1.

While performing RFI ( Request for Inspection), Site Execution teams shall inform to planning team on daily basis for intended next day work consisting location, Activity, Time by __ of the same day

a)

3:00PM

b)

6:00PM

c)

5:00PM

d)

12:00PM

2.

While fixing Road alignment, internal calibration shall be carried out every

a)

1 Week

b)

1 Month

c)

Once

d)

Daily

3.

Clearing is defined as removing and disposing of all unwanted surface material, such as trees, brush, grass, weeds, downed trees, and other material. Grubbing is defined as removing and disposing of all unwanted vegetative matter from underground, such as stumps, roots, buried logs, and other debris.

Question: Grubbing is done for the maximum girth of

a)

100MM

b)

150MM

c)

300MM

d)

250MM

4.

The maximum depth of ground clearing the top soil is up to

a)

50MM

b)

100MM

c)

150MM

d)

200MM

5.

Original Ground level (OGL)

means the level of the ground that existed before any excavation for new buildings or structures on the land is undertaken.

Question: OGL will be taken after

a)

Clearing and Grubbing and Compaction.

b)

only Compaction

c)

Only Clearing

d)

Only grubbing

6.

Before commencing the earthwork, we need to mark

a)

Row Line

b)

Center Line

c)

Toe Line

d)

Boundary Line

7.

The soil in earthwork should be compacted up to ____ of lab MDD.

a)

60%

b)

95%

c)

70%

d)

90%

8.

Every 4th layer of Embankment shall be checked w.r.t. Toe width & level at interval of every

a)

10 Mtr

b)

20 Mtr

c)

30 Mtr

d)

Not required

9.

Clods and hard lumps of earth will be broken to a maximum size of _____ for embankment.

a)

75MM

b)

50MM

c)

100MM

d)

Not required

10.

Optimum Moisture Content (OMC)

is the water content at which the soil attains maximum dry density.

Question: The Moisture content to be maintained in earthwork during compaction should be

a)

+.5% to -1%

b)

+1 % to -.5%

c)

+1 to -2%

d)

upto 2 %

11.

During earthwork in subgrade, roller should overlap ___ of the preceding pass.

a)

1/4

b)

1/2

c)

1

d)

1/3

12.

In medians, the top most layers shall be compacted lightly in order to facilitate sufficient growth of roots of grass and plants/shrubs.

a)

True

b)

False

13.

During construction of GSB, GSB layer shall be constructed on the

a)

Embankment Top Layer

b)

Sub Grade Top Layer

c)

WMM Top Layer

d)

None of the above

14.

Camber in Road, refers to the curvature or slope provided to the surface of a road or any other paved surface. It is designed to ensure proper drainage of water from the road surface.

Question: Camber is checked & corrected...

a)

After final rolling

b)

Before final rolling

c)

during compaction test

d)

before compaction test

15.

Speed of the roller shall be maintained uniformly during rolling. What is maximum limit to check?

a)

Not Exceeding 3km/hr

b)

Not Exceeding 4km/hr

c)

Not Exceeding 5km/hr

d)

Not Exceeding 1km/hr

16.

The tolerance on the surface level of GSB shall be

a)

+/-10MM

b)

+/-5MM

c)

+/-2MM

d)

None of the above

17.

WMM: Wet Mix Macadam, It is composed of crushed aggregates, including gravel and stone dust, mixed with water and a binding agent such as bitumen emulsion or cement

Question: During compaction of WMM, the compaction should be more than

a)

95%

b)

70%

c)

98%

d)

92%

18.

Prime Coat & Tack Coat shall comply with IS

a)

8881

b)

882

c)

8881

d)

8887

19.

Prime Coat is the application of a suitable bituminous binder applied to a non-bituminous granular base as a preliminary treatment before the application of a bituminous surfacing.

Tack coat is a sprayed application of an asphalt binder upon an existing asphalt or Portland cement concrete pavement prior to an overlay, or between layers of new asphalt concrete.

Question: Prime Coat is spray application of a single coat low viscosity, low porous bituminous material over wet mix macadam granular surface at the rate of

a)

0.5-1.0 kg per Sqm

b)

0.1-1.5 kg per Sqm

c)

0.7-1.0 kg per Sqm

d)

0.5-2.0 kg per Sqm

20.

The design of PQC should be based on

a)

Compressive Strength

b)

Tensile Strength

c)

Flexural Strength

d)

None of the above