WorksheetsRecap Quiz (Project Contract Management)
Total questions: 33
Worksheet time: 23mins
Department Order stating that PDM shall be used.
DO 133, S. 2015
DO 133, S. 2016
DO 133, S. 2017
DO 133, S. 2018
It is a tabulation of the number of units, capacity and type of equipment which are required in each month of contract duration.
Manpower Deployment Schedule
Equipment Utilization Schedule
Manpower Allocation
Equipment Allocation
_______ is predicted / projected / correlated from cumulative monthly target accomplishment in percent along the duration of the project. Inflow and outflow of cash maybe developed below the bar chart presentation.
S-Curve
Accumulative Flow
Cash Flow
None of the Above
The amount of time whereby a successor activity is required to be delayed with respect to a predecessor activity.
Lag
Lead
Both A and C
None of the Above
The amount of time whereby a successor activity can be advanced with respect to a predecessor activity.
Lag
Lead
Both A and C
None of the Above
A critical path method technique for calculating the early start and early finish dates by working forward through the schedule model from the project start.
Back Pass
Backward Pass
None of the Above
Forward Pass
A simple visual diagram that represents each activity in the form of horizontal bars which are laid out in a time scaled chart. The completed portions are usually shaded / darkened, to depict activity completion.
Bar Chart
Pie Chart
Graph Chart
None of the Above
A critical path method technique for calculating the late start and late finish dates by working backward through the schedule model from the project end date.
Back Pass
Backward Pass
None of the Above
Forward Pass
The amount of time a scheduled activity may either be delayed or extended from its early start date without delaying the project finish date.
Float
Dummy
Both A and B
None of the Above
A logical relationship in which a successor activity cannot start until a predecessor activity has started.
Start to Start
Start to Finish
Finish to Start
Finish to Finish
A logical relationship in which a successor activity cannot finish until a predecessor activity has started.
Start to Start
Start to Finish
Finish to Start
Finish to Finish
A logical relationship in which a successor activity cannot start until a predecessor activity has finished.
Start to Start
Start to Finish
Finish to Start
Finish to Finish
A logical relationship in which a successor activity cannot finish until a predecessor activity has finished.
Start to Start
Start to Finish
Finish to Start
Finish to Finish
Once a month, the contractor may submit a statement of work accomplished (SWA) or progress billing and corresponding request for the progress payment for work accomplished.
Mobilization / Advance Payment
Progress / Payments
Release of Retention
Final Billing
The preparation of the proposed Variation Order will be the:
Project Engineer of the Contractor
Project Engineer of the DPWH
Section / Division Chief of the Implementing Office
Head of Implementing Office
What department order stated the requirements for issuance of Certificate of Completion and Certificate of Acceptance for Infrastructure Contracts.
Department Order No. 98, Series 2015
Department Order No. 99, Series 2015
Department Order No. 100, Series 2015
Department Order No. 101, Series 2015
Upon receipt of notice from the contractor that the project is completed, the Head of the Implementing Office shall instruct its Inspectorate Team to conduct an inspection of the project and to submit its Completion Inspection Report within,
Ten (10) days
Fifteen (15) days
Twenty (20) days
Twelve (12) days
Upon receipt of advice from the contractor that the defects and deficiencies indicated in the said Notice have been corrected, the Head of the Implementing Office shall instruct the Inspectorate Team to conduct an Inspection of the project and to submit its Completion Inspection Report within,
Five (5) days
Seven (7) days
Nine (9) days
Ten (10) days
What Department Order stated the Approval of Work Suspension Order, Work Resumption Order, and Contract Time Extension for Civil Works Projects?
Department Order No. 117, Series 2023
Department Order No. 46, Series 2022
Department Order No. 11, Series 2021
Department Order No. 39, Series 2024
A standard form in Project Implementation involving the summary of Contractors Accomplishment during a particular period, usually a month, showing quantities of work done on each contract pay item, the unit cost of such work item and the total cost of such work done during the month.
Standard Project Logbook
Site Instruction
Statement of Work Accomplished
Itemized Cost of Revision
Is a written authority issued by the Implementing Office granting the contractor additional time beyond the approved completion date in order to carry out additional work or on account of other special circumstances that warrant such additional contract time.
Work Suspension Order
Variation Order
Work Resumption Order
Contract Time Extension
Issued by the Implementing Official to cover the introduction of new work necessary for the completion, improvement or protection of the project which was not included as items of work in the original contract.
Extra Work Order
Change Order
As - Staked Plan
Certificate of Availability of Funds
In claiming for any Variation Order, the contractor shall, within ____ calendar days after such work has been commenced pursuant to Item 3.2 hereof; or, within ______ calendar days after the circumstances or reasons justifying a claim for extra cost shall have occurred, deliver a notice giving full and detailed particulars of any extra cost in order that it may be investigated at that time. What is X and Y?
15 and 7
7 and 28
7 and 30
15 and 30
The following are the activities under Pre - Construction Stage, except;
Familiarization of Approved Plans, Specification and Contract Documents
Conduct Joint As - Staked Survey
Conduct Parcellary Survey
Conduct Pre - Construction Conference
Department Order on Contracts with Negative Slippage in Accordance with the Revised IRR of RA 9184.
Department Order No. 66, Series 2017
Department Order No. 193, Series 2016
Department Order No. 28, Series 2015
Department Order No. 125, Series 2015
Involves watching the progress of a project performance schedules during the execution of the project and identifying lagging areas requiring timely attention and action. It is the periodic checking of progress of works against the targets laid down in order to ensure timely completion of the project.
Project Control
Project Monitoring
Field Documentation
Construction Logbook
It is the first official meeting between the contractor, the assigned DPWH Field Engineers in the project, and the end user of the project (if any) and other concerned stakeholders.
Coordination Meeting
Joint As - Staked Survey
Pre - Construction Meeting
Technical Meeting
Department Order on the Revised Guidelines on the Installation of Project Billboards.
Department Order No. 11, Series 2021
Department Order No. 11, Series 2022
Department Order No. 46, Series 2022
Department Order No. 117, Series 2023
Is best described as the deployment of resources at the project site. This also involves any work that is necessary to provide access to the site.
Construction Phase
Mobilization
Completion
Monitoring
It is an activity necessary to verify the actual field condition and to identify modifications and other deviations in the project (such as change in road alignment, change and / or addition of new items of work, etc.)
As - Staked Survey
Road Right of Way Assessment
Pre - Construction Phase
Construction Phase
Department Order on the Administrative Action on Contracts with Negative Slippage in Accordance with the Revised IRR of RA 9184.
Department Order No. 28, Series 2015
Department Order No. 66, Series 2017
Department Order No. 100, Series 2015
Department Order No. 193, Series 2016
Issued by the Head of Implementing Office after the one - year defects liability period, after all defects / deficiencies, if any shall have been repaired by the contractor to the satisfaction of the same Inspectorate Team and upon submission of the Warranty Certificate by the Contractor.
Certificate of Completion
Certificate of Acceptance
Liquidated Damages
Certificate of Inspection
The contractor shall cause the extension of the validity of the Performance Security to cover the additional contract time due to VO so that it will be coterminous with the issuance of the Certificate of Final Acceptance. True or False?
True
False