Total questions: 20
Worksheet time: 13mins
Which is not a determinant of effective capacity?
Facilities
Cost
Product and Service Factors
Product and Service
Factors
The term capacity refers to the maximum quantity an operating unit can process over a given period of time.
True
False
Capacity decisions are usually one-time decisions; once they have been made, we know the limits of our operations.
True
False
Round off your final answer to two decimal places. Determine the efficiency rate if; Actual capacity is 23,500, Design capacity is 35,000 and Effective capacity is 32,000.
(a)
Capacity planning requires an analysis of needs: what kind, how much, and when.
True
False
Utilization is defined as the ratio of effective capacity to design capacity.
True
False
According to the reading on restaurant sourcing practices, only fast-food restaurants are able to bring in outsourced foods.
True
False
A loan processing operation that processes an average of 7 loans per day. The operation has a design capacity of 10 loans per day and an effective capacity of 8 loans per day. Compute for the utilization rate.
70.00%
66.67%
87.50%
80.00%
None of the options
Capacity decisions often involve a long-term commitment of resources which, when
implemented, are difficult or impossible to modify without major added costs.
True
False
Capacity decisions are based on technological concerns, not demand forecasts.
True
False
A furnace repair team that services an average of four furnaces a day if the design capacity is six furnaces a day and effective capacity is five furnaces a day. Compute for the efficiency rate.
70.00%
66.67%
87.50%
80.00%
None of the options
Bottleneck operation is an operation in a sequence of operations whose capacity is lower than that of the other operations.
True
False
Outsourcing is an activity performed within the business, using the company’s assets and employees.
True
False
The goal of strategic capacity planning is to achieve a match between the long-term supply capabilities of an organization and the predicted level of long-term demand.
True
False
A loan processing operation that processes an average of 7 loans per day. The operation has a design capacity of 10 loans per day and an effective capacity of 8 loans per day. Compute for the efficiency rate.
70.00%
66.67%
87.50%
80.00%
None of the options
A furnace repair team that services an average of four furnaces a day if the design capacity is six furnaces a day and effective capacity is five furnaces a day. Compute for the utilization rate.
70.00%
66.67%
87.50%
80.00%
None of the options
Which is not a determinant of effective capacity?
Human Factors
The nature of demand
Policy
Supply Chain Factors
Which is not a factor to consider in deciding whether to perform in-house or outsource?
Expertise
The nature of demand
Policy Factors
Risks
Round off your final answer to two decimal places. Determine the utilization rate if; Actual capacity is 23,500, Design capacity is 35,000 and Effective capacity is 32,000.
(a)
Outsourcing is
exporting
Building a factory in another country to produce for that country’s market
Importing
A firm having someone else to do part of what it previously did itself