wayground logo

Free Printable Worksheets

NEW

Font size

S
M
L
XL
Worksheets

Final Exam - IP - Project Management

Total questions: 10

Worksheet time: 14mins

Name
Class
Date
1.

All of the following are tools of Control Quality, EXCEPT: (10 points)

a)

Cost quality

b)

 Inspection

c)

Control Charts

d)

Flowcharting

2.

The purpose of fishbone diagram is to: (10 points)

a)

Show how a process or system flows from beginning to end

b)

Simulate thinking, organize thoughts, and generate discussion

c)

Determine the organization of the project

d)

Show fundamental responsbilities and how they are related to one another and to the objectives of the project

3.

During project executing, a major problem occurs that was not included in the risk register. What should you do FIRTS? (10 points)

a)

Create a workaround

b)

Reevaluate and identify risks process

c)

Look for any unexpected effects of the problem

d)

Tell management

4.

After identifying a risk to you project, you determine that there is a high probability of the risk occurring, but its consequences are low. Which mitigation strategy would be BEST to adopt in this case? (10 points)

a)

Eliminate the consequence of the risk

b)

Avoid the risk

c)

Add the risk to the watch list

d)

Insure against the risk

5.

Workarounds are determined during which risk management process? (10 points)

a)

Identify risks

b)

Perform quantity risk analysis

c)

Plan risk responses

d)

Control risks

6.

Which of the following is not included in the risk register as an output of Identify Risks? (10 points)

a)

List of risk owners

b)

List of potential risk responses

c)

The root cause of the risks

d)

List of risks

7.

In the stakeholder management knowledge area, change request, corrective actions, and lesson learned are MOST likely to be the output of which process? (10 points)

a)

Plan stakeholder management and manage stakeholder engangement

b)

Control scope and develop project team

c)

Manage stakeholder engagement and control stakeholder engangement

d)

Plan stakeholder management and control stakeholder management

8.

Stakeholder assessment and classification in an output of which process? (10 points)

a)

Plan stakeholder management

b)

Identify stakeholder

c)

Manage stakeholder engagement

d)

Control stakeholder expectations

9.

What is one of the ways that expert judgement might be used in the stakeholder management knowledge area? (10 points)

a)

Asking another project manager who has worked with a difficult stakeholder what techniques he or she used to keep this stakeholder engagement

b)

Interviewing a difficult stakeholder to determine their level of impact, influence, and engagement in the project

c)

Meeting with the project sponsor to report your assessment of the relative impact and influence of the key stakeholders on the project

d)

Recording the relative impact, influence, interest, and attitude of various stakeholders in the stakeholder register

10.

Which stakeholder management processes are MOST likely to result in updates to the project management plan? (10 points)

a)

Control stakeholder engagement and plan stakeholder management

b)

Plan stakeholder management and identify stakeholders

c)

Manage stakeholder engagement and control stakeholder engangement

d)

Identify stakeholders and control stakeholder engagement