Sustainability, Green Buildings and LEED | LEED Green Associate

Total questions: 70

Worksheet time: 40mins

Name
Class
Date
1.

A building with zero net energy consumption is called:

a)

LEED Platinum buildings

b)

Living building

c)

Net-zero energy building

d)

Passive Energy Buildings

2.

An Energy Star certification or plaque can be earned by buildings that are in the top ___ percentile of existing buildings in terms of energy and water performance?

a)

25

b)

50

c)

75

d)

80

3.

Which of the following must be true for a project to earn LEED Silver certification? Choose 3

a)

Achieve at least 50 points

b)

Have one of the principal project team members be a LEED AP

c)

Have the project administrator be a LEED AP

d)

Meet the Minimum Program Requirements

e)

Achieve all prerequisites for the rating system

4.

Which of the following would not be considered part of the ‘built environment’?

a)

1000 acre neighborhood

b)

Roads

c)

Natural pond

d)

Single office building

e)

A city park developed on the site of a former steel mill

5.

Which of the following is used by a project team to analyze, and track LEED credits and prerequisites?

a)

LEED scorecard

b)

MPRs

c)

LEED track

d)

CIRs

6.

For a building project, when does the life cycle approach begin?

a)

After a site has been selected

b)

During project scheduling

c)

During materials selection

d)

With the initial pre-design decisions and goal setting

e)

Once the designer is selected

7.

A potential LEED project could be registered potentially under 2 rating systems. How should the project team decide which rating system to use? Choose 2

a)

The rating system that could earn the most points should always be selected

b)

The project team must submit a CIR

c)

The project team must independently decide which rating system to use

d)

Use the 40/60 rule

8.

A project team should prepare and complete a LEED Score Card to:

a)

To determine LEED responsibilities

b)

To estimate the target LEED certification level

c)

To prepare a cost estimate

d)

To register the project

9.

Which of the following variables affect LEED Registration cost? (Choose 2)

a)

Project’s rating system

b)

Project’s size

c)

Location of the Project – U.S. or Outside U.S

d)

Substantial completion of the project

e)

Time when the project team decides to register

10.

How should the project team decide which rating system to use when registering a project?

a)

Use the 40/60 rule

b)

The project team must submit a CIR

c)

LEED for New Construction

d)

The rating system that could earn the most points should always be selected

11.

Who is responsible for the development of the LEED Rating Systems?

a)

Product manufacturers

b)

Architects, engineers, and contractors only

c)

Local, state, and federal government agencies

d)

Volunteers

e)

USGBC National Members

12.

An Energy Star certification or plaque can be earned by buildings that earn ____ points out of 100?

a)

25

b)

75

c)

50

d)

80

13.

What does the LEED Volume Program help with?

a)

Cost-effective LEED certification on an entire portfolio of projects

b)

Cost-effective LEED certification for more than one project located on a single shared site like a corporate or education campus

c)

Energy Star Certification

d)

LEED ND Certification

14.

A project team for a new construction project is developing a LEED Score Card. What should the project team do with it once it has been completed?

a)

Use it as a tracking tool for LEED prerequisites and credits during the construction process

b)

Submit it to USGBC

c)

Use it to submit CIR

d)

Send it to project owner for approval

15.

Which of the following make the key aspects of the triple bottom line? Choose 3

a)

Energy

b)

Government

c)

Social responsibility

d)

Environment

e)

Economics

16.

What minimum floor area is needed for New Construction, Core and Shell, Schools, Existing Buildings: Operations and Maintenance projects?

a)

There is no minimum

b)

250 sq.ft

c)

5,000 sq. ft.

d)

1,000 sq. ft.

e)

10,000 sq. ft.

17.

Which of the following is true about LEED Plaque? Choose 3

a)

Projects can only display the plaques inside their building

b)

Projects may display the plaques outside their building

c)

Once the project accepts the final certification, it may apply for the LEED plaque

d)

Alternative 5

e)

Project teams may apply for multiple plaques

18.

Which of the following is a primary goal of the USGBC?

a)

Market transformation of the building industry

b)

To promote green products

c)

To reduce the construction costs of a building

d)

To promote green buildings

19.

Which of the following are LEED’s fundamental goals? Choose 3

a)

Protect and enhance biodiversity and ecosystem services

b)

Transform the built environment

c)

Enhance the economy

d)

Enhance individual human health

e)

Enhance community quality of life

20.

Which of the following represent the responsibilities of a LEED Project administrator? Choose 3

a)

Register the project with LEED online

b)

Invite team members to LEED Online

c)

Attend all project progress meetings

d)

Assign team members to credits in LEED Online

e)

Submit the project application to GBCI for review

21.

Built environment refers to:

a)

Considering the environment while building new structures

b)

Structures that provide stronger connections to nature

c)

Process of building green buildings

d)

Process of building traditional buildings

e)

Man-made environment that is comprised of buildings, surroundings and infrastructure

22.

A project team is conducting a project life cycle (PLC) analysis for a new Core and Shell project in Washington D.C. Which building elements are covered under the LEED BD+C: Core and Shell rating system? (Choose 3)

a)

Furniture, furnishings, and equipment (FF&E)

b)

Base Building Structure

c)

Base Building HVAC system

d)

Building Envelope

e)

Tenant fit-out

23.

What happens after the project is registered under LEED v4?

a)

The project will have a Green Rater assigned to the project

b)

The project team will receive the welcome package from GBCI

c)

The project will receive pre-certification

d)

The project team gains access to the LEED Online Portal

24.

Which of the following LEED rating systems address exterior site maintenance programs?

a)

LEED for Core and Shell

b)

LEED for Existing Buildings: Operations and Maintenance

c)

LEED for Schools

d)

LEED for New Construction

25.

An existing office building is undergoing envelope upgrades and HVAC replacement. Based on these upgrades, which LEED rating system is most suitable for the project?

a)

LEED for Existing Buildings: O+M

b)

LEED for Commercial Interiors

c)

LEED for Retail

d)

LEED for New Construction

26.

What is the minimum occupancy rate required for LEED for Existing Buildings: Operations & Maintenance to earn certification?

a)

Typical physical occupancy

b)

75%

c)

80%

d)

50%

27.

A project team is evaluating different project locations and sites for a potential LEED ND project. Which of the following must be true in order for the site to qualify for LEED certification under the LEED ND rating system? (Choose 2)

a)

The site should be at least 1500 acres

b)

The site should be no larger than 1500 acres

c)

The site should have at least 10 habitable buildings

d)

The site should have at least 2 habitable buildings

e)

The site should be at least 100 acres

28.

Which of the following is true about the EPA Energy Star Program? Choose 2

a)

Energy Star labels appliances

b)

Energy Star accredits individuals

c)

Energy Star certifies individuals

d)

Energy Star certifies buildings

29.

You are registering an office project in Hiawatha, Iowa under the LEED BD+C rating system. Which of the following design decisions would you NOT recommend for LEED certification?

a)

The area of the building will be 1500 square feet

b)

The building will be located 75 feet away from a lake

c)

The building will be three stories high

d)

The new building is located on a campus certified under LEED v4

e)

One of the modular offices will be moved to another location after project completion

30.

What is different about green building design compared to conventional design?

a)

Green building has longer schedules

b)

Green building uses an integrated building design

c)

Green building costs more

d)

Green building does not have a bidding phase

31.

What is the maximum no: of points a project can earn for a LEED Project?

a)

100

b)

110

c)

80

d)

60

32.

What are acceptable ways to use USGBC in text according to the USGBC Trademark Policy? Choose 2

a)

U.S. Green Building Council

b)

US Green Building Council

c)

U.S.G.B.C

d)

USGBC

e)

U.S. GBC

33.

Which of the following must be true for a project to earn LEED certification? Choose 2

a)

Have one of the principal project team members be a LEED AP

b)

Have the project administrator be a LEED AP

c)

Meet the Minimum Program Requirements

d)

Achieve all prerequisites for the rating system

e)

Achieve at least 50 points

34.

What logo is used to designate membership with USGBC?

a)

USGBC Faculty

b)

USGBC logo

c)

LEED AP logo

d)

LEED logo

e)

USGBC member logo

35.

The project team for a potential LEED project in Phoenix, Arizona submits a summary of early design stage submittal materials for GBCI review to pursue LEED Pre-certification. Which of the following statements must be true of the project?

a)

The project can only apply for Pre-certification after the completion construction

b)

The project must be registered under New Construction

c)

The project must be registered under Core and Shell

d)

The project can only apply for Pre-certification after the completion of detailed design documents

36.

Which of the following are NOT soft costs?

a)

Project drawings

b)

City permits

c)

Windows

d)

Commissioning of the building’s systems

37.

Which of the following is TRUE about LEED?

a)

LEED only certifies buildings

b)

LEED only certifies individuals

c)

LEED only certifies building products

d)

LEED certifies buildings and products

38.

The project team for a mixed use project located in Washington D.C. has more than 50% of its space for retail and a remaining 40% or less for office space. How should the project team decide which rating system to use?

a)

The project should choose office space since that occupies 40%

b)

The project should choose BD+C: Retail since that occupies the majority

c)

The project should use the 40/60 rule to decide on a rating system

d)

The project should submit a CIR

e)

The project should choose the rating system that will result in the lowest certification costs

39.

What term refers to a mandatory project characteristic, measurement, quality, value or function as identified within the LEED rating system?

a)

Prerequisite

b)

Credit

c)

Minimum Program Requirement

d)

CIR

40.

Which of the following elements of the LEED v4 development cycle is utilized for streamlining the approach to unique needs, constraints, and opportunities of different project types?

a)

Recertification

b)

LEED online

c)

LEED Technical Advisory Group (TAG)

d)

Interpretations

e)

Adaptations

41.

Which of the following can be seen as benefits of the Integrated Project Delivery (IPD) process? Choose 2

a)

Building Commissioning

b)

Faster design

c)

Maximized efficiency through all phases of design, fabrication, and construction

d)

Lower operating costs

42.

What may happen if a project does not comply with the minimum program requirements after LEED certification?

a)

The project team will need to submit an appeal

b)

The building’s certification may be revoked

c)

The project keeps the LEED certification

d)

An alternative compliance path can be used

e)

The project team will need to submit a CIR

43.

What statements are true regarding the LEED for Commercial Interiors rating system?

a)

Projects are only eligible if the tenants purchase the space

b)

This rating system is appropriate for spaces that are undergoing a complete interior fit-out of at least 60% of the certifying gross floor area

c)

This rating system can only be used if envelope upgrades are done

d)

The rating system requires HVAC replacement

e)

This rating system can only be used if base building is a LEED Core and Shell Certified Building

44.

Which of the following is an example of adaptive reuse?

a)

Demolishing an old steel mill and adding residences on the property

b)

Renovating a historic building

c)

Designing a building with a flexible floor plan that can accommodate offices or apartments

d)

Renovating an existing building

45.

Integrated project delivery (IPD) is associated with what?

a)

Construction Process

b)

Green Building Process

c)

Green Design process

d)

Traditional Building Process

46.

When comparing with the conventional building costs, what is the average marginal cost variance for green buildings?

a)

5-7%

b)

10-15%

c)

0-2%

d)

4-6%

47.

During what project phase should the project owner think of green design to build a green building and keep the costs comparable to a traditional building?

a)

It doesn’t matter

b)

Pre-design phase

c)

Construction Phase

d)

Design Phase

48.

A building owner for a new 20-story office building will occupy less than 25% of floor space. The completed building will be occupied by multiple tenants. What LEED rating system would be most appropriate for the base building?

a)

LEED for Commercial Interiors

b)

LEED for New Construction

c)

LEED for Core and Shell

d)

LEED for Existing Buildings: Operations & Maintenance

e)

LEED for Retail

49.

Which of the following should a LEED project use when certifying more than one project located on a single shared site like a corporate or education campus?

a)

LEED Volume Certifications

b)

LEED ND Certification

c)

LEED Campus Certifications

d)

LEED Portfolio

50.

Which of the following is true about Credit Interpretation Requests (CIRs)?

a)

CIRs can be submitted for credit appeals

b)

Points are awarded by the CIR process

c)

Potential LEED Projects can access all CIRS and submit new

d)

CIRs can be submitted for prerequisites

51.

Which of the following allows utility customers to offset the cost of power drawn from the utility by selling surplus energy to utility?

a)

Energy Star

b)

Net metering

c)

Energy plus

d)

Net zero

52.

A building owner for a new 20-story office building will occupy twelve (12) floors. What LEED rating system would be most appropriate for the owner’s interior fit-out of the twelve (12) floors?

a)

LEED for Retail

b)

LEED for New Construction

c)

LEED for Commercial Interiors

d)

LEED for Existing Buildings: Operations & Maintenance

53.

A Project team just registered a new construction project. What are acceptable ways to reference a LEED Registered Project? Choose 2

a)

The project is LEED Qualified

b)

The project is LEED Platinum certified

c)

The project is registered with the certification goal of LEED Gold certification

d)

The project is registered under the LEED Green Building Rating System

e)

The project is pre-certified

54.

Which of the following represent the main sustainability goals for the Materials and Resources category under the LEED v4 rating system? Choose 3

a)

Don’t use chemicals that degrade the atmosphere or contribute to climate change

b)

Utilize renewable energy onsite

c)

Re-use materials

d)

Recycle materials and resources

e)

Reduce waste

55.

Which of the following are seen as environmental impacts of buildings? Choose 3

a)

Building Industry created 7.36 million jobs in the construction industry in 2014

b)

Buildings generate 136 million tons of waste annually

c)

30% of buildings suffer from sick building syndrome

d)

Buildings are responsible for 14% of potable water consumption

e)

Buildings contribute to 38% of greenhouse gas emissions

56.

Which of the following is true of LEED for Existing Buildings: Operations & Maintenance rating system?

a)

Can be applied to only part of a building

b)

A LEED AP is required to be on the building maintenance staff for a LEED O+M Project

c)

It applies to any type of building project

d)

It assists project teams to measure building performance over a period of time

57.

Which of the following are examples of the variety of ways in which LEED v4 is more applicable across the globe? Choose 3

a)

Regionally specific solutions can be developed in collaboration with the LEED International Roundtable

b)

International projects may submit up to 5 FREE CIRs

c)

New international standards are also included as guidelines in the LEED Reference Guide

d)

All measurements and calculations are shown both in SI and IP

e)

International Projects are not allowed to use regionally specific solutions

58.

Who can use the USGBC logo?

a)

Only organizations that have received approval by the USGBC marketing department

b)

Any LEED AP

c)

Any USGBC member

d)

Any USGBC member or USGBC chapter

e)

Any USGBC National Member

59.

Which of the following are Minimum Program Requirements (MPR) under LEED v4? Choose 3

a)

Must comply with environmental laws

b)

Must use reasonable LEED boundaries

c)

Must comply with a minimum building area to site area ratio

d)

Must be in a permanent location on existing land

e)

Must comply with project size requirements

60.

What statement is true regarding green building?

a)

The construction of green buildings have significant cost difference to non-green buildings

b)

All green buildings are LEED certified

c)

ROI on green buildings are not significant

d)

The construction of green buildings have no major significant cost difference to non-green buildings

61.

Which of the following is true about LEED dynamic Plaque? Choose 2

a)

The LEED Dynamic Plaque displays the LEED Performance Score of the building across five categories: Energy, Water, Waste, Transportation and Human Experience

b)

Project may only apply for either LEED dynamic plaque or normal LEED plaque

c)

Projects can only display the plaques inside their building

d)

The LEED Dynamic Plaque is a building performance monitoring and scoring platform for LEED-certified projects

e)

The LEED Dynamic Plaque displays the LEED Performance Score of the building across six categories: Sites, Energy, Water, Materials, Transportation and Human Experience

62.

What is an example of a negative feedback loop?

a)

A thermostat where the temperature feedback indicates to the system when to turn off

b)

Warming oceans releasing greenhouse gasses which would warm the ocean even more

c)

A warmer atmosphere melts more ice, changing the Earth’s albedo which further warms the atmosphere

d)

Increased heat islands require more mechanical cooling which generates more greenhouse gas emissions causing the need for more cooling

63.

Where should a project team register a new LEED Project?

a)

GBCI Website

b)

USGBC Website

c)

LEED online portal

d)

Send registration application by mail to GBCI

64.

Where should a project team go for updates and errata for the LEED for New Construction rating system?

a)

LEED reference guides

d)

LEED online

65.

What is true about a project that earns 38 points towards certification under the LEED v4 rating system?

a)

The project would earn LEED Silver certification

b)

The project would not earn certification

c)

The project would earn LEED Gold certification

d)

The project would earn LEED Certified status

66.

How many project types does the LEED rating systems collectively address?

a)

5

b)

15

c)

21

d)

7

67.

A project in Raleigh, North Carolina was originally registered under BD+C: New Construction. Later during the pre-design stage, the owner finds 3 tenants to occupy the building space upon completion and hence wants to change the rating system to Core and Shell. Which action should be taken by the project team?

a)

Contact LEED technical customer service

b)

Submit a LEED interpretation

c)

Submit a project CIR

d)

Submit the issue via the feedback button within leedonline.com

68.

A hospitality project team member finds an area not addressed in the LEED reference guide regarding WE Credit Outdoor Water Use Reduction. The team implements the credit and submits a suggested approach for the credit during the preliminary LEED review process. Which of the following is true regarding this project team’s approach?

a)

The project team will receive a determination in the review comments at the discretion of the USGBC or GBCI reviewer assigned to the project.

b)

The approach will be rejected because it is outside the scope of the review process

c)

The approach will be rejected and a Project CIR will need to be submitted instead

d)

The project should submit a CIR along with credit documentation

69.

Which of the following variables affect LEED Certification cost? (Choose 3)

a)

Project Occupancy

b)

Project’s size

c)

Time when the project team submits documentation for review in LEED Online

d)

Project’s rating system

e)

Substantial completion of the project

70.

Which of the following are characteristics of the integrative process (IP) credit under the LEED rating system? Choose 2

a)

IP Credit falls under Location and Transportation

b)

IP Credit is a prerequisite for LEED School projects

c)

IP Credit overlaps and touches upon every other credit category

d)

It is embedded throughout the rating system