could take 180 weeks in the worst case. What is the PERT estimate for the expected duration of the work package?
a)
45 weeks
b)
70 weeks
c)
90 weeks
d)
140 weeks
5.
Your customer wants the project to be completed six months earlier than planned. You believe you can meet this target by overlapping project activities. The approach you plan to use is known as—
a)
Critical chain 
b)
 Fast tracking 
c)
 Leveling 
d)
Crashing
6.
Activity A has a duration of three days and begins on the morning of Monday the 4th. The successor activity, B, has a finish-to-start relationship with A. The finish-to-start relationship has three days of lag, and activity B has a duration of four days. Sunday is a nonworkday. Such data can help to determine—
a)
The total duration of both activities is 8 days
b)
Calendar time between the start of A to the finish of B is 11 days
c)
The finish date of B is Wednesday the 13th
d)
Calendar time between the start of A to the finish of B is 14 days
7.
 “I cannot test the software until I code the software.” This expression describes which of the following dependencies?
a)
Discretionary
b)
Rational
c)
Preferential
d)
Mandatory or hard
8.
You are remodeling your kitchen and decide to prepare a network diagram for this project. Your appliances must be purchased and available for installation by the time the cabinets are completed. In this example, these relationships are—
a)
Start-to-finish
b)
Finish-to-start
c)
Start-to-start
d)
 Finish-to-finish
9.
Decomposition is a technique used for both WBS development and activity definition. Which following statement best describes the role decomposition plays in activity definition as compared to creating the WBS?
a)
Final output is described in terms of work packages in the WBS
b)
Final output is described as deliverables or tangible items
c)
Final output is described as schedule activities
d)
Decomposition is used the same way in scope definition and activity definition
10.
When sequencing project activities in the schedule, all the following are true EXCEPT—
a)
 There may be scheduled dates for specific milestones
b)
Every activity is connected to at least one predecessor and at least one successor
c)
Lead or lag time may be required
d)
Necessary sequencing of events may be described by the activity attributes