wayground logo

Free Printable Worksheets

Font size

S
M
L
XL
Worksheets

Chapter 12: Project Completion

Total questions: 10

Worksheet time: 7mins

Name
Class
Date
1.

* old system is shut down and new system initiated,

* quick delivery of new system is critical,

* old system must be replaced ASAP,

* may be appropriate for non mission critical applications,

* places more pressure on the project team.

a)

Parallel

b)

Phased

c)

All of these

d)

Direct Cutover

2.

* modulated; allows for an organized and managed approach,

* problems encountered during early phases can impact the overall implementation schedule,

* but experiences during the initial implementation can help future implementations run smoothly,

* more time but less risky.

a)

Parallel

b)

Phased

c)

All of these

d)

Direct Cutover

3.

* old and new systems run concurrently,

* old system as safety net/backup in case of problems,

* can increase confidence in the new system,

* takes longer and requires more resources than direct (more expensive, less risky),

* places more pressure on the system users.

a)

Parallel

b)

Phased

c)

All of the above

d)

Direct Cutover

4.

Project closure due to resource constraints, misjudged value, needs changes, project starvation

a)

Normal

b)

Premature

c)

Perpetual

d)

Failed

e)

Changed Priority

5.

Cost of project completion outweighs any benefits

a)

Normal

b)

Premature

c)

Perpetual

d)

Failed

e)

Changed Priority

6.

Realities of project closure include:

a)

Bugs still exist

b)

Resources are running out

c)

Documentation becomes unimportant

d)

Promised delivery dates may not be met

7.

Individual Performance Review

a)

Avoid “Why can’t you be more like….?”

b)

Constantly blame the member for the project's condition.

c)

Pick favourites and be biased.

d)

Reviews should provide a consensus on improving performance.

8.

Postmortem Review

a)

Between project manager and stakeholders.

b)

Determine the project’s MOV.

c)

Review the project scope, schedule, budget, and quality objectives.

d)

Review each of the project deliverables.

9.

Project Audit

a)

Generally conducted by the project manager and project team.

b)

Preferably performed by an outside auditor.

c)

Present no fear of accusation from special interests.

d)

Have no or shallow base of project and/or industry experience.

10.

Evaluation of Project MOV

a)

Was the sponsor/customer satisfied?

b)

May sometimes occur weeks or months after the project is complete in order to obtain an objective assessment.

c)

Was the project team satisfied?

d)

Project success is not determined.