NEW
Font size
Worksheets07. Cost Management
Total questions: 12
Worksheet time: 10mins
You recently submitted a change request to the change control board (CCB) for an updated communications management plan to include more frequent and detailed project status updates with the intent of addressing declining stakeholder engagement.
Where is the best place to find the decision status of the change request?
Change Log
Project Charter
Stakeholder Register
Lesson Learned Register
A project manager determines that actual costs to date are $5M and then estimates that approximately $4M will still need to be spent to complete the project for a total anticipated expenditure of $9M. However, the budget for the project is only $8.5M, which is a projected variance of -$0.5M. The anticipated expenditure of $9 M is documented and reported to stakeholders according to the communications management plan.
What has been reported to the stakeholders?
Estimate to complete
Cost Baseline
Estimate Activity Duration
Cost forecast
1During the evaluation of the project's financial statements at the end of a project phase, concerns about some of the charges were raised. The project manager explains that the costs were justified early in the project and as the project progressed.
Which of the following is the best input for the project manager to provide for reconciliation?
Basis of Estimates
Assumption Log
Project Charter
Cost Baseline
The project charter for a cross-functional project has already been approved. The project manager wants to identify stakeholders as soon as possible so that the project planning can start. The project manager quickly creates a document listing the project manager, project sponsor, and the project customer as the only project stakeholders. What has the project manager done wrong?
The project manager has done nothing wrong, as the people that are documented are all project stakeholders.
The project manager did not identify all of the project stakeholders
The project manager should have identified all project stakeholders before the approval of the project charter.
The project manager should have done this exercise after developing the project management plan
Which of the following statements about the planned value, the earned value, the schedule variance, and the cost variance of a project is false?
The cost variance is the difference between the earned value and the actual cost.
The schedule variance is the difference between the earned value and the planned value.
The planned value is the budget authorized for the work to be performed
The earned value is the value of work to be completed in terms of the approved budget.
You have taken over as Project Manager for a project that has had issues delivering on time. You review Earn Value Management and find the corresponding SPI and CPI value are 0.86 and 1.12 You advice the Project Sponsor , who ask you to bring project back on track within the next two months. What will you do next?
Apply schedule crashing to bring project back on track.
Apply Fast Tracking to bring project back on track.
Update Risk Register and assign the project failure to Executive with the power to bring it back on track
Reduce the project scope to bring the project back on track.
