WorksheetsMasonry 2 Module 1 review
Total questions: 10
Worksheet time: 20mins
To document a revision in the original construction drawings, a change order must be issued by the construction manager or the _____.
building owner
architect
building inspector
site supervisor
Changes to a building plan made after the contract is signed are called _____.
emendations
alterations
amendments
revisions
The heavy line used to show the main outline of a structure on a construction drawing is called the _____.
object line
center line
section line
dimension line
The abbreviation commonly used on plans to indicate a footing is _____.
FOOT
FG
FTNG
FTG
The rough sizes by which construction materials such as brick or lumber are commonly known are called _____.
working sizes
nominal sizes
approximate sizes
actual sizes
On a plan drawn to a 1/4" = 1' scale, a line 6 inches long represents a distance of _____.
16 feet, 6 inches
24 feet
25 feet, 3 inches
27 feet
Residential floor plans are typically drawn at a scale of _____.
1" = 1'-0"
3/4" = 1'-0"
1/2" = 1'-0"
1/4" = 1'-0"
The mason’s estimate of the number of masonry units needed for a job is referred to as a(n) _____.
quantity takeoff
quantitative analysis
materials inventory
unit requirements schedule
A wall measuring 12' high by 40' long with two openings measuring 8' high by 10' wide will require _____ block. Include a 5 percent waste factor.
252
360
378
420
For 1,000 brick, approximately _____ is required for the mortar.
200 lb
1/2 ton
1,200 lb
1 ton