1.

What is the current 12th PM Forum theme?

a)

Schedule Management

b)

Cost Management

c)

Risk Management

d)

Quality Management

2.

The project management triangle is a model of the constraints of project management.

What is the missing constrain?

(type your answer)

(a)  

3.

Positive impact of risk is referred as :

a)

Chance

b)

Opportunity

c)

Profit

d)

Luck

4.

Negative effect of risk is referred as :

a)

Problem

b)

Issue

c)

Threat

d)

Trouble

5.

Event risk is commonly linked with :

a)

Aleatoric uncertainty

b)

Stochastic uncertainty

c)

Epistemic uncertainty

d)

Ontological uncertainty

6.

The picture is referring to :

a)

Risk heatmap

b)

Risk register

c)

Monte Carlo analysis

d)

Tornado chart

7.

Overall project risks is the same with the sum of individual risks.

a)

True

b)

False

8.

Identifying a risk as high, moderate, or low would be an example of which risk assessment?

a)

Quantitative

b)

Qualitative

c)

Adverse

d)

Dynamic