1.
A project manager is about to close a project that missed its performance goals. The project manager is gathering the information that is most pertinent to the project’s poor performance. Which of the following is least likely to help in this task?
a)
Risk report
b)
Project team assignments
c)
Assumption log
d)
Change log
2.
A project manager has taken over a project early in its execution. The company has a policy that specifies the minimum frequency for conducting risk audits on all projects. What should the project manager do to determine the timing of the risk audits for this particular project?
a)
Look in the project management plan
b)
Check the applicable policy in the organizational process assets
c)
Review the risk register for risk audit information
d)
Use discretion to determine when and if a risk audit is needed
3.
As part of project planning, a team member is using the resource breakdown structure and RACI chart. What process would benefit the most from these techniques?
a)
Control Costs
b)
Plan Resource Management
c)
Identify Stakeholders
d)
Manage Project Knowledge
4.
While updating the monthly cost reports, you have discovered that an error was made in the original funding request. As a result, the budgeted amount approved was higher than the project actually needed. You understand that the cost baseline should be updated. What should you do next?
a)
Issue a change request
b)
Update the cost baseline
c)
Prepare cost estimates
d)
Issue work performance reports
5.
The project manager and members of the project team start an Ishikawa diagram for a quality issue. Someone writes down 'source material' as a potential cause. What is the next best action for the project manager?
a)
Instruct the production department to stop using the source material
b)
Request the team to brainstorm other possible causes of the quality issue
c)
Suggest switching from the Ishikawa diagram to the cause-and-effect diagram
d)
Direct the team to focus on issues from the customer perspective of quality
6.
A project team is testing a prototype of a new drone. Something goes wrong and causes the drone to crash and explode.Fortunately, this risk has been identified early in the project, and the contingency reserves allocated for the risk are sufficient to construct another prototype. What should the project manager do next?
a)
Submit a change request to update the cost baseline
b)
Use the contingency reserves to construct a new prototype
c)
Submit a change request to tap into the contingency reserves
d)
Terminate the project since the only prototype was destroyed
7.
A project sponsor asks the project manager how well the project is doing in terms of budget. The project manager reviews work performance data and informs the sponsor that the project is doing well. What is wrong with the project manager's approach?
a)
Nothing is wrong with the project manager's approach.
b)
The project manager should have reviewed work performance information.
c)
The project manager should have reviewed the cost baseline.
d)
The project manager should have consulted the accounting department.
8.
The sponsor asked the project manager to share the project progress and recommunicate project objectives to the stakeholders. After reviewing the communications management plan and the stakeholder engagement plan, the project manager decides that a presentation at the upcoming project status meeting would be the best way to share the information. The presentation is well received with a lot of positive feedback. Which of the following should the project manager update?
a)
Project communications log
b)
Organizational process assets
c)
Communications management plan
d)
Stakeholder engagement plan
9.
A supplier that the project is using to subcontract some of the project work has delivered all the contracted work. Which value does the project manager attribute to the accepted deliverable?
a)
Net present value
b)
Earned value
c)
Accepted value
d)
Planned value
10.
A project manager is in the process of analyzing activity sequences, durations, resource requirements, and schedule constraints. What would be the most likely outcome of this process?
a)
Schedule register
b)
Assumption log
c)
Schedule model
d)
Stakeholder register
11.
You are one of several project managers working for a construction company, and you are obtaining the equipment and supplies for a project to build a new convention center. The performing organization owns much of the construction equipment, which must be reserved in advance per company policy. Once you have confirmed the equipment's availability for your project, what should you do to ensure the equipment is available when you need it?
a)
Revise the resource requirements documentation
b)
Reserve the equipment by updating the organizational process assets
c)
Modify the project schedule with the required equipment
d)
Record the equipment in the resource breakdown structure
12.
As a project manager, you are in the process of working with the project stakeholders to foster the appropriate level of stakeholder involvement. Which activity are you least likely to perform in support of this process?
a)
Clarifying and resolving issues that have been identified by the stakeholders
b)
Developing a matrix that compares current and desired stakeholder engagement levels
c)
Addressing any risks or potential concerns related to stakeholder engagement
d)
Managing stakeholder expectations through negotiation and communication
13.
The project is falling behind schedule and is over budget. Nonetheless, there is pressure from the project sponsor to complete the project as planned. You must determine what the project’s performance must be from this point onwards to achieve the delivery goals. Which calculation are you most likely to use?
a)
SPI
b)
TCPI
c)
SV
d)
BAC
14.
As the agile project progresses, it becomes evident that the user stories are not sufficiently tested. At the iteration retrospective meeting, the team conducts a why-why analysis and determines the root cause of the issue. Which of the following was the most likely root cause found by the team?
a)
Vague project scope
b)
Lack of tacit knowledge
c)
Incomplete definition of done
d)
Poor osmotic communication
15.
A key team member has left the project, and the planned risk response is implemented by replacing the team member with an individual that is very capable and highly productive. However, the project manager now feels there is a risk that the productivity of the team may suffer as a result of not having an established working relationship with the replacement team member. This new risk is an example of which type of risk?
a)
Residual risk
b)
Risk enhancement
c)
Secondary risk
d)
Reserve risk
16.
A project manager is in the process of implementing the communications management plan for a project to construct a new hydroelectric plant. The performing organization is based in the United States, and the hydroelectric plant will be built in a remote region of Brazil. As it relates to project communications, which of the following tailoring considerations is the least relevant?
a)
Physical location
b)
Language
c)
Communication technology
d)
Policy compliance and auditing
17.
You are managing a project that is currently in the closing stage. You want to confirm that all deliverables were accepted,validate that the exit criteria have been met, evaluate the satisfaction of stakeholders, and gather lesson learned. What should you do?
a)
Conduct data analysis
b)
Obtain expert judgment
c)
Hold meetings
d)
Validate scope
18.
You are the project manager who is in the process of preparing the project planning documents. As you gather data, you want to be as thorough as possible given the vast scope of the project. Therefore, you want to use a standardized list of items to be considered during this process. What should you do to find this information?
a)
Check the lessons learned repository
b)
Consult the project management plan
c)
Check the organizational process assets
d)
Review the scope baseline
19.
You were recently hired by an electrical engineering firm to take over as the project manager for the installation of backup generators in a religious community. When reviewing the project schedule, you notice that several holidays that are observed by the community were not accounted for. What would be the first project document that you would add the community's observed holidays to as non-working days?
a)
Master schedule
b)
Project calendar
c)
Duration estimates
d)
Resource calendar
20.
A company has authorized a dedicated change control board (CCB) to review and evaluate all change requests that are submitted for any project. If the project sponsor is a member of the CCB, which of the following best describes an individual or group that can request a change on a project?
a)
Project manager
b)
Project sponsor
c)
Project team
d)
Any stakeholder