Wayground logo

Free Printable Worksheets

Font size

S
M
L
XL
Worksheets

BT3 EXAMINATION NO.1 MODULE 1

Total questions: 30

Worksheet time: 23mins

Name
Class
Date
1.

the main supporting component of any building structure.

a)

Flooring

b)

Footings

c)

Foundation

d)

Soil

2.

Flooring System provide the structure's stability from the ground.

a)

TRUE

b)

FALSE

3.

What type of Settlement is shown?

a)

Uniform

Settlement

b)

Tipping

Settlement

c)

Downward

Settlement

d)

Differential

Settlement

4.

Construction workers often use this type of foundation when the structure load is relatively low in comparison to the capacity of bearing of the surface soil.

a)

Deep

Foundation

b)

Shallow

Foundation

c)

Mat

Foundation

d)

Raft

Foundation

5.

used when the surface soil's bearing capacity is not enough to support the structure's loads.

a)

Isolated

Footing

b)

Deep

Foundation

c)

Shallow

Foundation

d)

Strap

Foundation

6.

It is one of the simplest and worldwide popular foundations.

Mostly used to support a single column.

a)

Pile

Foundation

b)

Raft

Footing

c)

Isolated

Spread Footing

d)

Combined

Footings

7.

_________ are generally used when there is a heavy load coming from the upper superstructure.

a)

Spread

Footings

b)

Stepped

Footings

c)

Combined

Footings

d)

Cantilevered

Footings

8.

it is a continuous slab that covers the entire area of building a foundation and transfers its weight to the ground.

a)

Mat

Footing

b)

Combined

Footing

c)

Raft

Foundation

d)

Pile

Foundation

9.

What type of Foundation

System is shown?

a)

Pile

Foundation

b)

Drill

Foundation

c)

Caissons

Foundation

d)

Mat

Foundation

10.

It is like a small-diameter column that is driven into or cast in the ground.

a)

Driven

Foundation

b)

Pile

Foundation

c)

Post

Driven

Foundation

d)

Column

Foundation

11.

Composed of a series of linear beams and joists overlaid with a plane of sheathing or decking, or consist of a nearly homogeneous slab of reinforced concrete.

a)

Slab

System

b)

Structural

System

c)

Foundation

System

d)

Floor

System

12.

the primary part of the structural framing system that will carry the load.

They are intended to bend to resist and redistribute the load.

a)

Column

b)

Girder

c)

Beam

d)

Joist

13.

a horizontal structural member used in framing to span an open space,

often between beams.

a)

Girder

b)

Joist

c)

Beam

d)

Column

14.

they are there to support the beams and provide

the main horizontal support for the structure.

a)

Slab

b)

Girder

c)

Joist

d)

Footings

15.

In flat plate system, it is possible to have large span.

a)

TRUE

b)

FALSE

16.

Identify the Given Floor System

a)

Flat Plate

Slab

b)

Slab on

Beam

c)

Flat Slab

Floor System

d)

Waffle

Slab

17.

the term used for the process of creating

a temporary mould into which concrete is poured and formed.

a)

Form

Works

b)

Framing

c)

Bracing

d)

Scaffolding

18.

It consists of uniformly spaced concrete ribs spanning in one direction,

  reinforced concrete slab constructed monolithically with ribs and beams

  which are spanning between columns.

a)

Waffle

Slab

b)

One Way

Joist Floor

System

c)

Two Way

Joist Floor

System

d)

Slab on

Beam

19.

identify the Given type of

Floor System?

a)

Flat Plate

System

b)

One Way

Floor Slab

c)

Slab

on Beam

d)

Flat Slab

Floor System

20.

the degree to which an element of structure

changes shape when a load is applied.

a)

Bending

b)

Deflection

c)

Camber

d)

Deformation

21.

a structure and a surface that defines an area; carries a load;

provides security, shelter, or soundproofing; or, is decorative

a)

Floor

b)

Ceiling

c)

Wall

d)

Roof

22.

This wall is also known as a hollow wall.

They reduce their weights on the foundation.

They act as good as sound insulation. 

a)

Shear

Wall

b)

Panel

Wall

c)

Cavity

Wall

d)

Faced

Wall

23.

The usage of the cavity wall is important,

especially in large and high-rise buildings. 

a)

TRUE

b)

FALSE

24.

 It is a non-bearing wall between columns or pillars that are supported.

a)

Cavity

Wall

b)

Veneered

Wall

c)

Panel

Wall

d)

Partition

Wall

25.

Cast in Placed Concrete is a form of concrete that is prepared, cast

and cured off-site, usually in a controlled factory environment.

a)

TRUE

b)

FALSE

26.

The assemblies are built as per the requirements

specified for the project. 

a)

Prefabricated

Concrete

b)

Pre-cast

Concrete

c)

Cast In Placed

Concrete

d)

Poured

Concrete

27.

are relatively rigid walls used for supporting

soil laterally so that it can be retained at different levels on the two sides.

a)

Masonry

Wall

b)

Stone

Wall

c)

CHB

Wall

d)

Retaining

Wall

28.

Hollow Concrete blocks are composed of Portland cement and aggregate, the high density blocks may use sand and gravel while low density blocks use industrial waste instead of aggregate.

a)

TRUE

b)

FALSE

29.

an Eco-friendly Construction material that

is manufactured by recycled waste and materials

like coal ash, rice husk, and fly ash.

a)

CHB

b)

Hollow

Brick

c)

Solid

Brick

d)

Engineered

Brick

30.

Identify the Given Type

of Wall Concrete Construction.

a)

Drywall

Construction

b)

CHB Wall

Construction

c)

Poured Concrete

Wall Construction

d)

Metal Framed

Wall Construction