1.

The critical path is the

a)

Shortest Path

b)

Longest Path

2.

The critical activities have a slack of zero

a)

True

b)

False

3.

The forward pass gives us the Critical Path

a)

True

b)

False

4.

The length of the Critical Path is also the earliest finish of the project

a)

True

b)

False

5.

The critical path has a slack of zero

a)

True

b)

False

6.

Slack means the difference between earliest start and latest finish

a)

True

b)

False