Worksheets01 Push vs Pull System Quiz
Total questions: 7
Worksheet time: 4mins
Which system assumes all work will take as long as allowed with no defective parts ever built?
Push System
Pull System
Hybrid System
Lean System
In which system does the receiving workstation not accept any defective parts?
Push System
Lean System
Pull System
Hybrid System
What is a main identifier of pull systems in production cycles?
Total Quality Management
Just-in-Time inventory
KANBAN methods
Six Sigma principles
Which system creates only the parts requested from a downstream workstation?
Lean System
Pull System
Push System
Hybrid System
What is the aim of having a visual aid like KANBAN in pull systems?
To increase lead times
To reduce costs
To confuse workers
To slow down production
In which system does everyone's work get triggered by required start dates?
Push System
Pull System
Hybrid System
Lean System
Which system is based on customer demand and aims to reduce stock levels?
Push System
Lean System
Pull System
Hybrid System