Font size
WorksheetsCPM Quiz
Total questions: 10
Worksheet time: 6mins
In a CPM network diagram, the arrows represent...
relationship of the logic
only the Critical Path
Early start dates
Late start dates
The statement "the vital few and trivial many rule" comes from a principle also known as
Murphy's Law
Pareto's Law
Newton's Law
Law of Thermodynamics
Which of the following is not associated with CPM
Allows management to set priorities
Helps determine the effects of changes or delays
Can not be used in litigation
Identifies the critical activities
The most common relationship in CPM scheduling is...
Start-start
Finish-start
Finish-finish
Start-Finish
To calculate Float of an activity, you (a) Early Start from Late start or Early finish from Late finish
Redundant arrows are necessary to show the proper flow of the logic in the diagram
True
False
It is always a good idea to get input from key management personnel before starting the logic diagram.
True
False
Logic loops help the scheduler understand the relationships of activities that occur at the same time
True
False
To be used successfully, CPM must be developed (choose all that apply)
As a team effort
By involving management personnel
With training so that all can understand it
After the job is completed
Which of the following should the CPM scheduler consider when determining the network logic diagram?
Employ a computer program that uses metric
Try to separate trades
Don't worry about who uses the schedule
Use a Work Backlog System (WBS)