CPM Quiz

Total questions: 10

Worksheet time: 6mins

Name
Class
Date
1.

In a CPM network diagram, the arrows represent...

a)

relationship of the logic

b)

only the Critical Path

c)

Early start dates

d)

Late start dates

2.

The statement "the vital few and trivial many rule" comes from a principle also known as

a)

Murphy's Law

b)

Pareto's Law

c)

Newton's Law

d)

Law of Thermodynamics

3.

Which of the following is not associated with CPM

a)

Allows management to set priorities

b)

Helps determine the effects of changes or delays

c)

Can not be used in litigation

d)

Identifies the critical activities

4.

The most common relationship in CPM scheduling is...

a)

Start-start

b)

Finish-start

c)

Finish-finish

d)

Start-Finish

5.

To calculate Float of an activity, you (a)   Early Start from Late start or Early finish from Late finish

6.

Redundant arrows are necessary to show the proper flow of the logic in the diagram

a)

True

b)

False

7.

It is always a good idea to get input from key management personnel before starting the logic diagram.

a)

True

b)

False

8.

Logic loops help the scheduler understand the relationships of activities that occur at the same time

a)

True

b)

False

9.

To be used successfully, CPM must be developed (choose all that apply)

a)

As a team effort

b)

By involving management personnel

c)

With training so that all can understand it

d)

After the job is completed

10.

Which of the following should the CPM scheduler consider when determining the network logic diagram?

a)

Employ a computer program that uses metric

b)

Try to separate trades

c)

Don't worry about who uses the schedule

d)

Use a Work Backlog System (WBS)