The operation in which the plumb line of a theodolite passes through the ground station mark is called
Setting up
Leveling
Centering
Transiting
The departure of a line is obtained by
Lcosθ
L cos2 θ
L tan θ
L sinθ
The linear misclosure is generally expressed as a fraction of
perimeter of traverse / closing error
perimeter of traverse / bearing
distance / perimeter of traverse
angle / perimeter of traverse
For a closed traverse, which check is more important and essential? Choose two answers.
Σ Latitude = 0
Σ Departure = 0
Σ coordinates = 0
F.B - B.B = 180
If n is the number of sides of a traverse, while traversing clockwise the sum included angles should be
(2n +4) 90°
360°
(2n − 4) 90°
(n − 4)90°
In traversing, the traverse can be
Closed
Open
Closed with central station
Closed or open
Latitude of a line is defined as
Orthographic projection of a survey line on the E-W line
Orthographic projection of a survey line on the reference meridian
None of the above
Bearing of line A to B is 127° and apart by 304.50 meter and . The Latitude of line AB is
71.934
-0.602
243.185
-183.253
A traverse survey work can be classify as 2nd class order when its linear misclosure is 1:6780
TRUE
FALSE
tan−1 error departureerror latitude is the formula to determine angular misclosure
TRUE
FALSE