Total questions: 10
Worksheet time: 5mins
An Agile project should have:
Occasional early deliveries, if the business is prepared to accept lower quality
A regular pattern of delivery of developer-focused products
An irregular and unpredictable delivery of products
A regular pattern of delivery of business-valued increments
An Agile project?
Should have no control over its progress
Is always out of control
Is controlled by the velocity of the most junior team member
Should be able to demonstrate control of its progress
Once a project is underway, the approach to planning is
Plans should only be changed with full approval of all stakeholders
Plans should never be changed
It is normal to need to plan and re-plan as the project progresses
Plans are not required
The reason for holding regular retrospectives is:
It allows learning which can be used to improve team performance during the project
It gives management information to use in team members? performance reviews
It prevents deviation from the process which the team has been following
It allows the team to take a welcome break from work
A burn-down chart shows
The declining energy level of the team
The progress of the work and features completed
The rate of reduction of budget for a projec
The number of hours worked after dark
A sustainable pace mean
. Working long hours is the only way to deliver early
The team should establish a velocity that can be sustained with normal working hours
If the team work long hours regularly they will get used to it, and be able to sustain it
A 40 hour week is for the weak
Which of the following are attributes of an Agile team?
Infinite patience
Cynicism
Trust and courage
Hope and charity
An Agile approach values ?
People over process
Process over people
Plans over process
Plans over people
The leadership style of an Agile Leader is ?
Fascinating
Facilitative
Fabulous
Fantastic
The working culture of an Agile team is ?
Collaborative
Connective
Collective
Contemplative