Seminar on Project Documentation - QA & QC Procedures

Total questions: 20

Worksheet time: 10mins

Name
Class
Date
1.

A documented proof attesting that the quality of construction materials fails or meets the specifications requirement.

a)

Materials Test Report

b)

Materials Inspection Report

c)

Manufacturer's Certificate

d)

Certificate of Quality Control and Assurance

2.

Specifically, the objectives of calibration are: to check the __________ of the instrument and; to determine the __________ of the instrument.

a)

precision and traceability

b)

accuracy and traceability

c)

accuracy and derivability

d)

mastery and accountability

3.

It is the basic means or a tool by which an engineer or an inspector can use to determine whether the materials should be allowed to be incorporated or be rejected into the works:

a)

Materials Test Report

b)

Materials Inspection Report

c)

Materials Testing

d)

Manufacturer's Certificate

4.

What is the description of DPWH Department Order No. 188, Series of 2022?

a)

Revised Guidelines for the Calibration of Testing Equipment of the DPWH Implementing Offices

b)

Revised Schedule of Fees and Charges for Laboratory Testing of Construction Materials

c)

Standard Forms in Project Implementation

d)

Integration of Quality Assurance Units from Central and Regional Offices and Reconstitution of QAU

5.

The services of accredited private testing laboratories can only be availed by the contractor to test construction materials in behalf of DPWH after securing of what approved document?

a)

Authorization Letter from the Project Engineer

b)

Private Laboratory’s Certificate of Accreditation

c)

Approved Sample Card

d)

Waiver issued by DPWH Testing Laboratory

6.

The following are the causes of the inaccuracy of laboratory testing equipment/apparatus EXCEPT:

a)

Normal Wear and Tear

b)

Electric or Mechanical Shock

c)

Extended Use

d)

Capital

7.

Who must submit construction material sample/s to be tested in the laboratory if it passes or fails the specifications requirement?

a)

The DPWH Materials Engineer/Materials-in-Charge

b)

A Contractor’s Authorized Representative

c)

The Project Engineer

d)

Both The DPWH Materials Engineer/Materials-in-Charge and A Contractor’s Authorized Representative

8.

When is the proper time that the materials testing should be done in a construction of a project?

a)

During the construction stage

b)

After the construction stage

c)

Prior to incorporation into the work

d)

Both during the construction stage and prior to incorporation into the work

9.

This procedure refers to the process of making tests to determine the degree of compliance of delivered or constructed materials with the specifications.

a)

Quality Control

b)

Testing

c)

Calibration

d)

Valuation

10.

In general, calibration improves the accuracy of measuring device, thus, ___________.

a)

improve product quality

b)

earn product savings

c)

reduce product quality

d)

damage person's credibility

11.

Pursuant to __________, as general policy, the use of calibration, laboratory and field testing equipment or apparatus with no or expired calibration certificate shall be strictly prohibited

a)

Department Order No. 184, Series of 2022

b)

Department Order No. 22, Series of 2018

c)

Department Order No. 126, Series of 2016

d)

Department Order No. 253, Series of 2003

12.

A written record used for monitoring and updating day-to-day activities in the project site.

a)

Certificate of Quality Control and Assurance

b)

Quality Control Program

c)

Project Logbook

d)

Inspection Report

13.

The request for calibration shall be submitted at least __________ before the expiration date.

a)

Three (3) months

b)

Two (2) months

c)

One (1) month

d)

Four (4) months

14.

A ___________ provides a snapshot look at a project and provides valuable information in the development of the project execution plan and the assignment of resources to the project.

a)

Key Personnel

b)

Contract Data

c)

Project Description

d)

Project Profile

15.

It is the adjustment or standardization of the accuracy of the measuring instrument/ equipment, usually by comparison with a certified reference or standard.

a)

Estimation

b)

Calibration

c)

Quantification

d)

Valuation

16.

Standard Project Logbook Format:

a)

Department Order No. 21, Series of 2010

b)

Department Order No. 32, Series of 2017

c)

Department Order No. 50, Series of 2020

d)

Department Order No. 46, Series of 2022

17.

Calibration of laboratory testing equipment/apparatus shall be conducted on the following conditions EXCEPT:

a)

According to the Manufacturer's recommendation

b)

Never

c)

Periodically

d)

After any electrical or mechanical shock

18.

Amendments to Department Order No. 55, Series of 1989, re: Submission of Materials Quality Control Reports and Other Related Documents:

a)

Department Order No. 21, Series of 2010

b)

Department Order No. 32, Series of 2017

c)

Department Order No. 50, Series of 2020

d)

Department Order No. 46, Series of 2022

19.

A program of quality control works in a certain project which involve inspection and testing of materials to be incorporated into a work. 

a)

Quality Assurance Program

b)

Quality Control Program

c)

Certificate of Quality Control and Assurance

d)

Inspection Report

20.

Standard Project Forms in Project Implementation:

a)

Department Order No. 21, Series of 2010

b)

Department Order No. 32, Series of 2017

c)

Department Order No. 50, Series of 2020

d)

Department Order No. 46, Series of 2022