WorksheetsProject, Work Measurement & Aggregate Plan
Total questions: 20
Worksheet time: 11mins
Normal time = observed time x …….. Question
1 point
rating
rating coefficient
rating factor
performance
If observed time for performing a task is 1 minute and the rating is 110%, then the normal time is …….
1.2
1.11
1.1
1.12
Based on the question in picture below, what is the actual production per quater? (assume there are no beginning inventory)
45000
40000
30000
35000
Based on the above question, what is the total ending inventory?
80 000 unit
40 000 unit
For attending natural calls : allowances come under
Interference allowances
Relaxation allowance
Policy allowance
Special allowance
If observed time for performing a task is 1 min and the rating is 120%, total allowance is 10%, then the standard time is……..
1.32 min
1.42 min
1.22 min
1.12 min
Refer to the picture above;
Compute the total normal time.
72.05
73.08
77.8
79.8
Which of the labor standards set is not recommended to be use?
Time studies
Predetermined time standards
Work Sampling
Historical experiences
Which statement below explain on definition of process allowance?.
relax & overcome fatigue- Muslims go to pray
extra time given to correct minor defects in product or equipment.
extra time given for non working time that arise by nature of the process it self.
extra time given because of labour regulation & trade union demands.
Aggregate planning may require:
forecast value
measurable items
method for determining the cost
all of the above
_________________is an approach to determine the quantity and timing of production for the intermediate future.
Aggregate planning
Planning Process
Chase strategy
Transportation method
The objective of aggregate planning is to meet forecast demand while ________ over the planning period.
minimizing cost
maximizing service level
minimizing stock out
minimizing fixed cost
Which of the following is the formula for Total Float ?
Let (Head)- EET (Tail)- Duration
EET(H)-EET(T)-duration
EET(Head)-EET(TAIL)- duration
EET(H)-LET(T) - duration
Based on the following diagram and table, identify the critical activity .
A, D, F, G, H
D, F, E, G, H
B, D, F, G, H
A, C, E, G, H
Based on the diagram, calculate total float for activity G.
1 week
-1 week
2 weeks
0 week
A project has eight activities that need to be completed (Activity A to H) and will be completed in 20 weeks. The EET, LET and duration for activity F are as per the diagram below. If activity F is revised from 4 weeks to 8 weeks, calculate the new completion time for the project.
20weeks
24weeks
23weeks
19weeks
Based on the following table, identify critical path.
2, 4. 5, 7, 8
1. 2, 3, 4, 5, 6, 7, 8
1, 2, 4, 5, 8
3, 6, 7
Based on the table , which one is the correct way to draw pert diagram?
What is the completion time for this pert diagram ?
15 weeks
25 weeks
15 days
25 days
Start the work at earliest time and finish it at earliest time too. This statement refer to:
Total Float
Free Float
Independent Float
Fee time