Foresights on a survey are always taken after backsights.
True
False
Most surveying elevations start at 100 feet to avoid negative numbers when measuring slope.
True
False
A station in a survey may have a foresight and no backsight.
True
False
To get the station elevation, subtract the backsight from the height of instrument.
True
False
When completing field notes, column headings are not necessary, as all surveyors follow the same format.
True
False
To calculate the height of instrument, add the backsight measurement to the elevation.
True
False
The longer the distance of the traverse, the greater the allowable error.
True
False
Most surveys assume a starting benchmark elevation of 100 feet.
True
False
During a profile survey, there is never the need for a turning point because all of the readings may be taken from one level or transit location.
True
False
Which tools are commonly used to measure long distances when surveying?
chaining ring and pins
hand sighting caliper
surveyor's scale
tape measure
In surveying, how should 6 inches be noted?
1/2 ft
0.05 ft
0.5 ft
0.6 ft
Who on a taping crew has the responsibility of taking the zero end of the tape and advancing in the direction of the line to be measured, pulling the tape behind?
head tape person
note keeper
rear tape person
secondary tape person
The total distance covered in a leveling circuit is called a __________.
traverse
allowable error
station
benchmark
The maximum acceptable distance that a survey may be off in measurement after being closed-out on the benchmark i s known as:
traverse
allowable error
station
benchmark
The location of the leveling rod when the reading is geing taken is called a:
traverse
allowable error
station
benchmark
A permanent point of known or assumed elevation from which leveling surveys are started is called a:
traverse
allowable error
station
benchmark
A solid location, usually marked by a temporary stake, on which a foresight is taken, to which the instrument is moved, and from which a backsight is taken is a:
turning point
foresight
station
benchmark
A level reading taken on a point of unknown elevation is a:
turning point
foresight
station
benchmark
The process of determining the elevations of a series of points at measured intervals along a line.
profile leveling
benchmark
elevation
station
A permanent point of known or assumed elevation from which a leveling survey is started.
profile leveling
benchmark
elevation
station
The height of a point relative to the benchmark location of the survey.
profile leveling
benchmark
elevation
station
The location of the leveling rod when the reading is being taken.
profile leveling
benchmark
elevation
station
A level reading taken on a point of known or assumed elevation.
backsight
height of instrument
foresight
turning point
The elevation of the level line of sight with respect to the benchmark, as indicated by the cross hairs in the telescope.
backsight
height of instrument
foresight
turning point
A level reading taken on a point of unknown elevation.
backsight
height of instrument
foresight
turning point
A solid location, usually marked by a temporary stake, on which a foresight is taken, to which the instrument is moved, and from which a backsight is taken to determine a new height of instrument.
backsight
height of instrument
foresight
turning point
The measurement records for a survey.
field notes
allowable error
foresight
turning point
The maximum acceptable distance that a survey may be off in measurement after being closed out on the benchmark.
field notes
allowable error
foresight
turning point