CONTRACT MANAGEMENT

Total questions: 14

Worksheet time: 7mins

Name
Class
Date
1.

CONSTRUCTION MANAGEMENT SERVICES DOES NOT INCLUDE :

a)

SCHEDULING & COST CONTROL

b)

COST CONSEQUENCES OF DESIGN AND CONSTRUCTION DECISIONS

c)

DESIGN AND CONSTRUCT THE CONSTRUCTION

d)

COORDINATION OF CONSTRUCTION ACTIVITIES

2.

THE ADVANTAGES OF CONSTRUCTION MANAGEMENT EXCEPT :

a)

QUALITY CAN BE ASSURED BY THE HIGH LEVEL OF SUPERVISION BY THE PROJECT MANAGER

b)

SAVE THE COST OF THE OVERALL PROJECT

c)

SUITS COMPLEX PROJECTS WHERE THE DESIGN CAN BE DEVELOPED IN STAGES

d)

AS DESIGN FOR EACH WORK PACKAGE IS COMPETED, WORK CAN BEGIN

3.

THE DISADVANTAGES OF CONTRACT MANAGEMENT ARE :

a)

THE PROJECT WILL BE DELAYED AND COST WILL INCREASE

b)

NO COMMITMENT ON PRICE UNCERTAINTY

c)

TOTAL COST OF PROJECT IS NOT USUALLY KNOWN UNTIL THE PROJECT IS WELL UNDER WAY

d)

THE CLIENT TAKES ALL RISK

4.

What is design and build method ?

a)

contractor only responsible for construct the project and delivery the completed project in accordance in the contract document

b)

single contractor that has been appointed to design and construct the works

5.

An advantages of design and build approach is that construction can be begin before design 100% complete.

a)

true

b)

false

6.

What is the disadvantages of design and build method ?

a)

earlier commencement on site

b)

lack of check and balance

c)

reducing project delivery time

7.

The client, designers and contractor are the prime movers to ensure succesful completion of project. You as a project manager of Megah Holdings to award the contract to make sure the project completed within cost time and quality.

a)

fast track contract

b)

lump sum

c)

partnering

8.

An ongoing stadium to be renovated or upgraded before the upcoming sea games. What are the advantages of fast track contracts?

a)

reduced time

b)

trustworthy parties

c)

greater quality

9.

There are many methods of awarding a contract available. Price Based System/Fixed Price Contract are consist of except

a)

Lump Sum (LS) Contract

b)

Schedule of Rates (SoR) Contract

c)

Bill of Quantities (BoQ) Contract

d)

Cost Plus Percentage of Cost Contract

10.

Examples of Project for Lump Sum Contract are as follows except

a)

High rise building

b)

Signalization

c)

Painting

d)

Guardrail

11.

In Bill of Quantities (BoQ) contract, the detail price of each item is quoted. True or false?

a)

True

b)

False

12.

Below are Standard Forms of Contract that commonly use in Malaysia except

a)

FIDIC

b)

PWD

c)

PAM

d)

ICE

13.

Which of these contract form is derived from ICE

a)

IEEE

b)

FIDIC

c)

PAM

d)

PWD

14.

What is the purpose of standard form of contract for construction

a)

To specify the key variables concerning construction

b)

To form a complete construction planning

c)

To build a legal and safety for building and civil construction