Chapter 3: Monitoring Contractor Performance

Total questions: 10

Worksheet time: 12mins

Name
Class
Date
1.

Contract Administrator can be any key players such as;


I. Project Architect

II. Lead Consultant

III.Engineer

IV.Client Representative

a)

I & II

b)

II & IV

c)

II, III & IV

d)

All of the above

2.

Which of the followings are incorrect?


I. Contract Administrator making sure each involve parties has the capabilities to carry out their contractual obligations.


II. Contract Administrator is responsible for administrating construction standard form contracts.


III. Standard form contract is a contract which is a non-negotiated contract and is in pre-printed forms.

a)

II

b)

I

c)

III

d)

All of the above

3.

What is the purpose of project duration?

a)

To warn the sub-contractors on the need to take remedial measures when delay occur.

b)

To make sure the contract is completed within time duration

c)

To detect any consequent delay on every activity against a base program.

d)

To officially handover possession of site to contractor

4.

Regular checks at least once a month to check the actual construction progress against programme of work, when behind schedule what action should be taken?


I identify the causes of delays

II speed up the work

III resubmit work for approval

1V revise work programme

a)

I & II

b)

II & IV

c)

II, III & IV

d)

All of the above

5.

There are five (5) types of meetings, except?

a)

Sub-Contractors

b)

AD-HOC

c)

Statutory Meeting

d)

Coordination Project Management

6.

Which of the following are the matter that discuss in the site possession meeting?


I. To set out the procedures pertaining

II. To introduce the various project team members to each other

III. To explain the general requirement of the contract to the contractor

IV. To handover the various contract documents

a)

. I & II

b)

II & IV

c)

II,III & IV

d)

All of the above

7.

Which of the following meetings that not required contractor to attend?

a)

Site Progress Meeting

b)

Ad Hoc Meeting

c)

Coordination/Project Management Meeting

d)

Site Possession Meeting

8.

What is the issue to be dealt in Nominated Sub-Contractor (NSC) coordination meeting?

(can choose more than 1 answer)

a)

Financial issue

b)

Site problem

c)

Team problem

d)

Issue involving 3rd parties

9.

Which of the following are the importance of site records?

I. Reduce delays.

II. Get clearer insight on site.

III. Track the progress of tasks.

IV. Avoid any extra charges by suppliers

a)

I & IV

b)

II & III

c)

I, II, & IV

d)

All of the above

10.

Which of the following is false about site diary?

a)

Prepared by site supervisor.

b)

Endorsed by Contract Administrator or Sub-contractor’s representative.

c)

Weather is not included in the site diary.

d)

Usually site supervisor will prepare it day by day.