Masonry 2 Module 1 review

Total questions: 10

Worksheet time: 20mins

Name
Class
Date
1.

To document a revision in the original construction drawings, a change order must be issued by the construction manager or the _____.

a)

building owner

b)

architect

c)

building inspector

d)

site supervisor

2.

Changes to a building plan made after the contract is signed are called _____.

a)

emendations

b)

alterations

c)

amendments

d)

revisions

3.

The heavy line used to show the main outline of a structure on a construction drawing is called the _____.

a)

object line

b)

center line

c)

section line

d)

dimension line

4.

The abbreviation commonly used on plans to indicate a footing is _____.

a)

FOOT

b)

FG

c)

FTNG

d)

FTG

5.

The rough sizes by which construction materials such as brick or lumber are commonly known are called _____.

a)

working sizes

b)

nominal sizes

c)

approximate sizes

d)

actual sizes

6.

On a plan drawn to a 1/4" = 1' scale, a line 6 inches long represents a distance of _____.

a)

16 feet, 6 inches

b)

24 feet

c)

25 feet, 3 inches

d)

27 feet

7.

Residential floor plans are typically drawn at a scale of _____.

a)

1" = 1'-0"

b)

3/4" = 1'-0"

c)

1/2" = 1'-0"

d)

1/4" = 1'-0"

8.

The mason’s estimate of the number of masonry units needed for a job is referred to as a(n) _____.

a)

quantity takeoff

b)

quantitative analysis

c)

materials inventory

d)

unit requirements schedule

9.

A wall measuring 12' high by 40' long with two openings measuring 8' high by 10' wide will require _____ block. Include a 5 percent waste factor.

a)

252

b)

360

c)

378

d)

420

10.

For 1,000 brick, approximately _____ is required for the mortar.

a)

200 lb

b)

1/2 ton

c)

1,200 lb

d)

1 ton