Ms Project - Pretest

Total questions: 10

Worksheet time: 15mins

Name
Class
Date
1.

How do you create a Project file?

a)

Open the application, select File then select New from the application menu

b)

Open the application, then press Ctrl + N

c)

Open Windows Explorer, find my official corporate template or latest updated project file then copy it to a new file, and then double click to open

d)

Open the application, select File then select Open

2.

Which of the following is the first thing you usually do after opening your named project file?

a)

Enter the task name

b)

Enter the Project Start Date

c)

Check calendar, change my Project Status Date and Project Current Date

d)

Close the Application

3.

Which of the following is your typical way of creating new task?

a)

Type the name of the tasks under Task field

b)

Select a task, in Task tab click Insert New Tasks

c)

Copy the list of tasks from email approved by my customer then paste them to Task field

d)

Click Inspect Button

4.

Which of the following is your typical way of scheduling tasks?

a)

Enter Start Date and Finish Date for each task in my project

b)

Enter only Start Date and Duration for each task in my project

c)

Obtain Project Start Date from approved Project Charter and put it in Project Information, then enter tasks with their respective durations, then link the tasks using their respective relationships, ensuring all tasks are automatically scheduled

d)

Select a task, in Task tab click Insert New Tasks

5.

How do you usually assign Work and Material Resources in your project?

a)

Create resource in Resource Sheet, select task in Gantt Chart then Assign Resource in Resource Tab, select a resource then click Assign

b)

Create resource in Resource Sheet, select task in Gantt Chart then Assign Resource in Resource Tab, select a resource and type the assignment unit in % or number

c)

Create resource in Resource Sheet, right click a task in Task Usage then select Assign Resource, select a resource and type the assignment unit in % or number

d)

Create new project, list the Tasks in Gantt Chart, list the Resources in Resource Sheet, assign the appropriate resource to tasks, then in Project Tab click Set Baseline

6.

How do you usually assign Cost Resource?

a)

In Gantt Chart, insert Cost column and type the cost for that task

b)

Create resource in Resource Sheet, select task in Gantt Chart then Assign Resource in Resource Tab, select a resource and type the cost

c)

Create resource in Resource Sheet, right click a task in Task Usage then select Assign Resource, select a resource and type the cost

d)

Create new project, in Project Tab click Set Baseline

7.

How do you create baseline?

a)

Create new project, in Project Tab click Set Baseline

b)

Create new project, list the Tasks in Gantt Chart, list the Resources in Resource Sheet, assign the appropriate resource to tasks, then in Project Tab click Set Baseline

c)

Create new project, list the Tasks in Gantt Chart, list the Resources in Resource Sheet, assign the appropriate resource to tasks, level if any resource is over-allocated, then in Project Tab click Set Baseline

d)

In Gantt Chart, click Task tab and for each task click Mark on track

8.

How do you update your project?

a)

In Gantt Chart, I click Task tab and for each task I click Mark on track

b)

In Gantt Chart, I click Task tab and for each task I click Update Task, enter the % complete, Actual Start and Actual Duration

c)

In Project Tab, select Project Information and update the Status Date and Current Date, then in Task tab and for each task I click Update Task, enter the % complete, Actual Start and Actual Duration, then in Project Tab I click Update Project and select Reschedule uncompleted work to start after the Status Date

d)

In Gantt Chart, insert Cost column and type the cost for that task

9.

How do you update your Cost Resource?

a)

In Gantt Chart, view the Entry table, insert Cost column and type the real cost

b)

In Gantt Chart, view the Tracking table, in Actual Cost column type the actual cost

c)

In Task Usage, select the Cost Resource of the task to be updated, then insert Actual Cost, and type the actual cost

d)

Create new project, in Project Tab click Set Baseline

10.

How do you share your project reports to the stakeholders?

a)

Print the Gantt chart (the schedule) and send one set of hardcopy to each stakeholder

b)

Create screen of the Gantt chart and send it along with the MPP file to the stakeholders by email

c)

Create screen of the Gantt chart or Earned Value chart or S-Curve, copy them to PowerPoint and save them as a PDF file, or make a PDF copy of the Project file; then send them to stakeholders by email; schedule routine project progress review meeting, make presentation of the project and present the progress in the review meeting

d)

Type the name of the tasks under Task field