VM Mid Sem Quiz 202020211

Total questions: 20

Worksheet time: 40mins

Name
Class
Date
1.

Which terminology is NOT related to Value Management?

a)

Value Analysis

b)

Value Planning

c)

Life-Cycle Cost Analysis

d)

Cost Transition

2.

Who is the first person introduced the Value Management approach?

a)

Lawrence Miles

b)

Dani Miles

c)

Larry Miles

d)

Stephen Male

3.

Which term is NOT associated with the basic principles of Value Management

a)

Multidisciplinary

b)

Cost Comparison

c)

Function Analysis

d)

Structured

4.

Which stakeholders are LESS relevant to the Value Management team/participants?

a)

End User

b)

Consultant

c)

Facilitator

d)

Auctioner

5.

The value can be breaks down into a balance between three construct, EXCLUDING;

a)

Performance

b)

Maintenance

c)

Expectation

d)

Resources

6.

Which of the construct is NOT form the equation of value?

a)

Worth

b)

Incentive

c)

Cost

d)

Benefit

7.

What is the best expression of "function"?

a)

Solution

b)

Maintenance

c)

Performance

d)

Cost

8.

What is the best definition of esteem value?

a)

The cumulative sum an owner is wiling to pay for prestige

b)

The cumulative sum an owner is wiling to pay for performance

c)

The cumulative sum an owner is wiling to pay for operation

d)

The cumulative sum an owner is wiling to pay for function

9.

The maximum benefit gained from VM application would be during the ............... stage of the development

a)

Operation

b)

Inception

c)

Tender

d)

Detail Design

10.

Which of the following is NOT the potential benefits of VM?

a)

Functionality

b)

Constructability

c)

Sustainability

d)

Procurement

11.

What is the best definition of a function?

a)

The specific work that a design/item must ready

b)

The specific work that a design/item must utilize

c)

The specific work that a design/item must be correct

d)

The specific work that a design/item must perform

12.

The following are the objectives of the pre-study stage, EXCEPT:

a)

Ensure that all parties are well coordinated

b)

Ensure that the study are properly targeted

c)

Ensure that there is sufficient pertinent information

d)

Ensure the achievement of the VM

13.

The following activities are conducted during the pre-study stage, EXCEPT?

a)

Conduct feasibility studies

b)

Meeting with the Local Authorities

c)

Verifying cost estimate

d)

Preparing the action plan

14.

Which of the followings is NOT an activities during the post-study phase

a)

Implementation of the recommendations

b)

Following-up the action plan

c)

Preparation of models and efficiency data

d)

Preparation of the final report

15.

Which of the following is the correct sequence of phases in the VM workshop stage

a)

Creativity - Development

b)

Function Analysis -Development

c)

Creativity - Evaluation

d)

Information - Development

16.

Function Analysis can be carried into the following levels, EXCEPT;

a)

Elemental

b)

Layout

c)

Component

d)

Unit

17.

Which of the following information is NOT relevant during the pre-study stage of VM?

a)

Land cost

b)

Cost plan

c)

Access road

d)

As Built Drawing

18.

The functions can be categorized into?

a)

Sell and Esteem

b)

Esteem and Aesthetic

c)

Work and Use

d)

Work and Esteem

19.

Which of the following organization responsible to oversee the implementation of VM at strategic level for government projects in Malaysia

a)

Local Authority

b)

Public Works Department

c)

Economic Planning Unit

d)

Ministry of Works

20.

What is common and recommended duration for VM job plan?

a)

30 hours

b)

35 hours

c)

40 hours

d)

45 hours