Level 3 site carpentry construction planning

Total questions: 10

Worksheet time: 5mins

Name
Class
Date
1.

A benefit of a programme of work is that it keeps a record of materials used

a)

True

b)

False

2.

Critical path analysis is a planning method?

a)

True

b)

False

3.

A disadvantage of a planning system is that minor changes in data can cause major changes in the chart

a)

True

b)

False

c)

Abstain

4.

Energy Performance Certificates shows you

a)

How hot your house is?

b)

How big your house is?

c)

How Efficient your house is?

d)

How expensive your house is?

5.

A good interpretation of what sustainability means is?

a)

Constant flow

b)

Fulfilling our quota

c)

Meeting todays needs without jeopardising the future

d)

Using alternative green methods

6.

which of the following would not be included in sustainable planning and management?

a)

Environmental impact surveys

b)

Waste minimisation

c)

Careful planning design and management

d)

Using more natural open spaces for infrastructure

7.

What does CDM stand for in construction

a)

Construction Damage Management

b)

Contractual Department of maintenance

c)

Construction Design Management

d)

Clinical Data management

e)

Cold Dark Matter

8.

What does SWMP in Construction

a)

Site water management plan

b)

Site waste maintenance plan

c)

Site water maintenance Plan

d)

Site waste management plan

9.

Which of the following is not an information source used in construction?

a)

Variation order

b)

Demograph

c)

Bill of quantities

d)

Gant chart

10.

What is the main difference between an estimate and a quote?

a)

One is subject to change

b)

One is more expensive than the other

c)

One is legal binding

d)

one is supplied by the client