WorksheetsCritical Path Method (CPM)
Total questions: 13
Worksheet time: 4mins
It determines the earliest time each activity can start and finish and determines the total duration of the project.
Forward Pass
Backward Pass
Side Pass
Critical Path
It determines the latest time each activity can start and finish without delaying completion of project. It also helps determine the activities that can be delayed or not.
Forward Pass
Backward Pass
Side Pass
Critical Path
What is CPM?
critical process method
critical path activity
Critical path method
critical process activity
Critical path in network gives ___ to complete the project.
Critical time
Longest time
Shortest time
Production time
In Critical Path Method, the project completion period is the EF of last activities.
True
False
Changing the duration of a critical activity will not affect the overall completion time.
True
False
The starting activities that have no predecessor cannot be carried out in parallel.
True
False
Changing the duration of a non-critical activity will not affect the overall completion time, provided the revised float is positive.
True
False
The backward pass calculation cannot proceed if the forward pass had not completed.
True
False
The critical path activities can be identified only after all the floats were determined.
True
False
To start the backward pass computation, the LF is equal to EF for the last activity.
True
False
In Critical Path Method, the project completion period is the sum of all of all activities duration.
True
False