WorksheetsRM4DM
Total questions: 14
Worksheet time: 7mins
Who is responsible for managing risk at QatarEnergy LNG?
Operations & Maintenance personnel
Asset Managers & HOP's
Safety Officers & Loss Prevention Engineers
Everyone
CEO & COO's
How many risk categories are there as per QatarEnergy LNG risk assessment matrix?
1
2
3
4
5
Risks categorized as Red risks should be reduced as soon as possible and communicated immediately within the organization.
True
False
Yellow risks should be reduced unless it is not practicable to do so
True
False
Green risks should be reduced if lower cost options exist to reduce risk levels further
True
False
Process Safety incidents continue to reinforce that Major Accident Hazards (MAH) occur as a result the failures of -----------barriers?
one
two
multiple
three
four
What does the term ALARP mean?
As Low As Possible
As Low As Reasonably Practicable
As Low As Resources Permit
When is a risk reduction measure deemed grossly disproportionate?
If the budget is too high
if the budget is too high and the duration to implement the action is too long
If the cost and efforts to implement the risk reduction measure are too high in comparison to the anticipated benefits
Elimination, Substitution, Separation & Engineering Controls are Preventive Methods of control
True
False
Focusing on Mitigating controls eliminates Hazards
True
False
For RED operations risks (HSE, Financial and Reputation), identify the Accountable Authority level below
COO-2
COO
COO-1
HSEQ Department Manager
For Yellow operations risks (HSE, Financial and Reputation), identify the Accountable Authority level below
COO-1
COO-2
COO
HSEQ Department Manager
What is the Threshold criteria to Initiate an MVT?
Red or Yellow Financial Risk only
Consequence ≥ 1 MUSD and Exposure period
≥ 3 months
All of the above
Likelihood frequencies on the QatarEnergy LNG Matrix are annualized
True
False