wayground logo

Free Printable Worksheets

Font size

S
M
L
XL
Worksheets

Topic 1- Introduction to estimating

Total questions: 10

Worksheet time: 9mins

Name
Class
Date
1.

What is Gross Floor Area (GFA)?

a)

All the spaces

b)

All the enclosed spaces

c)

All covered spaces

d)

All open spaces

2.

Enclosed spaces are spaces have ​1)______, 2)_______ and ​ 3)________.

a)

floor

b)

ceiling

c)

enclosing wall at all side

d)

roof

e)

internal wall

3.

Are columns and balustrades considered as enclosing walls?

a)

yes

b)

no

4.

When measure GFA, sloping surfaces such as staircases shall be measured...

a)

Sloping as per real measurement

b)

Flat on plan

5.

Opened roof top carparks are calculated as GFA?

a)

Yes

b)

No

6.

Your name

4 lines
7.

What is the role of planning engineer in estimating?

a)

Report on the technical & financial progress to estimator

b)

Provide most economic sources for the supply of materials and plant, get quotations

c)

Prepare programme, temporary work designs, organisational chart

d)

Prepare BQ, examine amendments, set up agreements, assess risks

8.

Why first estimate is very important?

a)

Used to decide whether the project should be proceeded or not.

b)

Important to construct the building.

c)

Used to compare with subsequent estimate.

d)

As basis to allocate budget.

9.

During tendering stage, subcontractor will submit a quotation to main contractor, hence they need to perform an estimate. Which of the following is not the reason why they need to perform an estimate?

a)

to prepare BQ and specification for the project

b)

to have an idea of what is involved in the project

c)

to know at what stages they will be needed

d)

to justify how long it will take to complete their work

e)

to know how many workers and how much equipment

10.

Which of the following is not important when we decide which estimating methods to be used?

a)

The amount of information available during estimating stages

b)

The duration given to perform estimate

c)

The cost data information available in the company

d)

The project location