Overseeing 5

Total questions: 26

Worksheet time: 52mins

Name
Class
Date
1.

Information regarding delays to a contract must be passed on to the main contractor by means of

a)

Spoken message

b)

Text message

c)

Telephone

d)

Written letter

2.

Test instruments safe use and operating instructions are best found in

a)

BS 88

b)

Manufacturers manuals

c)

BS 7671

d)

GS 38

3.

How many socket outlets are to be installed in the kitchen?

a)

5

b)

3

c)

4

d)

14

4.

How can the level of understanding of a work colleague or new employee be checked?

a)

Ask questions

b)

Written test

c)

Ask colleagues

d)

Practical test

5.

In which room would the supply intake be found?

a)

Bedroom

b)

Lounge

c)

Lounge

d)

Hall

6.

The commissioning process will involve

a)

Installing accessories

b)

Demonstrating how things work

c)

Checking the work against the regulations

d)

Installing cables

7.

Commenting on the speed and quality of work produced by a colleague is considered to be

a)

Co-operation

b)

Motivation

c)

Instruction

d)

Monitoring

8.

A risk assessment has two indexes, those comparing possibility against

a)

Sustainability

b)

Similarity

c)

Severity

d)

Suitability

9.

Who is responsible for producing the drawing and specification for a large installation?

a)

The designer

b)

The sub-contractor

c)

The clerk of works

d)

The site supervisor

10.

Functional testing may involve

a)

Testing earth fault loop impedance

b)

Testing earth electrode

c)

Testing insulation resistance

d)

Operating light switches

11.

It is advisable to check materials arriving on site against

a)

Layout diagrams

b)

Building Regulations

c)

Timesheets

d)

Delivery note

12.

A customer requests the use of a 1980s time clock for which there are no instructions. Where will the instructions for both installation and operation most likely be found?

a)

Electrical wholesaler

b)

Building Regulations

c)

Internet search

d)

Local library

13.

Information for a component’s installation and operation is best sourced from

a)

BS 7671

b)

Manufacturer’s instructions

c)

On-Site Guide

d)

Delivery notes

14.

A Designers specification will identify the type of

a)

Wiring system

b)

Supply cable

c)

Metering equipment

d)

Supply transformer

15.

What type of diagram is shown for the lighting circuit?

a)

Layout diagram

b)

Circuit diagram

c)

Wiring diagram

d)

Schematic diagram

16.

Upon completion of work, copies of the Electrical Installation Certificate are to be

a)

Sent to the local authority

b)

Sent to the NICEIC

c)

Retained by the contractor

d)

Sent to the Building Regulations

17.

A Designer’s specification will identify the type of

a)

Earthing that is required

b)

Metering that is required

c)

Equipment to be installed

d)

Appliances to be installed

18.

It is considered good customer relations and good for business when employees

a)

Discuss working conditions with customers

b)

Develop good relationships with customers

c)

Advise customers without consulting managers

d)

Speak for the employer with no authority

19.

Information to be found on a layout diagram will include

a)

The control sequence

b)

Component positions

c)

How to wire the installation

d)

Methods of fixing accessories

20.

When a company employs 5 or more employees the company must produce

a)

A copy of the Building Regulations

b)

A copy of BS 7671

c)

A copy of the NICEIC handbook

d)

A health and safety policy

21.

What type of safety sign is triangular shaped with a yellow background and has a black border?

a)

Mandatory sign

b)

Warning sign

c)

Prohibition sign

d)

Information sign

22.

If a client asks for information on how a heating system operates and the trainee is unsure. The correct action is to

a)

Seek advice from the employer or a more experienced colleague

b)

Explain that trainees may not know the best answer

c)

Advise the client to go see the site manager

d)

Explain to the customer as well as possible

23.

Trainees who are unsure how a machine operates when asked by a site manager should

a)

Seek advice from the employer or a more experienced colleague

b)

Explain to the manager as well as possible

c)

Tell the manager how they believe it might work

d)

Explain that they are only trainees and would not know the answer

24.

Wherever possible safe isolation procedures should be carried out to

a)

Minimise inconvenience to the user

b)

Finish on time

c)

Make the job last as long as possible

d)

Maximise inconvenience to the user

25.

Communication with customers is important. Agreement must be made with regards to duration of

a)

Wholesaler’s delivery times

b)

Isolation

c)

Inactivity

d)

Work activities

26.

Test leads used with test instruments shall comply with

a)

BS 7671

b)

BS EN 60898

c)

GS 38

d)

BS 88