1.

Which of the following is involved in a taking-off process?

a)

Measure dimensions from drawings

b)

Measure dimensions and write descriptions

c)

Write descriptions

d)

Measure dimensions, write descriptions & squaring of dimensions

2.

The following are the purposes of Bills of Quantities, except:

a)

To provide a basis for tendering

b)

to provide a basis for interim certificate

c)

To provide a basis for valuing variations

d)

To assist a QS to organise his work

3.

What is the usage of Column 1 in a dimension papers?

a)

Writing descriptions

b)

Timesing

c)

Squaring

d)

Entering of dimensions

4.

A BQ can be use to provide a basis for feedback of information for the building user. True or False?

a)

TRUE

b)

FALSE

5.

Which is the correct order of dimensions as stated in SMM General Rules A.1.4?

a)

Width-length-thickness

b)

Height-length

c)

Depth-width-length

d)

Length-width-height

6.

The following are the methids to make alterations to dimensions/items, except:

a)

to 'nil' rhe item/description

b)

to write the word 'nil' in the squaring column against the dimensions

c)

'cross-out' the whole page

d)

'cross-out' the original figures and neatly write the new figures above it

7.

Girth calculation is usually applicable for the following items, except:

a)

Strip foundation

b)

External wall

c)

Perimeter drain

d)

Floor finishes

8.

What is the correct maximum depth to be used if the depth of a trench excavation is 1500mm?

a)

max depth n..e. 0.25m

b)

max depth n.e. 2.00m

c)

max depth n.e. 1.00m

d)

max depth n.e. 1.50m

9.

Which is INCORRECT about measuring Formwork?

a)

To measure the actual surface in contact with concrete

b)

Formwork shall be grouped according to categories

c)

Formwork n.e. 1.00m high to be given in linear metre

d)

Formwork to edges and faces of foundation exc. 1.00m high to be given in m3.

10.

Excavate to reduce level is to be given in square metre. True or false?

a)

True

b)

False

11.

All concrete members to be given in cubic metre.

True or False?

a)

True

b)

False

12.

The following should be measured separately for Curved on Plan, except:

a)

Brickwall

b)

Concrete work

c)

Trench excavation

d)

Formwork

13.

Horizontal DPM: if over 300mm thick to be given in m3; if not exceeding 300mm to be given in m2 and state tthe average thickness

a)

True

b)

False

14.

The following should be described in brickwork, except:

a)

height of the wall

b)

mortar composition

c)

thickness of wall

d)

types of bricks

15.

PROJECTION: when length on plan is more than 4 times of its thickness.

True or False?

a)

True

b)

False