Cavity Wall Construction

Total questions: 20

Worksheet time: 40mins

Name
Class
Date
1.

What is the collective term given to all work carried out above ground level?

a)

Substructure

b)

Superstructure

c)

Above Datum

d)

Walling

2.

What document is issued in conjunction with a plan or working drawing and provides written information about the work to be carried out?

a)

COSHH statement

b)

Risk assessment

c)

Specification

d)

Time sheet

3.

What would be placed between the two leaves of blockwork in footings before backfilling takes place?

a)

Insulation

b)

Lean mix concrete

c)

Mortar

d)

It is left hollow

4.

Masonry cement should not be used in substructure walling because:

a)

It produces a mortar that is too light in colour

b)

It contains a plasticiser that weakens the mortar

c)

It is too expensive

d)

The curing time is too long

5.

A strip foundation for a 300mm cavity wall is usually excavated to a width of:

a)

450mm

b)

600mm

c)

750mm

d)

900mm

6.

What is the minimum distance a damp proof course should be positioned above ground level?

a)

150mm

b)

300mm

c)

450mm

d)

600mm

7.

The three classifications of damp proof course are:

a)

Flexible, semi-flexible, rigid

b)

Brick, slate, plastic

c)

Flexible, semi-rigid, rigid

d)

horizontal, vertical, diagonal

8.

What is the purpose of a core hole, as shown in the image?

a)

It allows air to ventilate the cavity

b)

It provides access to the concrete floor slab

c)

It allows for the cavity to be cleared of mortar droppings at the end of each day

d)

It is where air bricks will eventually be positioned

9.

What is the minimum distance a tie iron should be bedded in to each leaf of a cavity wall?

a)

25mm

b)

50mm

c)

75mm

d)

100mm

10.

Which of the following statements is correct with regard to tie iron spacings in a cavity wall with a cavity of 100mm?

a)

Tie irons should be spaced 450mm horizontally and 450mm vertically

b)

Tie irons should be spaced 900mm horizontally and 900mm vertically

c)

Tie irons should be spaced 450mm horizontally and 900mm vertically

d)

Tie irons should be spaced 900mm horizontally and 450mm vertically

11.

What is the maximum horizontal distance tie irons should be positioned away from an opening or stopped end?

a)

100mm

b)

150mm

c)

200mm

d)

250mm

12.

At an opening or stopped end, what is the maximum vertical distance ties irons should be spaced apart? (choose two answers)

a)

Every course of blocks

b)

Every two courses of blocks

c)

Every 225mm

d)

Every 450mm

13.

When positioning partial fill insulation, which of the leaves of wall should be built first?

a)

It doesn't matter, you can build either

b)

The brickwork should be built first

c)

The blockwork should be built first

d)

They should be built together

14.

What is the minimum bearing for a metal cavity lintel?

a)

100mm

b)

150mm

c)

200mm

d)

250mm

15.

What is the purpose of a cavity tray?

a)

It prevents rising damp

b)

It increases the thermal insulation qualities of a property

c)

It protects a metal lintel from rusting and subsequently failing

d)

It forces water to the external leaf at point where the cavity is closed / bridged

16.

What is the purpose of the item shown in the sketch?

a)

it allows for moisture to be drained from a cavity

b)

It allows for ventilation of the cavity

c)

It closes of the gaps where dependant scaffold had been fixed

d)

It ensures perp joints are consistent in size

17.

Where should broken bond be positioned?

a)

At one end of a wall

b)

At both ends of a wall

c)

In the middle of a wall

d)

Under a door or opening

18.

Which type of drawing would contain hatchings?

a)

Elevation drawing

b)

Isometric drawing

c)

Detail drawing

d)

Sectional drawing

19.

If a cavity wall without openings was 5m long and 2 metres high, how many bricks, blocks and tie irons would be required?

a)

60 bricks, 6 blocks and 5 tie irons

b)

600 bricks, 60 blocks and 50 tie irons

c)

600 bricks, 100 blocks and 50 tie irons

d)

6000 bricks, 1000 blocks and 500 tie irons

20.

What is the component in the image used for?

a)

It is to insulate underfloor spaces

b)

It is to insulate loft spaces

c)

It is to close of cavities at openings / reveals

d)

It is to close of cavities at wall plate