Wayground logo

Free Printable Worksheets

Font size

S
M
L
XL
Worksheets

Critical Path Method (CPM)

Total questions: 13

Worksheet time: 4mins

Name
Class
Date
1.
What is critical path method (CPM)
a)
a step-by-step project management technique for process planning that defines critical and non-critical tasks
b)
a graphical display of project activities that helps the users understand the relationships among the activities.
c)
a project management tool to illustrate how the project will run.
d)
A graphical colourful displayed graph
2.

It determines the earliest time each activity can start and finish and determines the total duration of the project.

a)

Forward Pass

b)

Backward Pass

c)

Side Pass

d)

Critical Path

3.

It determines the latest time each activity can start and finish without delaying completion of project. It also helps determine the activities that can be delayed or not.

a)

Forward Pass

b)

Backward Pass

c)

Side Pass

d)

Critical Path

4.

What is CPM?

a)

critical process method

b)

critical path activity

c)

Critical path method

d)

critical process activity

5.

Critical path in network gives ___ to complete the project.

a)

Critical time

b)

Longest time

c)

Shortest time

d)

Production time

6.

In Critical Path Method, the project completion period is the EF of last activities.

a)

True

b)

False

7.

Changing the duration of a critical activity will not affect the overall completion time.

a)

True

b)

False

8.

The starting activities that have no predecessor cannot be carried out in parallel.

a)

True

b)

False

9.

Changing the duration of a non-critical activity will not affect the overall completion time, provided the revised float is positive.

a)

True

b)

False

10.

The backward pass calculation cannot proceed if the forward pass had not completed.

a)

True

b)

False

11.

The critical path activities can be identified only after all the floats were determined.

a)

True

b)

False

12.

To start the backward pass computation, the LF is equal to EF for the last activity.

a)

True

b)

False

13.

In Critical Path Method, the project completion period is the sum of all of all activities duration.

a)

True

b)

False