wayground logo

Free Printable Worksheets

Font size

S
M
L
XL
Worksheets

pre finals

Total questions: 111

Worksheet time: 2hrs 36mins

Name
Class
Date
1.

The privilege of someone to pass over land belonging to someone else; A narrow length of land used for the route of a railroad, electric power line, or public road

(a)  

2.

A mechanical switching device used for changing the connections in a circuit, or for isolating a circuit or equipment from the source of power

(a)  

3.

  1. A device that protects the transformer from internal fault



(a)  

4.

The distance between two adjacent poles that support conductors used in the electric system, usually in meters

(a)  

5.

  1. A device that closes and interrupts (opens) an electric circuit between separable contacts under both load and fault conditions



(a)  

6.

  1. What is the change-out loading of a distribution transformer?



(a)  

7.

What is the size of underground cable for main lines?

(a)  

8.

What is the lowest kVA rating of Meralco’s Distribution Transformer?

(a)  

9.

Highest rating (capacity) for overhead distribution transformer?

(a)  

10.

List at least 5 hardware, equipment and devices shown in the figure above

(a)  

11.

Name at least 3 offices under Network Planning & Design

(a)  

12.

Standard primary conductor for main/feeder line

(a)  

13.

In transformers, prefix “W” stands for what primary voltage

(a)  

14.

In transformers, suffix “B” stands for what secondary voltage

(a)  

15.

What does OSA stand for?

(a)  

16.

What does PCA stand for?

(a)  

17.

Name at least two PCA types

(a)  

18.

Provide 3 Reasons for Adopting UG Distribution/advantage

(a)  

19.

Provide 3 Disadvantages of UG system

(a)  

20.

Provide 4 UG Equipment’s/Materials used

(a)  

21.



(a)  

22.



(a)  

23.



(a)  

24.



(a)  

25.



(a)  

26.

Mechanical switching device used to change the connection of a circuit or isolate a circuit or equipment from the power source.

a)

Circuit Breaker

b)

Power Transformer

c)

Capacitor Banks

d)

Potential Transformer

e)

Disconnect Switch

27.

A device that transfers electrical energy from one circuit to another through inductively coupled conductors. It is used to covert between high and low voltages

a)

Circuit Breaker

b)

Power Transformer

c)

Capacitor Banks

d)

 Potential Transformer

28.

Device installed in substations in order to improve the power factor and voltage regulation. It also supplies kilovars to transmission and distribution system.

a)

Switchgear

b)

Potential Transformer

c)

Surge Arresters

d)

Capacitor Banks

29.

This is combination of electrical devices, fuses and/or circuit breakers used to protect the different distribution facilities.

a)

Switchgear

b)

Potential Transformer

c)

Surge Arresters

d)

Protection Relays

30.

Protective device against transient overvoltage that may cause flashover and serious damage to equipment.

a)

Switchgear

b)

Potential Trasformer

c)

Surge Arresters

d)

Capacitor Banks

31.

This is a kind of tripping where the primary and secondary breaker of a power transformer tripped.

a)

Transformer Differential Tripping

b)

Feeder or Circuit Tripping

c)

Bus Differential Tripping

d)

Capacitor Bank Tripping


32.

The personnel/office that gives clearance before any personnel can work on substation, subtransmission and distribution facility

a)

Substation Office

b)

System Operation/Delta

c)

Power System Protecion

d)

SCADA Office

33.

Enumerate the list of equipment



(a)  

34.

List the 4 types of power circuit breakers used in power substations

(a)  

35.

  1. List at least five (5) parts of a power transformer



(a)  

36.

A microprocessor controlled electronic device which interfaces objects in the physical world to a distributed control system or SCADA system by transmitting telemetry data to the system and/or altering the state of connected objects based on control messages received from the system.

(a)  

37.

Temporarily disables control from the Master Station

(a)  

38.

T/F: While energized, Meter IED current inputs should not be open while voltage inputs should not be shorted.

(a)  

39.

The DNP 3.0 architecture used for Substation RTUs.

(a)  

40.

The two main components of integrity poll are (a)   .

41.

The two types of communication network currently used in SAS.

(a)  

42.

  1. This device enables non-PRP or non-HSR equipment to connect to the SAS communication network. 



(a)  

43.

It interconnects all bays of the Substation Automation System with the station supervisory level and carries control in sequence such as measurement, interlocking and operations.

(a)  

44.

  1. Facilitates conversion of standard or proprietary protocol of one device to the protocol

suitable for the other device or tools to achieve the desired interoperability.



(a)  

45.

It is a communication standard developed recently in cooperation with manufacturers and users to create a uniform, future-proof basis for protection, control and automation of substations.

(a)  

46.
  1. Meralco absorbs Meralco absorbs around __% of generated power in the entire country.

a)

50

b)

55

c)

52

d)

53

e)

54

47.
  1. The Meralco distribution system is mostly 

a)

underground line

b)

looped line

c)

radial line

d)

sectorized line

e)

none of the above

48.

The voltage level of Meralco’s sub-transmission network is mostly

(a)  

49.

Paco Delivery point substation belongs to

(a)  

50.

Red Alert notice is being given by the System Operator when:

a)

Sector 1

b)

Sector 2

c)

Sector 3

d)

Laguna Sector

e)

Manila Sector

51.

Red Alert notice is being given by the System Operator when:

a)

Contingency reserve is zero

b)

Generation deficiency exist

c)

There is critical loading

d)

Imminent overloading of transmission lines or equipment

e)

 all of the above

52.

In Meralco, ILP means

a)

Information Leak Prevention

b)

Inner Line Permit

c)

 Independent Labor Party

d)

 Interruptible Load Program

e)

Individual Learning Plan

53.

SIPS means

(a)  

54.

The allowable deviation in system frequency is

(a)  

55.

A power transformer loading is considered normal if less than (a)   % of its rating

56.

The Automatic Load Dropping (ALD) instantaneous setting will kick in at (a)   Hz

57.

  1. T/F: All Delivery Point substations serving Meralco franchise is owned by National Grid Corporation of the Philippines (NGCP)



(a)  

58.

T/F: Meralco absorbs around 70% of the total generated power in Luzon

(a)  

59.

  1. T/F: All Meralco’s Sub-Transmission Lines are looped system



(a)  

60.

T/F: The system is in Yellow Alert if the contingency reserve is less than the capacity of the largest synchronized generating unit

(a)  

61.

  1. T/F: The Tetra Communication System is one of the tools used in system monitoring and control.



(a)  

62.

T/F: PSS/E stands for Power System Simulators for Engineers

(a)  

63.

T/F: The Operations Planning of SCC handles the real time monitoring and control of Meralco’s electric facilities.

(a)  

64.

T/F: MLD stands for Manual Load Device.

(a)  

65.

T/F: The ILP is a brainchild of Energy Regulatory Commission (ERC).

(a)  

66.

Which among the following pain points can be attributed to data gap?

a)

 Ownership of equipment data is unclear

b)

 Low asset data quality [both physical asset register (PAR) and fixed asset register (FAR)]

c)

Highly customized & disparate information systems operating on aging mainframe platform

d)

 All of the above


67.

Which open standard adapted by ADMS shows how managed elements shall be represented as a set of objects and its relationship?

a)

 Common Information Model

b)

PAS 55 Standard

c)

Global ID – CIM Mapping

d)

 IEC 61850

68.

What are the major hurdles in unlocking Meralco’s Smart Grid?

(a)  

69.
  1. Which of the following data tuning efforts are necessary before we could use advance ADMS applications? 

a)

Equipment Parameter Modelling (Conductor, Transformer, Substation, DG, etc.)

b)

Address Load Related Anomalies (Connectivity, Phasing, Load Group Assignment, etc.)

c)

Telemetry Quality Checks (Signal Attributes, Signal Availability, Signal Accuracy, etc.)

d)

All of the above

70.

The spatial system that will enhance design, construction, service application, O&M processes to keep up with the evolving electric distribution process and technology landscape?

a)

EAM

b)

Enterprise GIS

c)

Enterprise Data Warehouse

d)

ADMS

71.

  1. Where do ADMS users generate report like the Daily Interruption Report, ERC Report, Crew Report, etc.? 



(a)  

72.
  1. Where does GIS data come from? 

a)

 As-Built Report

b)

As-Found Report

c)

Data Engineering

d)

All of the above

73.

What coordinate system defines the Earth as a two-dimensional coordinate system with angular unit?

(a)  

74.

Which among the following is an EAM Asset?

a)

Distribution Transformer

b)

Metering Center

c)

Substation Switchgear

d)

None of the above

75.

Which ADMS record is automatically created whenever a telemetered device from SCADA trips out?

(a)  

76.

How is a map data represented in GIS?

(a)  

77.

  1. The asset lifecycle meets the work order lifecycle during? 



(a)  

78.

What is MERALCO’s Corporate Mission?

a)

. To be a world class customer-centric energy services provider managing a resilient and intelligent network

b)

A world-class, customer centric energy service provider managing a resilient, sustainable, and intelligent network by 2025

c)

To provide safe, reliable, and digitally-enabled energy services through strong partnerships, and highly-motivated and competent workforce

d)

To be an agile, innovative and technology-driven organization committed in providing safe, reliable, adequate, and cost-efficient energy services to customers through a digitally-enabled network.

79.
  1. Meralco absorbs Meralco absorbs around __% of generated power in the entire country.

a)

50

b)

55

c)

52

d)

53

e)

54

80.
  1. The Meralco distribution system is mostly 

a)

underground line

b)

looped line

c)

radial line

d)

sectorized line

e)

none of the above

81.

The voltage level of Meralco’s sub-transmission network is mostly

(a)  

82.

Paco Delivery point substation belongs to

(a)  

83.

Red Alert notice is being given by the System Operator when:

a)

Sector 1

b)

Sector 2

c)

Sector 3

d)

Laguna Sector

e)

Manila Sector

84.

Red Alert notice is being given by the System Operator when:

a)

Contingency reserve is zero

b)

Generation deficiency exist

c)

There is critical loading

d)

Imminent overloading of transmission lines or equipment

e)

 all of the above

85.

In Meralco, ILP means

a)

Information Leak Prevention

b)

Inner Line Permit

c)

 Independent Labor Party

d)

 Interruptible Load Program

e)

Individual Learning Plan

86.

SIPS means

(a)  

87.

The allowable deviation in system frequency is

(a)  

88.

A power transformer loading is considered normal if less than (a)   % of its rating

89.

The Automatic Load Dropping (ALD) instantaneous setting will kick in at (a)   Hz

90.

  1. T/F: All Delivery Point substations serving Meralco franchise is owned by National Grid Corporation of the Philippines (NGCP)



(a)  

91.

T/F: Meralco absorbs around 70% of the total generated power in Luzon

(a)  

92.

  1. T/F: All Meralco’s Sub-Transmission Lines are looped system



(a)  

93.

T/F: The system is in Yellow Alert if the contingency reserve is less than the capacity of the largest synchronized generating unit

(a)  

94.

  1. T/F: The Tetra Communication System is one of the tools used in system monitoring and control.



(a)  

95.

T/F: PSS/E stands for Power System Simulators for Engineers

(a)  

96.

T/F: The Operations Planning of SCC handles the real time monitoring and control of Meralco’s electric facilities.

(a)  

97.

T/F: MLD stands for Manual Load Device.

(a)  

98.

T/F: The ILP is a brainchild of Energy Regulatory Commission (ERC).

(a)  

99.

Which among the following pain points can be attributed to data gap?

a)

 Ownership of equipment data is unclear

b)

 Low asset data quality [both physical asset register (PAR) and fixed asset register (FAR)]

c)

Highly customized & disparate information systems operating on aging mainframe platform

d)

 All of the above


100.

Which open standard adapted by ADMS shows how managed elements shall be represented as a set of objects and its relationship?

a)

 Common Information Model

b)

PAS 55 Standard

c)

Global ID – CIM Mapping

d)

 IEC 61850

101.

What are the major hurdles in unlocking Meralco’s Smart Grid?

(a)  

102.
  1. Which of the following data tuning efforts are necessary before we could use advance ADMS applications? 

a)

Equipment Parameter Modelling (Conductor, Transformer, Substation, DG, etc.)

b)

Address Load Related Anomalies (Connectivity, Phasing, Load Group Assignment, etc.)

c)

Telemetry Quality Checks (Signal Attributes, Signal Availability, Signal Accuracy, etc.)

d)

All of the above

103.

The spatial system that will enhance design, construction, service application, O&M processes to keep up with the evolving electric distribution process and technology landscape?

a)

EAM

b)

Enterprise GIS

c)

Enterprise Data Warehouse

d)

ADMS

104.

  1. Where do ADMS users generate report like the Daily Interruption Report, ERC Report, Crew Report, etc.? 



(a)  

105.
  1. Where does GIS data come from? 

a)

 As-Built Report

b)

As-Found Report

c)

Data Engineering

d)

All of the above

106.

What coordinate system defines the Earth as a two-dimensional coordinate system with angular unit?

(a)  

107.

Which among the following is an EAM Asset?

a)

Distribution Transformer

b)

Metering Center

c)

Substation Switchgear

d)

None of the above

108.

Which ADMS record is automatically created whenever a telemetered device from SCADA trips out?

(a)  

109.

How is a map data represented in GIS?

(a)  

110.

  1. The asset lifecycle meets the work order lifecycle during? 



(a)  

111.

What is MERALCO’s Corporate Mission?

a)

. To be a world class customer-centric energy services provider managing a resilient and intelligent network

b)

A world-class, customer centric energy service provider managing a resilient, sustainable, and intelligent network by 2025

c)

To provide safe, reliable, and digitally-enabled energy services through strong partnerships, and highly-motivated and competent workforce

d)

To be an agile, innovative and technology-driven organization committed in providing safe, reliable, adequate, and cost-efficient energy services to customers through a digitally-enabled network.