All procurement of supplies and materials of the SK shall be charged against the budget for Capital Outlay (CO).
True
False
The SK shall constitute a Bids and Awards Committee
True
False
All purchases of supplies and materials shall be covered or supported by an approved Purchase Request (PR) and Purchase Order (PO).
True
False
Receipt of purchased S&M/P&E shall be covered by an Inspection and Acceptance Report (IAR) prepared by the SK Treasurer and accomplished by the Inspection and Appraisal Committee
True
False
Issue of purchased and donated property and equipment to SK officials shall be covered by an approved Requisition and Issue Slip (RIS) for accountability purposes.
True
False
Accountability for semi-expendable property and property and equipment shall be extinguished only in the following situations:
-Upon return of the item(s) to the SK Treasurer;
Upon, approval of the Request for Relief from Property Accountability (RRPA) in case of loss; and
Upon payment of the lost item based on the fair value at the time of loss and not when the loss was reported, if the RRPA is denied
True
False
Construction of property and equipment shall be recorded and monitored in the _______________________________.
Property and Equipment Card
Construction in Progress Card (CIPC)
Stock Card
______________ and Registry of Donated Supplies and Materials (RDSM)
shall be maintained to record/monitor the receipt and issue/loss/transfer/disposal of supplies and materials
Property and Equipment Card
Construction in Progress Card
Stock Card
___________________________ and Registry of Donated Property and Equipment (RDPE) shall be maintained to record the receipt, issue, transfers, losses, and disposals of the property and equipment
Property and Equipment Card
Construction in Progress Card (CIPC)
Stock Card
SK Treasurer is the Supply and Property Officer
True
False