MYCESMM2 - CLASS E & F

Total questions: 14

Worksheet time: 14mins

Name
Class
Date
1.

CLASS E in MYCESSM2 refers to Demolition and Site Clearance.

a)

TRUE

b)

FALSE

2.

Water bodies shall consist of, but not limited to, rivers, lake and sea, unless expressly required.

This Definition rules refers to ....

a)

E110, D1

b)

E120, D3

c)

E100, D3

d)

E120, D4

3.

The project site clearance include 20 nos between 2.0 - 3.0 m girth of tree.

Choose the suitable code of MYCESMM2 for this activities. ​ ​

​ ​ (a)  

Choose from the below words
E230
E210
E220
E240
4.

The below rules applied to E311 EXCEPT

a)

D5

b)

D6

c)

A5

d)

A7

5.

For Code E800, the additional rules applied is

a)

A1

b)

A2

c)

A3

d)

No Additional Rules Applied

6.

Construction Activities ; Stripping of top soil is under MYCESMM2 Class ​ ​ (a)   ​ (b)  

Choose from the below words
F
111
E
R
H
110
100
7.

Excavation to remove Unsuitable Material refers to below EXCEPT

a)

stumps

b)

large amounts of roots and grass

c)

earth

d)

rubbish

8.

Excavating for pile cap and group of piles as shown in the picture are under

a)

Earthworks; Cut to Filling; Earth

b)

Earthworks; Foundation; Earth

c)

Earthworks, Cut and Dispose; Earth

d)

Earthworks; Fillings; Replacement

9.

Excavation Ancillaries; Timber Support left in refers to code ​ ​ (a)  

Choose from the below words
F220
F200
F239
F230
F330
10.

TOTAL CUT = 1900M3

TOTAL USM = 520M3

TOTAL FILL = 2100M3

The volume for imported materials required is ​ ​ ​ (a)  

Choose from the below words
720
200
1380
520
11.

Match the following

F311

Close Turfing

F410

Excavation and disposal of rock using explosion

E211

Excavation of earth, including transportation, storage at site and filling

F133

Filling of material borrow pit from site

12.

Material from Filling from borrow pit on the site is labelled as​ (a)  

Choose from the below words
Excavated Material
Mass Concrete
Imported Material
Other stated material
13.

MyCESMM2 (2018) stands for ‘Malaysian Civil Engineering Standard Method of Measurement (2nd revision)’

a)

True

b)

False

14.

Hydroseeding includes RULES ​ (a)   ​ (b)   ​ (c)   ​ ​ (d)  

Choose from the below words
M31
M32
A21
A24
M34
A23
A20
C15