WorksheetsChapter 3: Monitoring Contractor Performance
Total questions: 10
Worksheet time: 12mins
Contract Administrator can be any key players such as;
I. Project Architect
II. Lead Consultant
III.Engineer
IV.Client Representative
I & II
II & IV
II, III & IV
All of the above
Which of the followings are incorrect?
I. Contract Administrator making sure each involve parties has the capabilities to carry out their contractual obligations.
II. Contract Administrator is responsible for administrating construction standard form contracts.
III. Standard form contract is a contract which is a non-negotiated contract and is in pre-printed forms.
II
I
III
All of the above
What is the purpose of project duration?
To warn the sub-contractors on the need to take remedial measures when delay occur.
To make sure the contract is completed within time duration
To detect any consequent delay on every activity against a base program.
To officially handover possession of site to contractor
Regular checks at least once a month to check the actual construction progress against programme of work, when behind schedule what action should be taken?
I identify the causes of delays
II speed up the work
III resubmit work for approval
1V revise work programme
I & II
II & IV
II, III & IV
All of the above
There are five (5) types of meetings, except?
Sub-Contractors
AD-HOC
Statutory Meeting
Coordination Project Management
Which of the following are the matter that discuss in the site possession meeting?
I. To set out the procedures pertaining
II. To introduce the various project team members to each other
III. To explain the general requirement of the contract to the contractor
IV. To handover the various contract documents
. I & II
II & IV
II,III & IV
All of the above
Which of the following meetings that not required contractor to attend?
Site Progress Meeting
Ad Hoc Meeting
Coordination/Project Management Meeting
Site Possession Meeting
What is the issue to be dealt in Nominated Sub-Contractor (NSC) coordination meeting?
(can choose more than 1 answer)
Financial issue
Site problem
Team problem
Issue involving 3rd parties
Which of the following are the importance of site records?
I. Reduce delays.
II. Get clearer insight on site.
III. Track the progress of tasks.
IV. Avoid any extra charges by suppliers
I & IV
II & III
I, II, & IV
All of the above
Which of the following is false about site diary?
Prepared by site supervisor.
Endorsed by Contract Administrator or Sub-contractor’s representative.
Weather is not included in the site diary.
Usually site supervisor will prepare it day by day.