WorksheetsCMA 490 - Chapter 1 Review
Total questions: 15
Worksheet time: 8mins
Project ___ is the planning, organizing, managing, and controlling of the resources required to complete a project.
finance
restructuring
turnover
management
___ are standard procedures that have been learned, adapted, and applied based on the experience of team members and participants constructing other construction projects.
Best practices
Operational processes
Continuous improvement
Work breakdown structures
The ___ BIM is used as the basis for maintenance systems and building automation systems.
4D
6D
as-constructed
completed-project
___ management is a management style in which problems or opportunities are addressed before they occur.
Reactive
Proactive
Passive
Interactive
A ___ risk is a risk that is known, but it cannot be determined whether or when it will occur and to what extent.
known-unknown
unkown-known
known-known
unkown-unknown
The project ___ is the path that a construction project takes from initiation to completion.
work breakdown structure
life cycle
schedule
scope
The four primary project constraints that are used in project management theory are ___.
time, cost, quality, & scope
time, cost, quality, & expertise
weather, cost, quality, & scope
time, safety, quality, & security
___ is the magnitude of the project and the work that encompasses it.
Cost
Time
Quality
Scope
___ on construction sites is linked to the other constraints listed, but it is something that should not be negotiable or given a choice of flexibility.
Cost
Safety
Quality
Scope
SMART goals are goals that are specific, ___, achievable, relevant, and time-oriented.
moderate
milestone-based
manageable
measurable
A ___ is a list of the tasks required to construct a project, the expected durations to complete the tasks, the relationship between the tasks, and the dates that work on the tasks is expected to start and finish.
work breakdown structure
project plan
schedule
punch list
The ___ schedule is also known as the actual schedule because it reflects the actual progress on a project.
bid
look-ahead
baseline
master
A slight delay is called a ___.
lag
float
lead
slack
___ is the amount of time an activity can be delayed before it affects the completion date of another activity.
Baseline
Float
Lead
Lag
A(n) ___ is a point in time on the project schedule that has no duration, is easily recognizable, and is significant.
activity
phase
milestone
block