What is best to use to review the requirements of each of the stakeholders?
work breakdown structure
requirements documentation
requirements management plan
requirements traceability matrix
What is needed when meeting with the stakeholders to define and document all the needs for a project?
controlling the scope
creating the WBS
collecting requirements
verifying the scope
When 50% of vote decides what course of action?
majority
dictatorship
plurality
unanimity
What document will outline the methods to create and manage requirements as well as to prioritize requirements?
requirements documentation
requirements management plan
requirements traceability matrix
work breakdown structure
What is used to analyze, document, and manage all the stakeholder requirements for a project?
requirements traceability matrix
requirements documentation
requirements management plan
work breakdown structure
To create a model to gather feedback before finalizing the product or project?
prototype
survey
observation
facilitated workshop
To make a decision and everyone agrees?
plurality
dictatorship
majority
unanimity
What is happening when someone has meeting to determine needs for a project?
controlling the scope
collecting requirements
creating WBS
verifying the scope
Which is a group decision making techniques that can be used?
autocracy majority, plurality, and unanimity
dictatorship, majority, plurality
majority, plurality, and unanimity
dictatorship, majority, plurality, and unanimity
In a project scope statement, the price and how long the project will take would be listed under which section?
project acceptance criteria
project constraints
project deliverables
project exclusions
To track, define, and manage each activity of the project is considering to be?
collecting requirements
creating the WBS
verifying the scope
defining the scope
All information has been collected from shareholders and has bee agreed upon. A list of each item agreed upon would be located where?
project acceptance criteria
project constraints
project deliverables
project exclustions
A must to have within the project. For example, a house built within the city limits must have city water.
project constraints
project deliverables
project exclusions
project acceptance criteria
A stakeholder refuses to allow something to be added to the project scope statement.
project deliverables
project exclusions
project constraints
project acceptance criteria
In a project scope statement, to assume an outdoor project is always going to have good weather and all contractors are going to work well with one another is considered to be?
project assumptions
project acceptance criteria
project constraints
project deliverables
In a project scope statement, all requirements from the stakeholders has been listed and agreed upon. What section would this be under?
project acceptance criteria
project deliverables
project exclusions
project constraints
To break down a project into categories to determine milestones?
defining scope
collecting requirements
verifying scope
creating a WBS
After a project has been broken down into categories, each task in the category can be delegated to another of the team would be considered?
product analysis
group creativity techniques
decomposition
focus group
Which layer would be best when a team is using Work Breakdown Structure (WBS) to complete a home restoration project?
control accounts, planning packages, and work packages
activity, control accounts, planning packages
control accounts, activity packages, and work packages
control accounts, planning packages, and activity packages
A team has used Work breakdown structure (WBS) to subdivide into more manageable tasks and all task has been assigned or hired out. What is the name of the document that describes the cost estimates, quantity requirements, description of work, and contract information?
work breakdown structure
work breakdown structure dictionary
requirements documentation
project scope statement
Once a project scope baseline has been made, it can be used to inform the development of the:
requirements, scope statement, and WBS
scope statement, WBS, and WBS dictionary
requirements, scope statement, and WBS dictionary
WBS and WBS dictionary
Which tool or technique will the project manager use in the process of creating a WBS?
decomposition
estimating
inspection
variance analysis
To determine the process for handling scope change request. Which process is being conducted?
verify scope
collect requirement
control scope
define scope
Which phrase is a project in when the project manager would get a signature at the completion of a phase of a project?
planning
executing
monitoring and controlling
closing
To meet with stakeholders to ensure the scope of products delivered aligns with what was planned for in the scope baseline project? What process is this?
define scope
control scope
collect requirements
verify scope
What technique is used when a project manager examines a product, taste a product, or inspects for product to ensure it meets project scope?
inspection
variance analysis
estimating
decomposition
During what process is work decomposition performed?
verifying scope
collecting requirements
defining scope
creating WBS
A project financial project manager creates a report to income company income statement and balance sheet. A stakeholder reviews statements and signs it. Which process is being conducted?
collecting requirements
controlling the scope
defining the scope
verifying the scope
A call is being made to a company to request work performance information regarding their progress on project so it can be compared to the scope baseline. Which process is this?
define scope
verify scope
control scope
collect requirements