WorksheetsCM2 Midterm Mock Exam
Total questions: 50
Worksheet time: 25mins
This management involves creating a project charter with coverage and intent of the work including personalities involved and lay-outing a management plan on how the project will be executed.
Integration Management
Scope Management
Schedule/Time Management
Cost Management
This management area involves planning of project scope or coverage of work involve and definition of all tasks involved.
Integration Management
Scope Management
Schedule/Time Management
Communications Management
This management involves definition of activities involved, identifying the succession of construction activities, and estimating the needed resources based on the activities.
Integration Management
Scope Management
Schedule/Time Management
Quality Management
This management area involves preparing estimated cost, budgeting the cost corresponding to the activities, and adherence to and control of the budget per project cost.
Cost Management
Quality Management
Resource Management
Communications Management
This management area involves establishing the project quality, carrying out quality assurance in the construction activities, and implementing control to the established project quality.
Cost Management
Quality Management
Resource Management
Communications Management
This management area involves setting up requirements for necessary human resources, hiring staff and workers as required, and formulating groups to work as project teams.
Cost Management
Resource Management
Communications Management
Risk Management
This management involves formulation of communication means within the organization, systematizing information distribution, and establishing format in reporting work performances,
Resource Management
Communications Management
Risk Management
Quality Management
This management area involves formulating a management plan for project risks, identification of the risks involved in construction, and evaluating project risks that are qualitative and quantitative.
Communications Management
Risk Management
Procurement Management
Stakeholder Management
This management area involves the preparation of resource purchases and acquisition for a project, organizing terms for contracting work packages, and soliciting bidder, sub-contractor, seller responses.
Risk Management
Procurement Management
Communications Management
Cost Management
This management area involves identifying all participant involved in the project, organizing meeting of project stakeholders, and managing and monitoring commitments of and conflicts between project participants.
Stakeholder Management
Procurement Management
Risk Management
Cost Management
Fill in the blank for PROJECT MANAGEMENT COURSE OF ACTION:
Initiating to Planning to _________ to Monitoring to Closing
Executing
Manipulating
Installing
Constructing
The person in charge to oversee all phases from conceptualization, plan, definition, implementation, monitoring, and control, up to the turn-over and close-out.
Project Manager
Construction Manager
Construction Supervisor
Contractor
The person in charge of the daily construction operations, overseeing all activities being done per trade. He/she monitors the time, cost and quality of construction works and reports to the Project Manager.
Project Manager
Construction Manager
Construction Supervisor
Contractor
The person that conducts daily supervision of workers at the construction site. He/she does a regular scrutiny of the field works including that of the sub-contractors through full-time project inspections and reports to the Construction Manager.
Project Manager
Construction Manager
Construction Supervisor
Contractor
The person makes decisions, controls work, interprets policies and generally is the ______ in the process of accomplishing work. He/she represents the management to the workers and on the other hand, he/she represents the workers to the management.
Keyman
Man in the Middle
Marginal Man
Another Worker
In the ____ concept, the construction supervisor is pressed between two opposing dynamics of management and workers
Keyman
Man in the Middle
Marginal Man
Another Worker
The idea refers to the sociological concept that the construction supervisor is along the margin of the main construction activities and tasks concerning his team. For short, he is left out, with the management and workers directly dealing.
Keyman
Marginal Man
Man in the Middle
Human Relation Specialist
In the construction supervision concept, he/she was only given a position as a title, but in reality, he/she is just another worker
Middle Man
Another Worker
Marginal Man
Human Relation Specialist
The management in some cases relies on the construction supervisor for human resources. It is perceived that the easy way to obtain workers and to get their cooperation is through the construction supervisor and so he/she is more considered as a ____ rather than a technical individual
Middle Man
Human Relation Specialist
Another Worker
Keyman
Disciplined way of carrying out construction works, examining the processes in order to find the efficient methods and work to develop better ones
Method Study Method
Work Measurement
Work Study
Used to establish the time it should take to carry out a specific job/work
Method Study Method
Work Measurement
Work Study
Combination of method study and work measurement which examines human work and systematically investigated all the factors affecting efficiency in order to effect improvement
Method Study Method
Work Measurement
Work Study
Basic procedure in work study method where the job needs to be improved or set up
Select
Record
Examine
Develop
Basic procedure in work study method where all the relevant facts about the job and the work elements are in it
Select
Record
Examine
Install
Basic procedure in work study method where critically the facts and work elements
Examine
Develop
Install
Maintain
Basic procedure in work study method with the best method from the alternative methods available
Develop
Install
Maintain
Examine
Basic procedure in work study method with set up to the new method on construction site
Install
Develop
Maintain
Examine
Basic procedure in work study method which monitor the new method to ensure success
Maintain
Install
Develop
Examine
Differences in terms of height, weight, looks, etc., have little significance in most clerical and administrative positions but there are exceptions when these might interfere with the performance of job resposibility especially in construction
Physical Differences
Mental Differences
Emotional Differences
Individual's capacity for knowledge and understanding as applied in new or changing situations. Reference to the previous job of the employee may help in his evaluation. His performance and ability to comprehend and follow instructions are crucial considerations when assigning a particular work to a certain individual
Physical Differences
Mental Differences
Emotional Differences
Individual's temperament and emotional stability, which can be recognized from the individual in some of the following ways: ability to change the way he/she is doing things if necessary or as called for by the situation, etc
Physical Differences
Mental Differences
Emotional Differences
Formal agreement for the construction, extension, alteration, or repair of buildings or any structures contained in a set of documents
Construction Contract
Working Drawings
General Documents
Material Specifications
Type of contract where contractor bids a single fixed price for overall activities in the project scope. The contractor is responsible for estimating project costs from drawings then adds overhead and his profit to determine the value of the project
Lump-sum Contract
Unit Price Contract
Cost-plus Contract
By Administration Contract
Type of contract where the total price is based on the price of each item's unit. The contactor is paid as per the rates of items specified in the bill of quantity
Lump-sum Contract
Unit Price Contract
Cost-plus Contract
By Administration Contract
Type of contract where the contractor is paid based on the actual cost of the project, including direct and indirect costs, plus a specific fee. This fee could be a fixed fee or a percentage of costs
Lump-sum Contract
Unit Price Contract
Cost-plus Contract
By Administration Contract
Type of contract where the owner/client directly pays all the costs for labor, materials, tools, and equipment rentals and other incidentals such as permits, water, and power consumption on site
Unit Price Contract
By Administration Contract
Turn-key/ EPC Contract
Time and Materials Contract
Type of contract that has common features of the lump-sum and cost-plus contracts. The contractor is paid based on the actual costs plus a certain fee either fixed or percentage of total cost in case of the cost of the project does not exceed certain target cost specified by the owner/client
Target/GMP Contract
Turn-key/EPC Contract
Time and Materials Contract
By Administration Contract
Type of contract where the owner/client pays for the time spent by the builder and his subcontractors and must pay for the actual costs of construction materials
Time and Materials Contract
By Administration Contract
Lump-sum Contract
Unit Price Contract
Type of contract where the contractor takes total resposibility for the engineering design, procurement, and construction and provides a fully equipped facility ready for operation "at the turn of a key"
Target/GMP Contract
Time and Materials Contract
Turn-key/EPC Contract
By Administration Contract
Commonly used way of graphically representing a project schedule that consists of columns and rows, the left column contains the task list and other columns represent time intervals - days, weeks, months or years
Bar/Gantt chart
Velocity chart/S-curve
Line of balance chart
Network diagram CPM
A time-scaled graph based on the value from the planned value, earned value and the actual cost
Velocity chart/S-curve
Bar/Gantt chart
Activity on arrow
Line of balance chart
Time-scheduling technique that is typically used in situations where skilled resources are performing the same activity on multiple products within a project
Line of balance chart
Velocity chart/S-curve
Bar/Gantt chart
Activity on arrow
Time-scheduling technique for analyzing a network diagram. It calculated dates when activities in the network should occur and identified flexibility in the performance of some activities
Network diagram CPM (Critical Path Method)
Line of balance chart
Activity on arrow
Bar/Gantt chart
Activities are represented by a line between two circles where the first circle represents the start of the activity and is known as the start event (i-node) and the second circle represents the finish of the activity and is known as the finish event (j-node)
Activity on arrow
Network diagram CPM
Bar/Gantt chart
Line of balance chart
Calculates the earliest times when activities can occur
Forward pass
Backward pass
Float
Calculates the latest times
Forward pass
Backward pass
Float
Difference between forward pass and backward pass which indicates the degree of flexibility there is in the performance of the activity
Forward pass
Backward pass
Float
CPM
Event-oriented system that did not become successful to construction industry because of the event orientation and the use of three time estimates instead of one
PERT
CPM
ILY
ILYT
An activity-oriented system which used single time estimates and usually start at the beginning and worked to the end of the project
PERT
CPM
IMY
IIRC
Basic procedure in work study method where the job needs to be improved or set up
Select
Record
Examine
Develop