wayground logo

Free Printable Worksheets

NEW

Font size

S
M
L
XL
Worksheets

Project, Work Measurement & Aggregate Plan

Total questions: 20

Worksheet time: 11mins

Name
Class
Date
1.

Normal time = observed time x …….. Question

1 point

a)

rating

b)

rating coefficient

c)

rating factor

d)

performance

2.

If observed time for performing a task is 1 minute and the rating is 110%, then the normal time is …….

a)

1.2

b)

1.11

c)

1.1

d)

1.12

3.

Based on the question in picture below, what is the actual production per quater? (assume there are no beginning inventory)

a)

45000

b)

40000

c)

30000

d)

35000

4.

Based on the above question, what is the total ending inventory?

a)

80 000 unit

b)

40 000 unit

5.

For attending natural calls : allowances come under

a)

Interference allowances

b)

Relaxation allowance

c)

Policy allowance

d)

Special allowance

6.

If observed time for performing a task is 1 min and the rating is 120%, total allowance is 10%, then the standard time is……..

a)

1.32 min

b)

1.42 min

c)

1.22 min

d)

1.12 min

7.

Refer to the picture above;

Compute the total normal time.

a)

72.05

b)

73.08

c)

77.8

d)

79.8

8.

Which of the labor standards set is not recommended to be use?

a)

Time studies

b)

Predetermined time standards

c)

Work Sampling

d)

Historical experiences

9.

Which statement below explain on definition of process allowance?.

a)

relax & overcome fatigue- Muslims go to pray

b)

extra time given to correct minor defects in product or equipment.

c)

extra time given for non working time that arise by nature of the process it self.

d)

extra time given because of labour regulation & trade union demands.

10.

Aggregate planning may require:

a)

forecast value

b)

measurable items

c)

method for determining the cost

d)

all of the above

11.

_________________is an approach to determine the quantity and timing of production for the intermediate future.

a)

Aggregate planning

b)

Planning Process

c)

Chase strategy

d)

Transportation method

12.

The objective of aggregate planning is to meet forecast demand while ________ over the planning period.

a)

minimizing cost

b)

maximizing service level

c)

minimizing stock out

d)

minimizing fixed cost

13.

Which of the following is the formula for Total Float ?

a)

Let (Head)- EET (Tail)- Duration

b)

EET(H)-EET(T)-duration

c)

EET(Head)-EET(TAIL)- duration

d)

EET(H)-LET(T) - duration

14.

Based on the following diagram and table, identify the critical activity .

a)

A, D, F, G, H

b)

D, F, E, G, H

c)

B, D, F, G, H

d)

A, C, E, G, H

15.

Based on the diagram, calculate total float for activity G.

a)

1 week

b)

-1 week

c)

2 weeks

d)

0 week

16.

A project has eight activities that need to be completed (Activity A to H) and will be completed in 20 weeks. The EET, LET and duration for activity F are as per the diagram below. If activity F is revised from 4 weeks to 8 weeks, calculate the new completion time for the project.

a)

20weeks

b)

24weeks

c)

23weeks

d)

19weeks

17.

Based on the following table, identify critical path.

a)

2, 4. 5, 7, 8

b)

1. 2, 3, 4, 5, 6, 7, 8

c)

1, 2, 4, 5, 8

d)

3, 6, 7

18.

Based on the table , which one is the correct way to draw pert diagram?

a)
b)
c)
19.

What is the completion time for this pert diagram ?

a)

15 weeks

b)

25 weeks

c)

15 days

d)

25 days

20.

Start the work at earliest time and finish it at earliest time too. This statement refer to:

a)

Total Float

b)

Free Float

c)

Independent Float

d)

Fee time