1.

Which of the following is not a stakeholder in a financial project?

a)

Someone opposed to the project

b)

Project manager

c)

Someone who is not interested in the project

d)

Project sponsor

2.

Your company has entered into a contract to develop a new and improved website for another company. The contract specifies the major deliverables, with details about what the website will contain, the completion date, and budget. The appendix contains the change control procedures that will be used. What project life cycle should be used to deliver this project?

a)

Predictive

b)

Agile

c)

Hybrid

d)

Scrum

3.

An organization is exploring a new project with many unknowns, and most of the work to be done is designing software to build the best solution in collaboration with the customer. Which project management approach is best suited for this project?

a)

Agile

b)

Plan-driven

c)

Phased

d)

Predictive

4.

Which two of the following should be included in a project charter? (Choose two)

a)

Measurable objectives

b)

Detailed deliverables list

c)

Key stakeholders list

d)

Change request form