PMI BC Quiz 1

Total questions: 45

Worksheet time: 45mins

Name
Class
Date
1.

A customer is considering appending new features to the project deliverable. Before a project team member begins working on these new features, which is a mandatory step?

a)

Gain approval from the Project Manager

b)

Gain approval from the Project Sponsor

c)

Ensure the change control board (CCB) approves

d)

Ensure key subject matter experts (SMEs) approve

2.

A project is at the planning stage of the project. The Project Manager realizes that producing a complicated multi-functional application is not feasible with the current resources and decides to hire more resources to produce the application. The Project Manager identifies and contracts short-term resources. Which of the following risk response strategy represent this scenario?

a)

Mitigate

b)

Transfer

c)

Accept

d)

Avoid

3.

A Project Manager has performed the following steps:

I. Finished a major IT deployment project.

II. Confirmed with the release manager that all systems are working.

III. Confirmed that functionality has been verified by the quality assurance team.

IV. Informed the customer.

Which of the following is the next step the Project Manager should take?

a)

Update the risk register, stakeholders, and team members

b)

Add the lessons learned to the organization knowledge base

c)

Ensure that the procurement plan is closed out

d)

Review, verify, and complete the release documentation

4.
After realizing that a lack of resources on a project with an increasingly high workload, management outsources some significant tasks to keep the project on schedule. What should the Project Manager do in this situation?
a)
Revise the procurement management plan
b)
Review the communications management plan
c)
Escalate to the project sponsor
d)
Prepare an organizational chart
5.
A project has the following need: I. Nine hundred resource hours must be outsourced. II. Because of internal policies, all providers must be provided with the same information about the requirements. Which of the following action should the Project Manager take to ensure this?
a)
Hold direct negotiations with each provider
b)
Ensure the procurement management plan is sent to each provider
c)
Conduct a bidder conference with the providers
d)
Have each of the providers added to the stakeholder register
6.
A company has a goal of increasing customer satisfaction within four months. A project is initiated to meet this goal. The Project Manager needs to identify best practices. Which of the following, the Project Manager should utilize to achieve this?
a)
Benchmarking
b)
Interviews
c)
Facilitation
d)
Affinity diagram
7.
When a customer identifies performance issues with this product, a new product is released. The Project Manager realizes that cost of quality (COQ) should have been used to estimate this cost. Which of the following category of COQ should the Project Manager have used?
a)
External failure costs
b)
prevention costs
c)
Appraisal costs
d)
Cost-benefit analysis
8.
The Project Manager is conducting a risk analysis based on a high-level scope and using expert judgement to prepare a document. What is the Project Manager doing, based on the description of the activity?
a)
Creating the project management plan
b)
Preparing a project scope statement
c)
Preparing a risk management plan
d)
Creating a project charter
9.
A Project Manager realizes that stakeholder interests will conflict on a project and decides to utilize a stakeholder engagement assessment matrix. The matrix pinpoints an influential stakeholder who is contrary to the project. The Project Manager requires to align this stakeholder's expectations. What should the Project Manager do to achieve this goal?
a)
Convey the stakeholder engagement plan
b)
Produce a stakeholder engagement plan
c)
Gain consensus on project objectives by meeting with all stakeholders
d)
Ensure that the stakeholder register is complete and updated
10.
A medium-sized company is developing into a new market. However, the company does not have prior experience in that market. A Project Manager needs to collect requirements. Which of the following two tools or techniques should the Project Manager apply? I. Product analysis. II. Create requirements traceability matrix. III. Prototypes. IV. Expert judgment.
a)
I and II only
b)
III and IV only
c)
I, II, and III only
d)
I, II, III, and IV
11.
A Project Manager has local and virtual team members for a project. To manage scheduling priority conflicts among team members, the project manager schedules a video conference call. Which statement is correct regarding this scenario?
a)
It demonstrates the Smooth/Accommodate conflict resolution technique
b)
It demonstrates the Force/Direct conflict resolution technique
c)
It is an example of the Collaborate/Problem Solve conflict resolution technique
d)
It is an example of the Compromise/Reconcile conflict resolution technique
12.
What should the Project Manager do to gain a stakeholder's approval if the stakeholder believes a project's deliverables were not accomplished?
a)
Review the project charter thoroughly with this stakeholder on a conference call
b)
Ensure that the stakeholder understands the quality management plan
c)
Perform a risk analysis after obtaining the stakeholder's new requirements
d)
Review the project scope while analyzing the stakeholder's needs and expectations
13.
A client's employee asks the Project Manager for an additional, new product feature during a status meeting. Which document should the Project Manager first refer to find out who has the power to approve this request?
a)
Change log
b)
Change management plan
c)
Responsible, accountable, consult, and inform (RACI) matrix
d)
Change request document
14.
Review the following steps. I. A project has been successfully delivered. II. The project manager is executing formal closure. III. ______________________________________. Which of the following is the Step 3?
a)
The Project Manager should obtain stakeholder acceptance
b)
The Project Manager should update the bid documents
c)
The Project Manager should reassign the project team
d)
The Project Manager should reallocate the unused funds
15.
Review the following project characteristics: I. The project is in initiation. II. Due to lack of funding, the project gets terminated. III. The Project Manager must close the project. Which of the following is the first action the Project Manager should take?
a)
Determine the potential impact of terminating the project by performing a risk analysis
b)
Rely on the communications management plan to properly inform all stakeholders
c)
Examine the organization's project closure guidelines
d)
Close all project procurement processes
16.
A Project Manager is attending a periodic review with stakeholders. The project sponsor asks the project manager how deliverables will be verified for accuracy and accepted. In which project document is this information found?
a)
Quality management plan
b)
Scope management plan
c)
Work performance reports
d)
Requirements management plan
17.
A project is being planned in a remote area with limited access to vehicles and equipment. A Project Manager suggests that the company deliver all heavy equipment themselves despite the significant expense. The Project Manager will take full accountability for this activity. Which of the following type of risk response is the Project Manager demonstrating?
a)
Transfer
b)
Mitigate
c)
Accept
d)
Avoid
18.
A client brings a Project Manager into a project during the execution stage of the project. The Project Manager reviews the project scope for cost estimating purposes and notices that some deliverables were missed in the work breakdown structure (WBS). Which of the following step should the manager take next?
a)
Verify with the stakeholders to see if these missed deliverables should be added
b)
Determine whether these deliverables are necessary by verifying with experts in the field
c)
Ask that the project management office (PMO) approve additional funds for this work
d)
Include the work in the WBS, per the 100% rule, and recalculate the total project cost
19.
A Project Manager is working with three key stakeholders. Every stakeholder has a different vision of the project and its goal. They all feel strongly about their opinion. The Project Manager requires to get approval of the project charter. What should the Project Manager do?
a)
Use facilitation and conflict management to ensure the three stakeholders are in agreement
b)
Conduct a stakeholder analysis
c)
Request that the project sponsor resolve the conflict
d)
Use the project kick-off meeting to settle the project goals
20.
Review the following project characteristics: I. A sponsor approves a project. II. The Project Manager asks chosen team members, key stakeholders, and the sponsor to a meeting. III. The primary goal of the meeting is to create a document that will guide the team in defining the main project deliverables. Which of the following will be the final output of this meeting?
a)
Work breakdown structure (WBS) dictionary
b)
Scope management plan
c)
Milestone list
d)
Requirements management plan
21.
A project team collected sensitive client data early on in the project to help in developing the project management plan. The team is now working on deliverables for the project. The compliance manager proposes an issue of project non-compliance. Which of the following is the first document the Project Manager should review in this case?
a)
Business case
b)
Statement of work (SOW)
c)
Risk register
d)
Issue log
22.
Suppose a project is underway and is 50% completed. An essential project team member requests 1.5 months leave for personal matters. What will be the Project Manager do first in that case?
a)
Assess how the leave will impact the project
b)
Check with this team member to see if the leave can be postponed
c)
Discuss the issue with the functional manager and request a replacement
d)
Refer to the resource management plan
23.
A Project Manager operates for a company that is planning to develop a new product. The new product will need currently unavailable skills. To start this project, what will the Project Manager do?
a)
Develop detailed project requirements
b)
Document the risk in the project charter
c)
Focus on quality control
d)
Develop a competitor analysis
24.
A Project Manager is doubtful about the project duration for a new product and consults several subject matter experts (SMEs). The first group suggests that it can be finished in 25 days. The second group identifies some risks that could make the duration up to 40 days. The third group offers a new method that can shorten the time to 10 days. Using the triangular estimating technique, what is the duration of the new project?
a)
23 days
b)
30 days
c)
25 days
d)
27 days
25.
A new product development project has the following characteristics: I. There are three main tasks. II. Task A must be delivered four weeks before task C starts. III. Once task B is finished, task C will start. What is the relation between A and B tasks?
a)

mandatory Start-to-start (SS)

b)

the default relationship Finish-to-start (FS)

c)

very rarely used Start-to-finish (SF)

d)

No inference given but it can be Finish-to-finish (FF)

26.
A product deliverable is undergoing acceptance testing. A senior-level stakeholder raises concern that an essential product feature for their department was not developed. The Project Manager wants to avoid this issue in the future. What is one method to achieve this goal?
a)
Prepare a change management plan
b)
Ensure a scope management plan gets approved
c)
Properly manage stakeholder expectations
d)
Hold a product demo with stakeholders
27.
A skincare company reports that customers are increasingly complaining that a product is underweight. A Project Manager needs to determine if something needs to be changed in the production line. Which of the following tool or technique can the Project Manager use for this task?
a)
Control chart
b)
Scatter diagram
c)
Histogram
d)
Affinity diagram
28.
A product passes 96% per cent of the functional requirements defined in the scope. However, a customer is unwilling to accept the product since it did not pass 100%. A Project Manager is assessing what could have been done differently to avoid this. What should the Project Manager have done?
a)
Assessed and evaluated the test management plan
b)
Reviewed the requirements documentation
c)
Ensured that the quality metrics were defined
d)
Created the work breakdown structure (WBS)
29.
A Project Manager is working on a data center migration project and is developing the schedule management plan. Per the project sponsor's request, the schedule must plan for all tasks as soon as possible. Additionally, the Project Manager is presented with modified resource availability that should not violate schedule constraints. The Project Manager needs to select the appropriate leads and lags relationship for this situation. Which of the following type should the Project Manager choose?
a)
Early start equals the late start in all activities
b)
Early start is smaller than the late start in all activities
c)
Early start equals the late start in some activities
d)
Early start is smaller than the late start in some activities
30.
A Project Manager is preparing the charter for a project. The project aims to automate 30 per cent of product testing. The project sponsor advises the Project Manager to assign senior test engineers to identify the tests that can be automated. However, the test department manager is uncooperative because they believe that the project will downsize in their department. What should the Project Manager do first?
a)
Request for the project sponsor to provide a rationale for test automation
b)
Have a meeting with the test department manager to review the statement of work (SOW)
c)
Raise the risk that the senior testing engineers will be unavailable for the testing
d)
Present data-driven, cost-benefit evidence of test automation to the test department manager
31.
A project has the following characteristics: I. Is in the process of completing the planning stage. II. A key stakeholder will be unavailable for 2.5 weeks during the project. The Project Manager must decide what to do first, after learning about the key stakeholder's unavailability. Which of the following is the correct step to take?
a)
Request that the finance department provide a replacement during the stakeholder's absence
b)
Continue with planning, and acknowledge the impact the change may have on the project schedule
c)
Ensure that the issue log is updated and inform the other stakeholders
d)
Organize a meeting with the sponsor to evaluate the situation and identify alternatives
32.
The project has the following characteristics: I. It is in the execution stage. II. A regulatory law has recently been approved that mandates immediate compliance. III. This law will impact the project's scope, schedule, and cost. The Project Manager needs to determine what to do first. What is the correct step to take?
a)
Begin the change request process
b)
Initiate mitigation of the risk
c)
Escalate the issue to senior management
d)
Ensure the project management plan is updated
33.
A deliverable on the project's critical path is lagging behind schedule. The cost performance index (CPI) is 1.3. The Project Manager can put the project back on schedule. Which of the following is the most likely outcome for the project?
a)
There will be activities performed in parallel
b)
There will be rework
c)
There will be a revised scope
d)
There will be an increase in costs and risks
34.
A project that should have been 90 per cent complete by now is only 65 per cent complete. The total project budget is US$120,000, and the actual cost spent to date (AC) is US$80,000. What is the scheduled performance index (SPI) and cost performance index (CPI) of this project?
a)
The SPI is 1.38, and the CPI is 1.2
b)
The SPI is 0.72, and the CPI is 0.98
c)
The SPI is 0.80, and the CPI is 0.91
d)
The SPI is 0.94, and the CPI is 1.04
35.
An intricate project has key stakeholders located in the United States, France, and China. The Project Manager discovers that a senior manager asked a team member for project information. Which step is appropriate to take next?
a)
Rely on the information in the stakeholder register
b)
Refer to the project management information system (PMIS)
c)
Ensure that the senior manager attends the next team meeting
d)
Read the communications management plan
36.
A Project Manager is working with a customer who repeatedly submits requests for new requirements for an existing software product. The Project Manager has already provided the completed scope definition for the product's next version release to stakeholders. Which step is appropriate for the Project Manager to take next?
a)
Hold a meeting with the product manager to request that the number of new requests be reduced
b)
Define project boundaries immediately with the sponsor
c)
Organize a meeting with the stakeholders to set expectations
d)
Analyze the scope management plan to see how changes in scope are handled
37.
A project is seven months into an execution. A Project Manager determines that the cost performance index (CPI) is .80. According to a trend analysis, the CPI has a downward trend. What is the next step that the Project Manager should take?
a)
Issue a change request for cost re-baselining
b)
Ask for additional resources
c)
Crash the project schedule
d)
Utilize the management reserve
38.
A project is being implemented. The research and development department communicate to the Project Manager that the product's requirements have changed. These changes were not anticipated, may significantly influence potential sales numbers, and could impact project scope. What is the appropriate action for the Project Manager to take?
a)
Update the risk register accordingly and identify risk responses
b)
Use forecasting methods
c)
Plan to use the contingency reserve and update the risk mitigation plan
d)
Utilize methods such as earned value management (EVM)
39.
A project has the following characteristics: I. US$3 million budget II. Planned value of US$630,000 III. Actual cost of US$650,000 IV. Earned value of US$540,000 Which statement is true about the current status of the project?
a)
The project is ahead of schedule and under budget
b)
The project is behind schedule and over budget
c)
The project is ahead of schedule and over budget
d)
The project is behind schedule and under budget
40.
A project is in the execution stage. Due to a demand to complete the project quickly, the Project Manager needs to rapidly allocate resources to establish the team and meet project requirements. Which action should the Project Manager take next?
a)
Build library services
b)
Deliver workshops
c)
Acquire and train the new team
d)
Host a webinar
41.
A Project Manager leaves the company and is replaced. The new Project Manager wants to start guiding the team toward project success. What should the new Project Manager do first?
a)
Look over the project charter to identify goals and deliverables
b)
Review the project diary and look for notes made by the former Project Manager
c)
Modify the project schedule, adding a new activity related to the knowledge transfer process
d)
Revisit the project budget to determine if extra time is required
42.
A Project Manager receives the following for a new project: I. Assumptions II. Restrictions III. Preliminary scope After receiving this information, what should the Project Manager do first?
a)
Review and understand the business case and project goals
b)
Put together the project team and assign project tasks
c)
Build the project schedule and determine the critical path
d)
Ensure project charter approval is obtained from the sponsor
43.
A Project Manager joins a project that has the following features: I. Globally distributed team II. Budget that is fixed III. Very tight deadlines During planning, what should the Project Manager do to avoid any scope creep and keep the team focused on delivering a product that meets requirements?
a)
Ask that all development team leads prepare detailed requirements
b)
Hold daily stand-ups with all development teams
c)
Put any changes to scope through the formal approval process
d)
Disallow stakeholders from directly interacting with the development team leads
44.
A project is delayed. To obtain the desired quality level of the deliverables, a change is required. First, the Project Manager issues a formal change request and communicates the change to all stakeholders. Then, the Project Manager learns that this communications approach did not meet stakeholders' expectations. What should the Project Manager do next?
a)
Refer to the communications management and stakeholder engagement plans
b)
Provide a change request to include stakeholders' expectations in the project management plan
c)
Organize a meeting with the project sponsor to better understand stakeholders' expectations
d)
Review the communications management plan, follow it, and issue a status report
45.
The project sponsor requests the Project Manager to change production materials because these materials could cause health problems to consumers. Which of the following is an appropriate step for the Project Manager to take?
a)
Follow the perform integrated change control process and thoroughly investigate the matter
b)
Immediately implement the change and submit a change request for formal documentation
c)
End the current work and enact the change control process
d)
Reject the change because the request is outside of scope