NEW
Font size
WorksheetsPMI BC Quiz 1
Total questions: 45
Worksheet time: 45mins
A customer is considering appending new features to the project deliverable. Before a project team member begins working on these new features, which is a mandatory step?
Gain approval from the Project Manager
Gain approval from the Project Sponsor
Ensure the change control board (CCB) approves
Ensure key subject matter experts (SMEs) approve
A project is at the planning stage of the project. The Project Manager realizes that producing a complicated multi-functional application is not feasible with the current resources and decides to hire more resources to produce the application. The Project Manager identifies and contracts short-term resources. Which of the following risk response strategy represent this scenario?
Mitigate
Transfer
Accept
Avoid
A Project Manager has performed the following steps:
I. Finished a major IT deployment project.
II. Confirmed with the release manager that all systems are working.
III. Confirmed that functionality has been verified by the quality assurance team.
IV. Informed the customer.
Which of the following is the next step the Project Manager should take?
Update the risk register, stakeholders, and team members
Add the lessons learned to the organization knowledge base
Ensure that the procurement plan is closed out
Review, verify, and complete the release documentation
mandatory Start-to-start (SS)
the default relationship Finish-to-start (FS)
very rarely used Start-to-finish (SF)
No inference given but it can be Finish-to-finish (FF)
