PMP PROJECT PROCUREMENT MANAGEMENT REV.2

Total questions: 16

Worksheet time: 16mins

Name
Class
Date
1.

196. All of the following are inputs to the Plan Procurement Management process

EXCEPT:

a)

Risk register.

b)

Stakeholder register.

c)

Procurement strategy.

d)

Enterprise environmental factors.

2.

197. Generally, a bid differs from a proposal in that the term:

a)

Bid is used when the seller selection decision will be based on price.

b)

Bid is used when technical capability or technical approach are paramount.

c)

Proposal is used when the selection decision will be based on price.

d)

Proposal is used when the project time frame is limited.

3.

198. The buyer structures procurement documents, which include all of the following EXCEPT:

a)

Procurement statement of work.

b)

Bid documents

c)

Source selection criteria and independent cost estimates.

d)

Control procurement documents.

4.

199. Approved change requests can generally include all of the following EXCEPT:

a)

Modifications to the terms and conditions of the contract.

b)

Modification to pricing.

c)

Seller invoices.

d)

Modification to descriptions of the products, services, or results to be provided.

5.

200. Which of the following is FALSE about advertising as one of the tools and techniques of the Conduct Procurement's process?

a)

Some government jurisdictions require public advertising of certain types of procurement items.

b)

Advertisements in general circulation publications and using online resources can cause public pressure, resulting in bid disputes.

c)

Advertising can often be used to expand existing lists of potential sellers.

d)

Advertisements can be placed in general circulation publications such as selected newspapers or in specialty trade publications.

6.

201. The buyer, usually through its authorized procurement administrator, provides the seller with ______________as an output of the Control Procurement process.

a)

Formal written notice that the contract has been completed

b)

Letters of commendation to all project team members

c)

Informal notice of acceptance of the deliverables

d)

A copy of the internal notice of completion provided to senior management

7.

202. In which type of contracts do buyers need to precisely specify the product or services being procured?

a)

Cost plus award fee contracts.

b)

Fixed-price contracts.

c)

Cost-reimbursable contracts.

d)

Partnership contracts

8.

203. Which of the following is one of the terms used to describe contested changes and potential constructive changes where the buyer and seller cannot reach an agreement on compensation for the change or cannot agree that a change has occurred?

a)

Forcing.

b)

Mediation

c)

Complaints.

d)

Claims

9.

204. Constructive changes are:

a)

Postponed as long as possible to protect the budget.

b)

Viewed as negative, quantified, and tabulated.

c)

Uniquely identified and documented by project correspondence.

d)

Submitted for bids to the relevant vendor list.

10.

205. All legal contractual relationships generally fall into one of the following broad categories EXCEPT:

a)

Request for proposal (RFP).

b)

Fixed-price contracts.

c)

Cost-reimbursable contracts.

d)

Time and material contracts (T&M).

11.

206. All of the following are true about the statement of work (SOW) for a procurement EXCEPT:

a)

It describes the procurement item in sufficient detail to allow prospective sellers to determine if they are capable of providing the products, services, or results.

b)

It should be as ambiguous, incomplete, and wordy as possible to allow for future negotiations.

c)

It can include specifications, quantity desired, quality levels, performance data, period of performance, work location,and other requirements.

d)

It can be revised and refined as required as it moves through the procurement process until incorporated into a signed agreement.

12.

207. Source selection criteria are developed and used to rate or score seller proposals. These criteria generally have all of the following characteristics EXCEPT:

a)

They are often included as a part of the procurement documents.

b)

They can be objective or subjective

c)

They may be limited to only the purchase price if the procurement item is readily available from a number of acceptable sellers.

d)

They generally require specification of the name of the transportation organization responsible for delivery of procured products.

13.

208. All of the following are tools and techniques of the Conduct Procurements process

EXCEPT:

a)

lnterpersonal and team skills

b)

Bidder conferences

c)

Expert judgment

d)

Proposal evaluation techniques

14.

209. Cost plus fixed-fee contracts (CPFF) have all of the following characteristics EXCEPT:

a)

Seller is reimbursed for all allowable costs for performing the contract work.

b)

Seller receives a fixed-fee payment calculated as a percentage of the actual project costs.

c)

Seller receives a fixed-fee payment calculated as a percentage of the initial estimated project costs.

d)

The fee is paid only for completed work and does not change due to seller performance unless the project scope changes.

15.

210. This type of analysis results in a decision as to whether particular work can best be accomplished by the project team or needs to be purchased from outside sources:

a)

Source-selection analysis

b)

Regulations analysis.

c)

Make-or-buy analysis.

d)

Data-gathering analysis.

16.

211. In many projects, negotiation is:

a)

Primarily the concern of contract administration.

b)

A discussion aimed at reaching an agreement.

c)

A direct result of ineffective decision making.

d)

Conducted by senior executives to increase the probability of project success.