This is a LOLER S***

Total questions: 10

Worksheet time: 4mins

Name
Class
Date
1.

When did LOLER come into force?

a)

5th December 1998

b)

5th December 1899

c)

1st January 1974

d)

5th December 2021

2.

What is PM28 specific to?

a)

Working Platforms

b)

Working Platforms of forktrucks

c)

MEWPS

d)

Working Platforms for engineers

3.

The ACoP that refers to LOLER has what leaflet number?

a)

L111

b)

L112

c)

L1133

d)

L113

4.

When lifting equipment is not appropriately marked, what percentage should equipment used for lifting people be de-rated by?

a)

25%

b)

75%

c)

50%

d)

45%

5.

What piece of equipment does not come under LOLER?

a)

Roller shutter door

b)

Vehicle Lift

c)

Passenger Lift

d)

Pallet truck

6.

What is the British Standard for the same working of Lifts?

a)

BS 7255

b)

BS 1493

c)

BS 7121

d)

ISO 12480

7.

Who is responsible for deciding whether a load test is needed?

a)

Competent Person

b)

Equipment manager

c)

Workshop manager

d)

Third party engineer

8.

According to LOLER regulation 8 every employer should ensure every lifting operation is... what?

a)

Properly planned by a competent person

b)

Appropriately Supervised

c)

Carried out in a safe manner

d)

Carried out by a skilled operator

9.

What LOLER regulation relates to regulation 23 of PUWER?

a)

11

b)

6

c)

3

d)

7

10.

In normal circumstances what is the timeframe to complete a report of thorough examination and to forward it on to the client?

a)

3 days

b)

7 days

c)

28 days

d)

42 days