PRELIMINARY ESTIMATING METHOD

Total questions: 15

Worksheet time: 3mins

Name
Class
Date
1.
Estimating is the process of looking into the future and trying to predict ........ and resource requirements’
a)
project planning
b)
project period
c)
project cost
d)
project circumstances
2.

Early estimate helps define the ......of the project, how big the project can be for the money available, and what quality is possible

a)

affordability

b)

capability

c)

tractability

d)

effort-ability

3.
Constructing a facility in Singapore is very different from constructing one in Perlis. This statement is refer to the project affected.
a)
location
b)
time
c)
cost
d)
labour
4.

An estimate is

a)

a calculation of the quantities of various items of work and the expenses

b)

is journal which is not usable for any project especially expenses of any project

c)

indicating a project will 100% work based on it without any error

5.

Estimation of a project is

a)

a forecast of its probable cost

b)

a forecast of money

6.

The purpose of cost estimating is to......

Choose all the correct answer below.

a)

find the cost of the manufacturing

b)

find the cost of operations involve

c)

assist in setting the price for the project

d)

find the cost irrelevant items

7.

Cost estimating is importance to:-

a)

know the quantities of various materials

b)

decide the proposal cost

c)

matching cost with budget

d)

invite client's quotation

e)

make the meeting interesting

8.

The selection of the method in estimating will depend on....


choose all correct answers

a)

The total and type of cost data available

b)

The experience of Quantity Surveyor

c)

The information and time to prepare the estimate

9.

The preliminary estimating is useful to the following parties EXCEPT

a)

Client

b)

Architect

c)

Contractor

d)

General Labour

10.

The common method use in preliminary estimating. The length and width of building is measured the inside faces of external wall. Choose the correct method of estimating related to the statement.

a)

Superficial area method

b)

Valuation method

c)

Cubic content method

d)

Approximates quantities method

11.

*Have close relationship between the cost of a project and the numbers of functional units

*Need a good experience of quantity surveyor

The above statement are related to

a)

Unit Valuation Method

b)

Floor Area Method

c)

Cubic Content Method

d)

Storey Enclosure Method

12.

The length and width are measured between external faces

of the external wall in superficial area method.


The above statement are related to

a)

Unit Valuation Method

b)

Superficial Area Method

c)

Cubic Content Method

d)

Storey Enclosure Method

13.

By using the cubic content method , find the height of the building in Figure 1

a)

6.50 metre

b)

6.65 metre

c)

6.70 metre

d)

6.75 metre

14.

Referred to floor plan, calculate the total floor area using the superficial area method. Ignore the wall thnickess.

a)

104.00 m2

b)

104.90 m2

c)

105.30 m2

d)

105.55 m2

15.

Estimate the total cost to build a mosque to house a congregation of 1500 individuals.

From a suitable cost data, get the cost/ congregation of a similar mosque that has been updated. Lets us say that the cost is RM 1400.00 / individual

a)

Ringgit Malaysia 21.0 million

b)

Ringgit Malaysia 2.1 million

c)

Ringgit Malaysia 2.11 million

d)

Ringgit Malaysia 2.1 trillion