1.

What is the minimum basic fee for publishing plants with a project construction cost of P40M?

a)

P 2.4 M

b)

P 2.8M

c)

P 3.2 M

d)

P 3.6M

2.

For a housing project exceeding 10 units, how much is the minimum fee chargeable for each additional unit, excluding the fees for the first 10 units?

a)

20% of basic fee

b)

30% of basic fee

c)

40% of basic fee

d)

60% of basic fee

3.

The multiplier applied in the multiple of direct personnel expense depends on the following except one:

a)

complexity of project office set-up

b)

office set-up

c)

experience of the Architect

d)

cost of transportation

4.

What is the minimum basic fee for public health centers with a project construction cost of P50M or less?

a)

5%

b)

6%

c)

7%

d)

8%

5.

Which group classification belongs projects involving extensive detail such furniture design, built-in equipment, special fittings, screens, counters, interiors and other detailed parts of appurtenances of buildings or structures and landscaping designs?

a)

Group 6

b)

Group 7

c)

Group 8

d)

Group 9

6.

Not a criteria for computing the Architect's compensation.

a)

talent and skill

b)

experience

c)

personal relations

d)

effort and time available

7.

When the Architect as Environmental Planner is commissioned to do town and regional planning or urban renewal projects, he performs the following except one:

a)

undertakes demographic analysis

b)

prepares concept development plans

c)

identifies social behavior and interaction

d)

undertakes environmental impact assessment

8.

Which work item is chargeable to the Owner and not included in the regular scope of services?

a)

miniature models of design studies

b)

extra drafting of changes made by Owner

c)

structural analysis

d)

electrical load calculation

9.

A method of compensation frequently used where there is a continuing relationship on a series of projects.:

a)

multiple of direct personnel expense

b)

percentage of construction cost

c)

professional fee plus expenses

d)

lump sum or fixed fee

10.

How are projects classified in determining the basis for the Architect's Basic Fee?

a)

material specifications

b)

total floor area

c)

degree of project complexity

d)

structural components

11.

Who shall accredit Continuing Professional Development providers?

a)

UAP

b)

Board of Architecture

c)

CHED

d)

schools of architecture

12.

A provision in the Architecture Act of 2004 pertaining to application of a foreign citizen taking the licensure examinations.

a)

non-registered person

b)

prohibition in practice

c)

vested rights

d)

reciprocity requirements

13.

A provision in the Architecture Act of 2004 pertaining to application of a foreign citizen taking the licensure examinations.

a)

signed plans prepared in his/her office by draftsmen

b)

paid only the regular fees in securing Certificate of Registration

c)

aided in unauthorized practice

d)

undertook projects with service agreements

14.

Which is an unethical action with respect to the Architect's responsibility to his client?

a)

undertakes construction for a fixed contract sum under design-build service

b)

does not offer preliminary sketches without an agreement

c)

advises client to forego unviable project

d)

guarantee any estimates or cost of the work

15.

The government architect-of-record shall collect from the concerned national or local agency an incentive pay to cover the civil liabilities in the equivalent amount of ___% of the project cost of every project provided it shall not exceed ___% of his annual salary which shall be paid full completion of the project.

a)

1% / 50%

b)

1.5% / 50%

c)

1% / 80%

d)

1.5% / 80%

16.

Not included in the scope of practice of Architecture.

a)

architectural designing

b)

structural designing

c)

site analysis

d)

quality surveys

17.

Not included in the scope of practice of Architecture.quality surveys

a)

architectural designing

b)

structural designing

c)

site analysis

d)

quality surveys

18.

What percentage of the Architect's Basic Fee is for the liability of the Architect under the Civil Code?

a)

5%

b)

10%

c)

15%

d)

20%

19.

What pre-design service involves investigating, identifying and documenting the needs of the client for use in the design of the project?

a)

Economic Feasibility Studies

b)

Space Management Studies

c)

Architectural Programming

d)

Site Selection and Analysis

20.

This is beyond the specific functions of the Board of Architecture.

a)

enter into a Memorandum of Agreement with CHED

b)

hear and decide civil cases on violations of Architecture Act

c)

approve, issue, limit or cancel temporary permits

d)

adopt an official seal of the Board

21.

Who could be disqualified to become a member of the Board of Architecture?

a)

a resident of the Philippines

b)

a BS Architecture graduate of a recognized American university and passed the local board exam

c)

an architectural practitioner for 5 years

d)

adopt an official seal of the Board

22.

This is not a reason for refusal of registration and removal of name from roster of architects.

a)

misrepresentation in application for examination

b)

convicted of a criminal offense

c)

immoral and dishonorable conduct

d)

conviction for a political offense

23.

This is not a reason for refusal of registration and removal of name from roster of architects.

a)

misrepresentation in application for examination

b)

convicted of a criminal offense

c)

immoral and dishonorable conduct

d)

conviction for a political offense

24.

Which is included in the Architect's Professional Fee?

a)

fees for soil tests

b)

fees for electronic system design

c)

fees for topograhical surveys

d)

fees for mechanical systems design

25.

A method of compensation frequently used where there is a continuing relationship on a series of projects.

a)

multiple of direct personnel expense

b)

percentage of construction cost

c)

professional fee plus expenses

d)

lump sum or fixed fee

26.

If portions of the buildings are erected at different periods of time, thus increasing the Architect's construction period and burden of services, the charges pertaining to services rendered shall be doubled. A suspension of construction for a period not exceeding ____ months shall not be covered by this provision.

a)

3 months

b)

4 months

c)

6 months

d)

9 months

27.

A Master's Degree in Architecture shall be credited how many months in the practical experience required of any person applying for examination?

a)

6 months

b)

12 months

c)

18 months

d)

24 months

28.

Approved form of security furnished by the Contractor and his Surety as a guarantee to the quality of the materials and equipment installed and the workmanship performed by the Contractor.

a)

Payment Bond

b)

Performance Bond

c)

Guarantee Bond

d)

Proposal Bond

29.

The selection of a member of the Board of Architecture will commence with the submission of a list of five nominees submitted by whom?

a)

PRC

b)

DPWH

c)

UAP

d)

DECS

30.

Which of the following services are expected from the architect serving as building/ground administrator?

a)

Building maintenance

b)

Post-construction evaluation

c)

Equipment maintenance

d)

Bidding of tenants for rentals/utilities

31.

When were the 3 architectural organizations integrated into one association of architects called UAP?

a)

1972

b)

1975

c)

1976

d)

1978

32.

Which of the ff. services is NOT performed by the Architect under the design-build service by administration?

a)

Prepares schedule of work, construction program, construction estimate, bill of mat’ls, etc

b)

Keeps records and books of accounts

c)

points construction superintendent, purchasing agent, timekeeper, property clerks, etc.

d)

Advances funding for payment of expenditures connected with work

33.

Which of the ff. services is NOT performed by the Architect under the design-build service by administration?

a)

Per diem plus reimbursable expenses

b)

Professional fee plus expenses

c)

Mixed methods of compensation

d)

Multiple of direct personal expenses

34.

Under what phase of design services does the architect prepare complete construction drawings and specifications on materials/construction methods?

a)

Schematic design

b)

Contract Documents

c)

Construction

d)

Design development

35.

Which of the following describes the percentage of project cost compensation method for architect’s services?

a)

Applicable only to pre-design services

b)

Uses multiplier for overhead and profit

c)

Related to size and type of project

d)

Most commonly used in ASEAN region

36.

What do you call the study which determines the viability of a project, such as the cost of development which brings about a potential return to the owner?

a)

Project study

b)

Financial feasibility study

c)

Economic feasibility study

d)

Project development and evaluation

37.

Which of the following activities is NOT within the scope of project management?

a)

Provides planning, programming, monitoring, advising activities on material costs/construction methods

b)

Economic analysis/project feasibility

c)

Segments, supplements, compliments functions of Architects, Engineers, and Contractor’s

d)

Provides overall control of construction activities

38.

What additional training is required of an Architect for the renewal of his professional license?

a)

Licensure Examination

b)

Post-Graduate Studies

c)

Continuing Professional Education

d)

Development Seminars/Workshops

39.

What PD created the Professional Regulation Commission (PRC) which regulates the practice of various professional in the Philippines?

a)

PD 1096

b)

PD 1185

c)

PD 223

d)

PD 1000

40.

What is the general basis of the Architect’s minimum basic fee?

a)

Architect’s professional standing in the community

b)

Owner’s offer

c)

Type of structure

d)

Project construction cost

41.

What part of Architect’s services is architectural programming

a)

Schematic design

b)

Pre-Design

c)

Design Development

d)

Contract Documents

42.

In a typical owner-architect agreement, which of the following is generally NOT included?

a)

Design and placement of signs

b)

Ownership of documents

c)

Labor contingencies

d)

Arbitration

43.

What part of the Architect services is space/management studies?

a)

Contract documents

b)

Pre-design

c)

Design development

d)

Schematic design

44.

Under the Civil Code, under what condition can the Architect or Engineer be held liable for damages within fifteen years after project completion?

a)

Due to violation of terms of contract

b)

Structure collapse due to faulty construction

c)

Structure collapse due to defects in plans/specification

d)

Structure collapse due to defective materials

45.

Under the Architect’s Code of Ethics with respect to responsibilities to his client , which of the following is unethical for the Architect to do?

a)

Advices client on practicability of the project which may be questionable even if this causes the loss of the project to him

b)

Considers the need of the client and effects of his work upon the life and wellbeing of the public

c)

Offers free preliminary sketches without the benefit of an agreement for legitimate compensatio

d)

Ascertain the exact scope of services with corresponding professional charges

46.

Which of the following is NOT within the scope of the practice of architecture?

a)

City/public administration

b)

Environmental site analysis and design

c)

Feasibility studies, financing, progm’g, promotional studies

d)

Building maintenance & administration

47.

What official body formulates rules and regulations relating to signing / sealing of drawings, specifications and other documents registered by the architect?

a)

United Architects of the Philippines

b)

Commission on Higher Education

c)

Board of Architecture

d)

Office of the Building Official

48.

In a typical owner-architect agreement, which of the following is NOT part of project construction cost?

a)

Plumbing/electrical fixtures/accessories

b)

Landscaping (covered walks, grotto, etc.)

c)

Fire-fighting features

d)

Fixed closets/cabinets

49.

Who advocated the “Virtues of an Architect”, which has been the basis’s of UAP’s principles of the Architect’s Code of Ethical Conduct?

a)

Louis Sullivan

b)

Le Corbusier

c)

Frank Lloyd Wright

d)

Marcus Vitruvius Pollio

50.

In the Architect’s Code of Ethics, to whom does the architect have responsibility to provide for arbitration as a method for settlement of disputes?

a)

Contractor

b)

Public

c)

Manufacturers/dealers

d)

Client