PM Skills for Life Training

Total questions: 15

Worksheet time: 8mins

Name
Class
Date
1.

What is the definition of a project?

a)

A long term endeavor to create a specific product, service or result

b)

A temporary endeavor to create a specific product, service or result

c)

short term endeavor to create a specific product, service or result

d)

A temporary endeavor to create a specific product

2.

Project management is:

a)


The centralized coordinated management of a program to achieve the program’s strategic objectives and benefits

b)


The application of information systems to manage in a coordinated way a group of related projects.

c)


The centralized coordination of operations and programs to achieve the program’s strategic objectives and benefits.

d)

The application of knowledge, skills, tools and techniques to project activities to meet the project requirements.

3.

The five project management process groups are:

a)

Initiate, plan, control, execute, close

b)


Define, design, deploy, evaluate, refine

c)

Design, measure, analyze, improve, control

d)


Initiate, plan, evaluate, execute, close

4.

  • Which of these is not an example of a project? 

a)


Buying clothes from the market on a special sale. 

b)

Planning for your friends wedding. 

c)

Building a bridge across the Amazon river. 

d)


Cleaning the office building every day. 

5.

You have completed your project delivery and currently are in the project closing process. You have started preparing the lessons learned document. What is the primary objective of the lessons learned document?

a)

Continuous improvement

b)

Risk audit

c)

Quality audit

d)

Process analysis

6.

To formally authorize the project, which of the following documents is necessary?

a)

Business case

b)

Project charter

c)

Project contract

7.

What is the critical path in a project network diagram?

a)

The path that requires the most resources

b)

The shortest path to complete the project

c)

The path with the highest priority tasks

d)

The longest path that determines the project’s duration

8.

The Project Management Triangle consists of which three constraints?

a)

Time, Cost, Quality

b)

Scope, Risk, Stakeholders

c)

Resources, Communication, Planning

d)

Objectives, Deliverables, Team

9.

What is the purpose of a lessons learned report in project management?

a)

To document risks encountered during the project

b)

To highlight the achievements of the project team

c)

To provide recommendations for improving future projects

d)

To analyze the financial performance of the project

10.

What does WBS stand for in project management?

a)

Work Breakdown System

b)

Workflow Building Strategy

c)

Workforce Budgeting System

d)

Work Breakdown Structure

11.

Which project management phase involves breaking down project deliverables into smaller, manageable components?

a)

Initiation

b)

Planning

c)

Execution

d)

Closing

12.

What is the primary goal of project management?

a)

Maximizing profits

b)

Minimizing risks

c)

Completing projects successfully

d)

Implementing new technologies

13.

A project manager is responsible for:

a)

a) Performing all project tasks personally

b)

b) Managing project resources and stakeholders

c)

c) Assigning tasks only to team members

d)

d) Reporting to the project sponsor only

14.

PMI provides globally recognized standards and best practices for:

a)

a) Human Resource Management

b)

b) Project Management

c)

c) Financial Management

d)

d) Marketing Management

15.

What does PMI stand for?

a)

a) Project Management International

b)

b) Professional Management Institute

c)

c) Project Management Institute

d)

d) Program Management Institute