Production of shoes requires the completion of nine work elements which are listed below:
Refer to image above.
What is the Cycle Time?
8 minutes
12 minutes
7 minutes
10 minutes
Refer to diagram above, calculate maximum daily capacity for this diagram.
35 units
42 units
55 units
25 units
Calculate the minimum number of workstation for this process. And apply the answer to the diagram.
What is the exact workstation?.
6 workstations
5 workstations
4 work stations
7 workstations
What is the heuristics line for this layout?
A,B - D,F - H,I - G - C,E
C,E - D,F - H,I - G - A,B
A,B- C,E - D,F - H,I - G
A,B - C,E - D,F - G - H,I
Refer to your table, what is the efficiency and idleness percentage?
96.67% , 3.33%
90.00 % , 3.13%
96.60% , 3.00%
91.30% , 3.40%
Refer to the picture, what types of layout is suitable for this picture?
work cell layout
process oriented layout
product oriented layout
retail layout
Which statement below is NOT TRUE?
Consists of different machines brought together to make a product.
It is appropriate for producing one standardized product, usually in large volume.
A design that attempts to maximize total cost by addressing trade off between space and material handling equipment.
An approach that addresses flow, allocate shelf space and responds to customer behavior.
How many types of questions will be ask for this chapter?
3
2
4
1
Is there a different when the question time in minutes or seconds?
Yes
No
Not sure
Why do you need to have a good layout?
Decisions regarding entitlement and aesthetics.
Selecting different material handling to be used.
Identification and understanding of the requirement for information flow.
Identification of the cost moving between the various assembly line.