Asphalt Estimating

Total questions: 17

Worksheet time: 9mins

Name
Class
Date
1.
What is used to figure long distances that need to be paved along the highway?
a)
Estimating tonnage
b)
Surveying
c)
Stationing
d)
Distance calculations
2.
If you began paving at station 1850+25.00 and by 3:00 you were at station 2160+50.00, how many feet were paved?
a)
30,250'
b)
31,025'
c)
32,500'
d)
33,010'
3.
What is 1/2 of the total distance across the center of a circle?
a)
pi
b)
Diameter
c)
Radius
d)
Circumference
4.
If you began paving from station 2854+30.00 to station 3265+78.00, how many feet were paved?
a)
41,148
b)
41,543
c)
41,854
d)
42,018
5.
What is the square yardage of the area?
a)
9,450 sq. ft.
b)
7,725 sq. ft.
c)
6,750 sq. ft.
d)
8,750 sq. ft.
6.
If you need to order 700 tons of asphalt for a job and want to have 10% extra, how many tons should you order?
a)
770 tons
b)
760 tons
c)
750 tons
d)
780 tons
7.
If the application rate for your job was 0.09 gallons per square yard and you had 45,025 square yards to cover, how many gallons of tack are needed?
a)
4,550.75
b)
4,250.50
c)
4,052.25
d)
4,425.75
8.
Refer to the following figure. How many square yards are in the area?
a)
277.77 sq. yd.
b)
100.75 sq. yd.
c)
25.52 sq yd.
d)
227.55 sq. yd.
9.
If you began paving at station 2854+30.00 and by 4:00 you were at station 3265+78.00, how many feet were paved?
a)
32,500'
b)
33,010'
c)
31,025'
d)
30,250'
10.
Refer to the following figure. How many square feet are in the area?
a)
150 sq. ft.
b)
2,500 sq. ft.
c)
500 sq. ft.
d)
5,000 sq. ft.
11.
What is the square footage of the area?
a)
1,041.67 sq. yd.
b)
975.54 sq. yd.
c)
850.75 sq. yd.
d)
775.00 sq. yd.
12.
You are paving a 12-foot lane 2" deep using 4000 lb. asphalt. The paver is moving at 10 feet per minute. How much asphalt will you use in an hour?
a)
90.58 tons per hour
b)
80.657 tons per hour
c)
110.324 tons per hour
d)
100.342 tons per hour
13.
What is the basic unit of measure for asphalt?
a)
The square yard
b)
The square foot
c)
The pound
d)
The ton
14.
If you paved from station 1850+25.00 to station 2160+50.00, how many feet were paved?
a)
30,250'
b)
31,025'
c)
33,010'
d)
32,500'
15.
How much extra asphalt is usually ordered to allow for loss?
a)
10%
b)
5%
c)
20%
d)
15%
16.
How much asphalt is needed for a parking lot that is 400' long by 200' wide, 4" deep with 4000-pound asphalt?
a)
1,975.29 tons
b)
1,557.00 tons
c)
2,075.22 tons
d)
1,000.75 tons
17.
You need 150 tons per hour. Your trucks can haul 20 tons each and it takes them an average of 2 hours to make the round trip from the jobsite to the plant and back. How many trucks will you need?
a)
20 trucks
b)
10 trucks
c)
15 trucks
d)
25 trucks