Project Management

Total questions: 23

Worksheet time: 27mins

Name
Class
Date
1.

Benefit of CPM...

a)

A) Provides a graphical view of the Project.

b)

B) Can't predict the time required to complete the project.

c)

C) Easy manage a complex work.

d)

D) Both A and C

2.

Which activity aims to maximize success of the project ?

a)

Performance monitoring

b)

CPM

c)

PERT

d)

Project Audit

3.

CPM is

a)

Critical Project Management

b)

Critical Path Management

c)

Critical Path Method

d)

Crash Project Method

4.

Which of the following statements is not correct

a)

PERT is probabilistic in nature

b)

CPM is probabilistic in nature.

c)

CPM and PERT use similar terminology but were developed independently

d)

All of these statements are correct

5.

Which of the following is not a rule of network construction?

a)

Each defined activity is represented by one and only one arrow.

b)

A network should have only initial and one terminal node.

c)

Identical initial and final nodes can identify two activities

d)

Only as few dummy activities should be included as is warranted

6.

Which is the first step of Schedule management process?

a)

Sequence activity

b)

Estimate activity durations

c)

Determine activities

d)

Develop schedule

7.

Which is the second step of Project scheduling process?

a)

Define activity

b)

Estimate activity durations

c)

Plan schedule management

d)

Develop schedule

8.

In this table, which information do we need more to build the schedule management plan up?

a)

Activity list

b)

Duration

c)

Predecessor

d)

CPM

9.

In this table, which information do we need to know if we would like to develop the project schedule management?

a)

Activity list

b)

Sequence activity

c)

Duration

d)

Task coding

10.

Slack time in project management is :

a)

The latest point in time when the schedule activity can begin so as not to delay the project completion date or any constraint.

b)

time a task can be delayed without causing another task to be delayed, or without impacting the overall project completion

c)

The earliest point in time when the schedule activity can begin

d)

The earliest point in time when the schedule activity can complete

11.

PERT is a technique, used to manage

a)

activities of a project

b)

sequencing

c)

quality

d)

uncertain tasks of a project

12.

A PERT network is activity-oriented while a CPM network is event-oriented

a)

True

b)

false

c)

cant say

13.

_________ are used to represent activity in a network diagram.

a)

circle

b)

square

c)

Rectangle

d)

arrow

14.

According to the time estimates made by the PERT planners, the maximum time that would be needed to complete an activity is called as __________

a)

a) The most likely time estimate

b)

b) Optimistic time estimate

c)

c) Pessimistic time estimate

d)

d) Expected time estimate

15.

The shortest possible time in which an activity can be achieved under ideal circumstances is known as ________

a)

a) Pessimistic time estimate

b)

b) Optimistic time estimate

c)

c) Expected time estimate

d)

d) The most likely time estimate

16.

What does event in CPM & PERT network refers to?

a)

The occurrence of a delay in the project

b)

A activity inserted into the network to show a precedence relationship with no passage of time

c)

beginning or completion of an activity or project e

d)

The earliest and activity can start

17.

Why does activities in the critical path are called critical

a)

Represent the maximum project completion time

b)

Can not tolerate any delay in completion

c)

Represent most expense in terms of resources

d)

Represent most longest and complex activities of the project

18.

In PERT, slack time equals

a)

ES + t

b)

LS-ES

c)

0

d)

EF-es

e)

non of the above

19.

Network models such as PERT and CPM are used to

a)

plan large and complex projects

b)

schedule large and complex projects

c)

monitor large and complex projects

d)

control large and complex projects

e)

all of the above

20.

if activity A is on the critical path, then the slack for A will equal

a)

LF-EF

b)

LS-ES

c)

0

d)

all of the above

21.

the earliest start time for an activity is equal to

a)

the largest EF of the immediate predecessors

b)

the smallest EF of the immediate predecessors

c)

the largest ES of the immediate predecessors

d)

the smallest ES of the immediate predecessors

22.

The latest finish time for an activity is found during the backward pass through the network. The latest finish time is equal to

a)

the largest LF of the activities for which it is an immediate predecessor

b)

the smallest LF of the activities for which it is an immediate predecessor

c)

the largest LS of the activities for which it is an immediate predecessor

d)

the largest LS of the activities for which it is an immediate predecessor

23.

To complete the wings assembly for an aircraft , Mr Mikhaeel has laid out the major steps and seven activities involved. these activities have been label A through G in the following table, which also shows their estimated completion times (in weeks) and immediate predecessors. determine the expected time and variance for each activity.

Now, Mikhaeel would like to determine the critical path for the entire wing assembly project as well as the expected completion time for the total project.