WorksheetsBrown Bag Session - June 2022
Total questions: 10
Worksheet time: 4mins
Which one is NOT part of Bukit Tua Phase 2B Project scope?
Host Tie-In Modification at BTJT-A and FPSO
4 Legged Wellhead Platform (BTJT-B) & 5 New Development Wells
A New 8" Liquid Pipeline from BTJT-A to FPSO
A New 16" FWS Pipeline & 6" Gas Lift Pipeline
The new platform BTJT-B is designed to cater 14,700 STB/D liquid production and 60 MMSFCD gas. True or False?
True
False
How many safe man-hours (Zero LTI) has the project achieved up to May 2022?
3 million
4 million
5 million
6 million
PETRONAS initiates intervention programs as part of the effort to achieve safe project execution. Which one is not part of the initiatives?
Leadership Fun Tour
Lead Program
Respect & Care Program
Regular Emergency Drill
Which one is not part of the Respect & Care Program?
Love Letter
LTI Free Board
Welcome Gate
Rewards & Recognition
"To realize Petronas Culture Belief element of Own it! by developing the sense of ownership within PMT, that HSE is everybody’s business through collaborative effort in identifying and rectifying potential hazards on site to create a safer working environment during project execution" is the objective of which program?
Safety Sharing Session/Touch The Heart
LLT (Leadership Listening Tour)
SWAT (Stop Work and Action Taken) Program
LeAD (Leadership on Area Demarcation) Program
Toolbox meeting is a group discussion that focuses on a particular safety issue. These tools is used to promote safety culture as well as to facilitate health and safety discussions on the sites throughout the execution of Bukit Tua Phase 2B. How often the meeting is held?
Daily
Weekly
Bi-weekly
Monthly
Safety Induction is done to cover all HSE matter that related with environment
situation/atmosphere, security issues, hazard and risk that probably occur on respected job site. Who are the target of the induction?
All workers regardless duration of stay on board
All workers who is the first time arrived in the work site.
All workers except Sub-Contractors
Safety Coordinators and Officers
During Installation, Hook-Up and Commissioning of Bukit Tua Phase 2B, who is in charge to be the safety role model and enhance safety behaviour of the team
Lead Hook-Up & Commissioning
Construction Site Representative (CSR)
Appointed Safety Agent
All Staff On-Board
The first well to drill in Bukit Tua Phase 2B Project is T3. True or False?
True
False