PMI 3.0

Total questions: 29

Worksheet time: 22mins

Name
Class
Date
1.

What is best to use to review the requirements of each of the stakeholders?

a)

work breakdown structure

b)

requirements documentation

c)

requirements management plan

d)

requirements traceability matrix

2.

What is needed when meeting with the stakeholders to define and document all the needs for a project?

a)

controlling the scope

b)

creating the WBS

c)

collecting requirements

d)

verifying the scope

3.

When 50% of vote decides what course of action?

a)

majority

b)

dictatorship

c)

plurality

d)

unanimity

4.

What document will outline the methods to create and manage requirements as well as to prioritize requirements?

a)

requirements documentation

b)

requirements management plan

c)

requirements traceability matrix

d)

work breakdown structure

5.

What is used to analyze, document, and manage all the stakeholder requirements for a project?

a)

requirements traceability matrix

b)

requirements documentation

c)

requirements management plan

d)

work breakdown structure

6.

To create a model to gather feedback before finalizing the product or project?

a)

prototype

b)

survey

c)

observation

d)

facilitated workshop

7.

To make a decision and everyone agrees?

a)

plurality

b)

dictatorship

c)

majority

d)

unanimity

8.

What is happening when someone has meeting to determine needs for a project?

a)

controlling the scope

b)

collecting requirements

c)

creating WBS

d)

verifying the scope

9.

Which is a group decision making techniques that can be used?

a)

autocracy majority, plurality, and unanimity

b)

dictatorship, majority, plurality

c)

majority, plurality, and unanimity

d)

dictatorship, majority, plurality, and unanimity

10.

In a project scope statement, the price and how long the project will take would be listed under which section?

a)

project acceptance criteria

b)

project constraints

c)

project deliverables

d)

project exclusions

11.

To track, define, and manage each activity of the project is considering to be?

a)

collecting requirements

b)

creating the WBS

c)

verifying the scope

d)

defining the scope

12.

All information has been collected from shareholders and has bee agreed upon. A list of each item agreed upon would be located where?

a)

project acceptance criteria

b)

project constraints

c)

project deliverables

d)

project exclustions

13.

A must to have within the project. For example, a house built within the city limits must have city water.

a)

project constraints

b)

project deliverables

c)

project exclusions

d)

project acceptance criteria

14.

A stakeholder refuses to allow something to be added to the project scope statement.

a)

project deliverables

b)

project exclusions

c)

project constraints

d)

project acceptance criteria

15.

In a project scope statement, to assume an outdoor project is always going to have good weather and all contractors are going to work well with one another is considered to be?

a)

project assumptions

b)

project acceptance criteria

c)

project constraints

d)

project deliverables

16.

In a project scope statement, all requirements from the stakeholders has been listed and agreed upon. What section would this be under?

a)

project acceptance criteria

b)

project deliverables

c)

project exclusions

d)

project constraints

17.

To break down a project into categories to determine milestones?

a)

defining scope

b)

collecting requirements

c)

verifying scope

d)

creating a WBS

18.

After a project has been broken down into categories, each task in the category can be delegated to another of the team would be considered?

a)

product analysis

b)

group creativity techniques

c)

decomposition

d)

focus group

19.

Which layer would be best when a team is using Work Breakdown Structure (WBS) to complete a home restoration project?

a)

control accounts, planning packages, and work packages

b)

activity, control accounts, planning packages

c)

control accounts, activity packages, and work packages

d)

control accounts, planning packages, and activity packages

20.

A team has used Work breakdown structure (WBS) to subdivide into more manageable tasks and all task has been assigned or hired out. What is the name of the document that describes the cost estimates, quantity requirements, description of work, and contract information?

a)

work breakdown structure

b)

work breakdown structure dictionary

c)

requirements documentation

d)

project scope statement

21.

Once a project scope baseline has been made, it can be used to inform the development of the:

a)

requirements, scope statement, and WBS

b)

scope statement, WBS, and WBS dictionary

c)

requirements, scope statement, and WBS dictionary

d)

WBS and WBS dictionary

22.

Which tool or technique will the project manager use in the process of creating a WBS?

a)

decomposition

b)

estimating

c)

inspection

d)

variance analysis

23.

To determine the process for handling scope change request. Which process is being conducted?

a)

verify scope

b)

collect requirement

c)

control scope

d)

define scope

24.

Which phrase is a project in when the project manager would get a signature at the completion of a phase of a project?

a)

planning

b)

executing

c)

monitoring and controlling

d)

closing

25.

To meet with stakeholders to ensure the scope of products delivered aligns with what was planned for in the scope baseline project? What process is this?

a)

define scope

b)

control scope

c)

collect requirements

d)

verify scope

26.

What technique is used when a project manager examines a product, taste a product, or inspects for product to ensure it meets project scope?

a)

inspection

b)

variance analysis

c)

estimating

d)

decomposition

27.

During what process is work decomposition performed?

a)

verifying scope

b)

collecting requirements

c)

defining scope

d)

creating WBS

28.

A project financial project manager creates a report to income company income statement and balance sheet. A stakeholder reviews statements and signs it. Which process is being conducted?

a)

collecting requirements

b)

controlling the scope

c)

defining the scope

d)

verifying the scope

29.

A call is being made to a company to request work performance information regarding their progress on project so it can be compared to the scope baseline. Which process is this?

a)

define scope

b)

verify scope

c)

control scope

d)

collect requirements